VANCOUVER, BC, Feb. 9, 2023
/PRNewswire/ - Silvercorp Metals Inc. ("Silvercorp" or the
"Company") (TSX: SVM) (NYSE American: SVM) reported its financial
and operating results for the three months ended December 31, 2022 ("Q3 Fiscal 2023"). All amounts
are expressed in US dollars, and figures may not add due to
rounding.
HIGHLIGHTS FOR Q3 FISCAL
2023
- Mined 296,050 tonnes of ore, milled 303,442 tonnes of ore, and
produced approximately 1.9 million ounces of silver, 1,100 ounces
of gold, 20.1 million pounds of lead, and 7.0 million pounds of
zinc;
- Sold approximately 1.9 million ounces of silver, 1,100 ounces
of gold, 19.3 million pounds of lead, and 7.1 million pounds of
zinc, for revenue of $58.7
million;
- Realized adjusted earnings attributable to equity holders of
$11.8 million, or $0.07 per share. The adjustments were made to
remove impacts from impairment charges, share-based compensation,
foreign exchange, mark-to-market equity investments, and the share
of associates' operating results;
- Reported net income attributable to equity holders of
$11.9 million, or $0.07 per share;
- Generated cash flow from operating activities of $25.7 million;
- Cash costs per ounce of silver, net of by-product credits, of
negative $1.15;
- All-in sustaining costs per ounce of silver, net of by-product
credits, of $9.28;
- Spent and capitalized $1.4
million on exploration drilling, $9.0
million on underground development, and $2.8 million on construction of the new mill and
tailings storage facility;
- Strong balance sheet with $210.3
million in cash and cash equivalents and short-term
investments. The Company holds a further portfolio of equity
investments in associates and other companies with a total market
value of $121.8 million as at
December 31, 2022.
FISCAL 2024
PRODUCTION GUIDANCE
- To mine and process 1,100,000 to 1,170,000 tonnes of ores,
yielding approximately 4,400 to 5,500 ounces of gold, 6.8 to 7.2
million ounces of silver, 70.5 to 73.8 million pounds of lead, and
27.7 to 29.7 million pounds of zinc.
- The guidance represents a production increase of approximately
3% to 8% in ores, 1% to 26% in gold, 3% to 8% in silver, 3% to 8%
in lead, and 14% to 23% in zinc compared to the expected production
results in Fiscal 2023.
CONSOLIDATED FINANCIAL RESULTS
Net income attributable to equity holders of the
Company in Q3 Fiscal 2023 was $11.9
million or $0.07 per
share, compared to net income of $5.1
million or $0.03 per
share in the three months ended December 31,
2021 ("Q3 Fiscal 2022").
In Q3 Fiscal 2023, the Company's consolidated financial results
were mainly impacted by i) increases of 8% and 12%, respectively,
in silver and lead sold, and a decrease of 6% in zinc sold; ii)
decreases of 7%, 8%, and 13%, respectively, in the realized selling
prices for silver, lead and zinc, and an increase of 13% in the
realized selling price for gold; iii) a foreign exchange loss of
$0.8 million arising from the
depreciation of the US dollar against the Company's functional
currencies, mainly the Chinese yuan and Canadian dollar; and iv) a
gain of $3.0 million on equity
investments.
Revenue in Q3 Fiscal 2023 was $58.7 million, down 1% compared to $59.1 million in Q3 Fiscal 2022. The decrease is
mainly due to a decrease of $4.6
million arising from the decrease in the net realized
selling prices for silver, lead and zinc, offset by an increase of
$4.2 million arising from the
increase in silver and lead sold.
Income from mine operations in Q3 Fiscal 2023 was
$21.7 million, up 1% compared to
$21.5 million in Q3 Fiscal 2022.
Income from mine operations at the Ying Mining District was
$19.0 million, compared to
$17.6 million in Q3 Fiscal 2022.
Income from mine operations at the GC Mine was $2.9 million, compared to $4.0 million in Q3 Fiscal 2022.
Cash flow provided by operating activities in Q3
Fiscal 2023 was $25.7 million, down
$3.0 million compared to $28.7 million in Q3 Fiscal 2022.
The Company ended Q3 Fiscal 2023 with $210.3 million in cash, cash equivalents and
short-term investments, up 5% or $9.3
million compared to $201.0
million as at September 30,
2022.
