RNS Number : 1403L
88 Energy Limited
18 April 2024
 

18 April 2024

 

88 Energy Limited (ASX:88E, AIM:88E, OTC:EEENF) (88 Energy, 88E or the Company) provides the following report for the quarter ended 31 March 2024. 

Highlights

 

Project Phoenix (~75% WI)

·      Successful Hickory-1 discovery well flow test and stimulation program (Flow Test) conducted during March and April 2024.

·      Upper Slope Fan System (USFS) produced at a peak flow rate of over 70 barrels of oil per day (bopd) of light oil, with multiple oil shows measuring ~40-degree API oil gravity.

·      Subsequent to quarter end the Shelf Margin Deltaic (SMD) produced at a peak flow rate of ~ 50 barrels of oil per day (bopd) of light oil, with multiple oil shows measuring ~39-degree API oil gravity.

·      Quality and deliverability of both SMD-B and USFS demonstrated via oil production to surface with the USFS reservoir producing under natural flow - positively differentiating Hickory-1 from results on adjacent acreage.

·      It is anticipated that these reservoirs would be developed from long horizontal production wells which typically produce at multiples of between 6 to 12 times higher than vertical wells. Project Phoenix also benefits from the ability to produce concurrently from multiple reservoirs in a single development scenario.

·      Independent Contingent Resource declaration to be sought for both the Upper SFS and Lower SFS reservoirs, as well as the SMD reservoirs, based on the flow of hydrocarbons to surface.

·      JV Partner Burgundy Xploration, LLC (Burgundy) transferred remaining outstanding 2023 cash call amount due of US$1.75 million and remains committed to the Hickory-1 flow test authorised funding expenditure (AFE).

 

 

Managing Director, Ashley Gilbert, commented on Project Phoenix:

"In what has proven to be a pivotal quarter for 88 Energy and its shareholders, we achieved the successful flow of oil to surface, for the first time, from the previously untested USFS reservoir and also subsequent to quarter end from the shallower SMD-B reservoir, both at our Hickory-1 discovery well. This represents a tremendous achievement that adds immediate value to Project Phoenix and unlocks multiple pathways for future commercialisation.

With flow testing operations complete, we will now transition to post well analysis and are moving to secure further Contingent Resources at Project Phoenix.

We expect to commence a formal farm-out process for Project Phoenix following completion of the Hickory-1 post flow test analysis, with the aim of attracting a strategic partner for the next stage of development and commercialisation."

 

Namibia PEL 93 (20% WI)

·      Transfer of 20% working interest in Petroleum Exploration Licence 93 (PEL 93) complete, being the first stage of a three-stage farm-in agreement following approval by the Namibian Ministry of Mines and Energy.

·      PEL 93 includes an extensive lead portfolio with ten significant independent structural closures identified from a range of geophysical and geochemical techniques and potential for more leads to be identified as dataset is expanded.

·      Seismic acquisition is planned for mid-2024 with potential initial exploration well targeting the Damara play as early as H2 CY2025.

Project Leonis (100% WI)

·      Maiden prospective resource estimate for Upper Schrader Bluff (USB) reservoir expected H1 2024.

·      Farm-out process commenced with multiple parties engaged and reviewing data room materials, ahead of potential drilling of a new well in 2025/2026.

Project Longhorn (~64% WI)

·      Two of the planned five workovers scheduled to be in completed in 1H 2024 are underway and are currently projected to be delivered under budget.

·      Q1 2024 production steadily averaged 328 BOE per day gross (~62% oil).

·      Company received cash flow distribution of A$0.7M in March 2024.

·      The Company also reduced it's working interest in 9 leases during the quarter by an average of a ~7% reduction in net WI's across these leases. Consideration for these leases totalled A$0.3M.

Corporate

·     Cash balance of A$17.5 million and no debt (as at 31 March 2024), ~20% of Hickory-1 flow test payments have been made, with the remainder expected to be paid in Q2 2024.

·      Net cash outflows in relation to operating expenses for Q1 2024 totalling A$0.77M as compared to A$1.44M in Q4 2023.