Working capital as at December 31,
2022 was $177.0 million, up 4%
or $6.0 million compared to
$170.9 million as at September 30, 2022.
CONSOLIDATED OPERATIONAL
RESULTS
In Q3 Fiscal 2023, the Company mined 296,050 tonnes of ore, up
1% compared to 292,072 tonnes in Q3 Fiscal 2022. Ore milled in Q3
Fiscal 2023 was 303,442 tonnes, effectively the same compared to
304,772 tonnes in Q3 Fiscal 2022.
In Q3 Fiscal 2023, the Company produced approximately 1.9
million ounces of silver, 1,100 ounces of gold, 20.1 million pounds
of lead, and 7.0 million pounds of zinc, representing increases of
1%, 0%, and 6%, respectively, in silver, gold and lead production,
and a decrease of 13% in zinc production over Q3 Fiscal 2022.
In Q3 Fiscal 2023, the consolidated production costs were
$77.73 per tonne, down 9% compared to
$85.73 per tonne in Q3 Fiscal 2022.
The all-in sustaining production costs per tonne of ore processed
in Q3 Fiscal 2023 were $136.90,
essentially the same compared to $137.04 in Q3 Fiscal 2022.
In Q3 Fiscal 2023, the consolidated cash costs per ounce of
silver, net of by-product credits, were negative $1.15, compared to negative $1.33 in the prior year quarter. The increase was
mainly due to a decrease of $0.6
million in by-product credits offset by a decrease of
$0.5 million in expensed production
costs.
The consolidated all-in sustaining costs per ounce of silver,
net of by-product credits, were $9.28
compared to $8.82 in Q3 Fiscal 2022.
The increase was mainly due to an increase of $3.1 million in sustaining capital expenditures
offset by a decrease of $1.1 million
in administrative expenses and mineral resources
tax.
EXPLORATION AND DEVELOPMENT
In Q3 Fiscal 2023, on a consolidated basis, a total of 70,228
metres or $2.5 million worth of
diamond drilling were completed (Q3 Fiscal 2022 – 127,532 metres or
$7.3 million), of which approximately
37,740 metres or $1.1 million worth
of diamond drilling were expensed as part of mining costs (Q3
Fiscal 2022 – 83,430 metres or $2.3
million) and approximately 32,448 metres or $1.4 million worth of diamond drilling were
capitalized (Q3 Fiscal 2022 – 44,102 metres or $5.0 million). In addition, approximately 9,719
metres or $3.8 million worth of
preparation tunnelling were completed and expensed as part of
mining costs (Q3 Fiscal 2022 – 8,705 metres or $3.3 million), and approximately 20,945 metres or
$9.0 million worth of tunnels,
raises, ramps and declines were completed and capitalized (Q3
Fiscal 2022 – 22,958 metres or $9.9
million).
In December 2022, the Company's
Kuanping Silver-Lead-Zinc-Gold Project ("Kuanping Project")
received a mining license (the "Kuanping Mining License") from the
Department of Natural Resources, Henan
Province, China. The
Kuanping Mining License covers 6.97 square kilometres and is good
until March 13, 2029.
As of December 31, 2022, a total
of $4.0 million in expenditures have
been incurred on the construction of the new 3,000 tonnes per day
flotation mill (the "New Mill") and the new tailings storage
facility (the "TSF"). A total of 2,147 metres of drainage tunnels
were completed, and the site preparation for the New Mill was also
substantially completed. The first batch of $4.1 million (RMB¥29.3 million) of milling
equipment was ordered. The environmental assessment study report
was revised and is pending government approval.
The Company spent approximately $1.8
million to upgrade most roads to concrete and upgrade
certain environmental protection facilities at the Ying Mining
District as part of our continued commitment to build and operate
green mines. The Company also spent approximately
$1.0 million to construct an X-Ray
Transmission Ore Sorting System ("XRT Ore Sorting System") to
optimize mine planning and improve processing head grades at the GC
Mine. The XRT Ore Sorting System is expected to be completed in the
fourth quarter of Fiscal 2023.