·      Cost reduction initiatives commenced in the quarter targeting a reduction in salary and overhead costs.  Further business optimisation activities underway, aimed at preserving and enhancing value for shareholders and advancement of key projects.

 

Project Phoenix (~75% WI)

Project Phoenix is focused on oil-bearing conventional reservoirs identified during the drilling and logging of Icewine-1 and Hickory-1 and adjacent offset drilling and testing.  Project Phoenix is strategically located on the Dalton Highway with the Trans-Alaskan Pipeline System running through the acreage.

The Hickory-1 discovery well was previously drilled in February 2023. All American Oilfield's upgraded Rig-111 was subsequently secured in September 2023 to conduct the flow test. During the March 2024 quarter, ice road and pad construction works were completed and the rig was subsequently mobilised. Flow test operations commenced in March 2024.

The testing operations focussed on the two primary targets, the SFS and SMD reservoirs. Of the SFS series of reservoirs, the Upper SFS reservoir was targeted to be flow tested as it has not been previously tested, whereas the Lower SFS has previously been flow tested and producibility of that reservoir confirmed on adjacent acreage. The Upper SFS was followed by a targeted testing of the SMD-B reservoir. Each zone was independently isolated, stimulated and flowed to surface using nitrogen lift to assist in an efficient clean-up of the well.

A diagram of a well-being Description automatically generated with medium confidence

 

Upper SFS flow test results

A 20ft perforated interval in the Upper SFS reservoir was stimulated via a single fracture stage of 241,611 lbs proppant volume. The well was cleaned-up and flowed for 111 hours in total, of which 88 hours was under natural flow back and 23.5 hours utilising nitrogen lift.

imageThe USFS test produced at a peak flow rate of over ~70 bopd. Oil cuts increased throughout the flow back period as the well cleaned up, reaching a maximum of 15% oil cut at the end of the flow test program. The Company expects that oil rates and cut would have likely increased further should the test period have been extended. The well produced at an average oil flow rate of approximately 42 bopd during the natural flow back period (with established production rates occurring over an ~11 hour test period, accumulating ~19bbls of oil. An additional ~6bbls of oil was recovered outside of the established production period), with instantaneous rates ranging from approximately 10 - 77 bopd with average rates increasing through the test period.  Importantly, the USFS zone flowed oil to surface under natural flow, with flow back from other reservoirs in adjacent offset wells only producing under nitrogen lift. A total of 3,960bbls of fluid was injected into the reservoir and 2,882bbls of water was recovered during the flow back period, most of which was injection fluid. Total flow rates (inclusive of recovery of frac fluid) averaged ~600 bbl/d over the duration of the flow back.

Multiple oil samples were recovered with measured oil gravities of between 39.9 to 41.4 API (representing a light crude oil).

Additionally, some natural gas liquids ("NGLs") were produced but not measured, as was anticipated in the planning phase. The presence of NGLs was demonstrated by samples from the flare line and by visible black smoke in the flare. Historically, NGL prices on the North Slope of Alaska have been similar or slightly below light oil prices and are therefore considered highly valuable. Further work is required to quantify the exact volume of NGLs, which 88 Energy intends to include as part of a maiden certified Contingent Resource assessment at Project Phoenix for the SFS reservoirs.

For full details in relation to the Upper SFS test results please refer to the ASX announcement dated 2 April 2024.

 

SMD-B flow test results (subsequent to quarter end)

A measuring tape in a beaker with liquid in it Description automatically generatedA 20ft perforated interval in the SMD-B reservoir was stimulated via a single fracture stage comprising 226,967 lbs of proppant volume. The well was cleaned-up and flowed for 84 hours in total, utilising nitrogen lift throughout the entire test period. The average fluid flow rate over the duration of the flow back period was approximately 445 bbls/d, with choke sizes ranging from 8/64ths to 33/64ths.