INDIVIDUAL MINE OPERATING
PERFORMANCE
Ying Mining District
GC Mine
FISCAL 2024 PRODUCTION, CASH
COSTS, AND CAPITAL EXPENDITURES GUIDANCE
In Fiscal 2024, the Company expects to mine and process
1,100,000 to 1,170,000 tonnes ore, yielding approximately 4,400 to
5,500 ounces of gold, 6.8 to 7.2 million ounces of silver, 70.5 to
73.8 million pounds of lead, and 27.7 to 29.7 million pounds of
zinc. Fiscal 2024 production guidance represents production
increases of approximately 3% to 8% in ores, 1% to 26% in gold, 3%
to 8% in silver, 3% to 8% in lead, and 14% to 23% in zinc compared
to the expected production result in Fiscal 2023.
The table below summarizes the work plan and estimated capital
expenditures in Fiscal 2024.

In Fiscal 2024, the Company plans to: i) complete 8,800 metres
of tunnels as major access and transportation ramps at estimated
capitalized expenditures of $6.3
million, representing a 26% increase in meterage and a 19%
increase in cost compared to the expected results in Fiscal 2023;
ii) complete 71,900 metres of exploration and mining development
tunnels at estimated capitalized expenditures of $30.3 million, representing a decrease of 4% in
meterage and an increase of 1% in cost compared to the expected
results in Fiscal 2023; iii) complete and capitalize 176,600 metres
of diamond drilling to upgrade and explore mineral resources for
future production at an estimated cost of $5.0 million, representing an increase of 11% in
meterage and a decrease of 38% in cost compared to the expected
results in Fiscal 2023; and iv) spend $23.1
million on equipment, the XRT Ore Sorting System, a paste
backfill plant, the mill and TSF (tailing storage facility).
In addition to the capitalized tunneling and drilling work, the
Company also plans to complete and expense 31,100 metres of mining
preparation tunnels and 96,200 metres of diamond drilling.
(a) Ying Mining District
In Fiscal 2024, the Company plans to mine and process 770,000 to
810,000 tonnes of ore at the Ying Mining District, including 30,000
– 40,000 tonnes of gold ore with an expected head grade of 3.6 g/t
gold, to produce approximately 4,400 to 5,500 ounces of gold, 6.2
to 6.5 million ounces of silver, 62.9 to 65.6 million pounds of
lead, and 9.1 to 9.5 million pounds of zinc. Fiscal 2024 production
guidance at the Ying Mining District represents production
increases of approximately 0% to 5% in ore, 1% to 26% in gold, 3%
to 8% in silver, 4% to 8% in lead, and 21% to 26% in zinc compared
to the expected production results in Fiscal 2023.
The cash production cost is expected to be $90.4 to $92.6 per
tonne of ore, and the all-in sustaining production cost is
estimated at $143.8 to $148.8 per tonne of ore processed, representing a
2% to 3% decrease in cash production cost and a 1% to 2% increase
in all-in sustaining production cost compared to the expected
results in Fiscal 2023.
In Fiscal 2024, the Ying Mining District plans to: i) complete
8,800 metres of metre tunnels as major access and
transportation ramps at estimated capitalized expenditures of
$6.3 million, representing an
increase of 26% in meterage and an increase of 19% in cost compared
to the expected results in Fiscal 2023; ii) complete 57,200
metres of exploration and mining development tunnels at estimated
capitalized expenditures of $23.9
million, representing a decrease of 8% in meterage and a
decrease of 6% in cost compared to the expected results in Fiscal
2023; iii) complete and capitalize 146,400 metres of diamond
drilling to upgrade and explore mineral resources for future
production at an estimated cost of $4.2
million, representing an increase of 13% in meterage and a
decrease of 24% in cost compared to the expected results in Fiscal
2023; and iv) spend $21.8 million on
equipment and facilities, including $12.9 million on the
construction of the TSF, $3.0 million
to build a paste backfill plant and a XRT Ore Sorting system to
optimize the mine plan and improve ore processing head grades, and
$1.2 million to improve certain power
facilities and to replace some electrical cables. The Company still
plans to complete the TSF in 2024 and is currently delaying
construction of the new 3,000 TPD mill by one year.
In addition to the capitalized tunneling and drilling work, the
Ying Mining District also plans to complete and expense 25,800
metres of mining preparation tunnels and 71,400 metres of diamond
drilling, representing decreases of 18% and 44%, respectively,
compared to the expected results in Fiscal 2023.
(b) GC Mine
In Fiscal 2024, the Company plans to mine and process 330,000 to
360,000 tonnes of ore at the GC Mine to produce 620 to 670 thousand
ounces of silver, 7.5 to 8.2 million pounds of lead, and 18.5 to
20.1 million pounds of zinc. Fiscal 2024 production guidance at the
GC Mine represents production increases of approximately 11% to 21%
in ore, 4% to 14% in silver, -2% to 6% in lead, and 12% to 21% in
zinc production compared to the expected results in Fiscal
2023.
The cash production cost is expected to be $50.3 to $52.3 per
tonne of ore, and the all-in sustaining production cost is
estimated at $79.6 to $84.2 per tonne of ore processed, representing a
10% to 11% decrease in cash production cost and a 4% to 5% decrease
in all-in sustaining production cost compared to the expected
results in Fiscal 2023.
In Fiscal 2024, the GC Mine plans to: i) complete and capitalize
14,700 metres of exploration and development tunnels at estimated
capital expenditures of $6.4 million,
an increase of 12% in meterage and an increase of 42% in cost
mainly due to increased tunnel dimension to allow small scale
mechanized equipment access, compared to the expected results
in Fiscal 2023; ii) complete and capitalize 30,200 metres of
diamond drilling at an estimated cost of $0.8 million, representing a 100% increase in
meterage and cost to prepare for future production, compared to the
expected results in Fiscal 2023; and iii) spend $0.7 million on equipment and facilities. The
total capital expenditures at the GC Mine are budgeted at
$7.9 million in Fiscal 2024, down
$0.5 million compared to the expected
results in Fiscal 2023.
In addition to the capitalized tunneling and drilling work, the
Company also plans to complete and expense 5,300 metres of tunnels
and 24,800 metres of underground drilling at the GC Mine,
representing decreases of 28% and 43%, respectively, compared to
the expected results in Fiscal 2023.
(c) Kuanping Project
The Company plans to carry out studies to complete the
environmental assessment report, water and soil protection
assessment report, and preliminary safety facilities and mine
design report as required for the Kuanping Project in Fiscal
2024. Further updates on the mine construction plan and cost
estimates will be provided upon completion of these reports.
CONFERENCE CALL
DETAILS
A conference call to discuss these results will be held
tomorrow, Friday, February 10, at
9:00 am PDT (12:00 pm EDT). To participate in the conference
call, please dial the numbers below.
Canada/USA TF: 888-664-6383
International Toll: 416-764-8650
Conference ID: 17900371
Participants should dial-in 10 – 15 minutes prior to the start
time. A replay of the conference call and transcript will be
available on the Company's website at www.silvercorp.ca.
Mr. Guoliang Ma, P.Geo., Manager
of Exploration and Resources of the Company, is the Qualified
Person as defined by National Instrument 43-101 – Standards of
Disclosure for Mineral Projects ("NI 43-101") and has reviewed and
given consent to the technical information contained in this news
release.
About Silvercorp
Silvercorp is a Canadian mining company producing silver, gold,
lead, and zinc with a long history of profitability and growth
potential. The Company's strategy is to create shareholder value by
1) focusing on generating free cashflow from long life mines; 2)
organic growth through extensive drilling for discovery; 3) ongoing
merger and acquisition efforts to unlock value; and 4) long term
commitment to responsible mining and ESG. For more information,
please visit our website at www.silvercorp.ca.
For further information
Silvercorp Metals Inc.
Lon Shaver
Vice President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: investor@silvercorp.ca
Website: www.silvercorp.ca
ALTERNATIVE PERFORMANCE (NON-IFRS) MEASURES
This news release should be read in conjunction with the
Company's Management Discussion & Analysis ("MD&A"), the
unaudited condensed consolidated interim financial statements and
related notes contains therein for the three and nine months ended
December 31, 2022, which have been
posted on SEDAR under the Company's profile at www.sedar.com and on
EDGAR at www.sec.gov, and are also available on the Company's
website at www.silvercorp.ca under the Investor section. This
news release refers to various alternative performance (non-IFRS)
measures, such as adjusted earnings and adjusted earnings per
share, cash costs and all-in sustaining costs per ounce of silver,
net of by-product credits, production costs and all-in sustaining
production costs per tonne of ore processed and working capital.
These measures are widely used in the mining industry as a
benchmark for performance, but do not have standardized meanings
under IFRS as an indicator of performance and may differ from
methods used by other companies with similar description. The
detailed description and reconciliation of these alternative
performance (non-IFRS) measures have been incorporated by reference
and can be found on page 30, section 12 – Alternative Performance
(Non-IFRS) Measures in the MD&A for the three and nine months
ended December 31, 2022 filled on
SEDAR at www.sedar.com and EDGAR at www.sec.gov and which
is incorporated by reference here in.
CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS
Certain of the statements and information in this news release
constitute "forward-looking statements" within the meaning of the
United States Private Securities Litigation Reform Act of 1995 and
"forward-looking information" within the meaning of applicable
Canadian and US securities laws (collectively, "forward-looking
statements"). Any statements or information that express or involve
discussions with respect to predictions, expectations, beliefs,
plans, projections, objectives, assumptions or future events or
performance (often, but not always, using words or phrases such as
"expects", "is expected", "anticipates", "believes", "plans",
"projects", "estimates", "assumes", "intends", "strategies",
"targets", "goals", "forecasts", "objectives", "budgets",
"schedules", "potential" or variations thereof or stating that
certain actions, events or results "may", "could", "would", "might"
or "will" be taken, occur or be achieved, or the negative of any of
these terms and similar expressions) are not statements of
historical fact and may be forward-looking statements.
Forward-looking statements relate to, among other things: the price
of silver and other metals; the accuracy of mineral resource and
mineral reserve estimates at the Company's material properties; the
sufficiency of the Company's capital to finance the Company's
operations; estimates of the Company's revenues and capital
expenditures; estimated production from the Company's mines in the
Ying Mining District and the GC Mine; timing of receipt of permits
and regulatory approvals; availability of funds from production to
finance the Company's operations; and access to and availability of
funding for future construction, use of proceeds from any financing
and development of the Company's properties.
Actual results may vary from forward-looking statements.
Forward-looking statements are subject to a variety of known and
unknown risks, uncertainties and other factors that could cause
actual events or results to differ from those reflected in the
forward-looking statements, including, without limitation, risks
relating to: global economic and social impact of COVID-19;
fluctuating commodity prices; calculation of resources, reserves
and mineralization and precious and base metal recovery;
interpretations and assumptions of mineral resource and mineral
reserve estimates; exploration and development programs;
feasibility and engineering reports; permits and licences; title to
properties; property interests; joint venture partners; acquisition
of commercially mineable mineral rights; financing; recent market
events and conditions; economic factors affecting the Company;
timing, estimated amount, capital and operating expenditures and
economic returns of future production; integration of future
acquisitions into the Company's existing operations; competition;
operations and political conditions; regulatory environment in
China and Canada; environmental risks; foreign exchange
rate fluctuations; insurance; risks and hazards of mining
operations; key personnel; conflicts of interest; dependence on
management; internal control over financial reporting; and bringing
actions and enforcing judgments under U.S. securities laws.
This list is not exhaustive of the factors that may affect any
of the Company's forward-looking statements. Forward-looking
statements are statements about the future and are inherently
uncertain, and actual achievements of the Company or other future
events or conditions may differ materially from those reflected in
the forward-looking statements due to a variety of risks,
uncertainties and other factors, including, without limitation,
those referred to in the Company's Annual Information Form under
the heading "Risk Factors" and in the Company's Annual Report on
Form 40-F, and in the Company's other filings with Canadian and
U.S. securities regulators. Although the Company has
attempted to identify important factors that could cause actual
results to differ materially, there may be other factors that cause
results not to be as anticipated, estimated, described or
intended. Accordingly, readers should not place undue
reliance on forward-looking statements.
The Company's forward-looking statements are based on the
assumptions, beliefs, expectations and opinions of management as of
the date of this news release, and other than as required by
applicable securities laws, the Company does not assume any
obligation to update forward-looking statements if circumstances or
management's assumptions, beliefs, expectations or opinions should
change, or changes in any other events affecting such statements.
Assumptions may prove to be incorrect and actual results may differ
materially from those anticipated. Consequently, guidance cannot be
guaranteed. For the reasons set forth above, investors should not
place undue reliance on forward-looking statements.