The SMD-B test produced at a peak estimated flow rate of ~50 bopd. Oil cuts varied throughout the flow back period, reaching a maximum of 10% oil cut. The well produced at an average oil cut of 4% following initial oil to surface, with instantaneous rates observed during the 16-hour period varying as the well continued to clean up. Total stimulation load water was not recovered and water salinity measurements indicated we were recovering load water at the conclusion of the test. Unlike flow tests on adjacent acreage where multiple gas lift mandrels and valves were used in completions designs, and nitrogen was unloaded in the tubing in stages up the well bore, Hickory-1 utilised a single gas lift mandrel where nitrogen was introduced via one valve at the deepest section. This is viewed as positive indication for future potential rates and performance.

Multiple oil samples were recovered, with measured oil gravities of between 38.5 to 39.5 API, representing a light crude oil.

Importantly, the SMD-B zone flowed oil to surface with little to no measurable gas, representing a low GoR production rate.  Pressurised oil samples collected during both the USFS and SMD tests will be transported to laboratories for further analysis.

The SMD-B flow test was concluded with sufficient information for the next steps, and the data recorded will assist 88E in optimisation and design processes in the next phase of advancement of Project Phoenix.

For full details in relation to the SMD-B test results please refer to the ASX announcement dated 15 April 2024.

 

Namibia PEL 93 (20% WI)

In February 2024, the Company announced the successful 20% WI transfer by Monitor Exploration Limited (Monitor) to 88 Energy in relation to PEL 93 located in the Owambo Basin, Namibia following receipt approval from the Ministry of Mines and Energy.

The Company, via its wholly-owned Namibian subsidiary, previously executed a three-stage farm-in agreement in November 2023 for up to a 45% non-operated working interest in onshore Petroleum Exploration Licence (PEL 93), which covers 18,500km2 of underexplored ground within the Owambo Basin in Namibia (refer to ASX announcement dated 13 November 2023).

Under the terms of the agreement, 88 Energy may earn up to a 45% working interest by funding its share of agreed costs under the 2023-2024 approved work program and budget as defined in the Farm-In Agreement (2024 Work Program) and any future work program budgets yet to be agreed. The maximum total investment by the Company is anticipated to be US$18.7 million.

The current and potential future PEL 93 Joint Venture partners and working interests are as follows:

A screenshot of a graph Description automatically generated

Namibia has been identified as one of the last remaining under-explored onshore frontier basins and one of the World's most prospective new exploration zones. PEL 93 is more than 10 times larger than 88 Energy's Alaskan portfolio and more than 70 times larger than Project Phoenix.

Recent drilling results on nearby acreage has highlighted the potential of a new and underexplored conventional oil and gas play in the Damara Fold belt, referred to as the Damara Play. Historical assessment utilised a combination of techniques and interpretation of legacy data to identify the Owambo Basin, and specifically blocks 1717 and 1817, as having significant exploration potential.

Monitor has utilised a range of geophysical and geochemical techniques to assess and validate the significant potential of the acreage since award of PEL 93 in 2018. It has identified ten (10) independent structural closures from airborne geophysical methods and partly verified these using existing 2D seismic coverage. Further, ethane concentration measured in soil samples over interpreted structural leads validates the existence of an active petroleum system, with passive seismic anomalies also aligning closely to both interpreted structural leads and measured alkane molecules (c1-c5) concentrations in soil.

The forward work-program will start with a low impact ~200 line-kilometre 2D seismic program focusing on confirming the structural closures of the 10 independent leads identified. The 2D seismic program will be conducted in mid-2024 following a period of planning, public consultation, updating of environmental compliance requirements and relevant approvals. Results from the 2D seismic program will then be incorporated into existing historical exploration data over the acreage, with results used to identify possible exploration drilling locations.

 

Project Longhorn (~65% WI)

In December 2023, the Joint Venture (Bighorn JV), Bighorn Energy LLC (Bighorn) which comprises Longhorn Energy Investments LLC (LEI) a 100% wholly owned subsidiary of 88 Energy with 75% ownership and Lonestar I, LLC (Lonestar or Operator) with remaining 25% ownership, finalised its 2024 work program and budget. The Bighorn JV agreed to a development program that included 5 workovers in 1H 2024 and 2 new wells in 2H 2024, contingent on successful workovers.

During the quarter, the Bighorn JV commenced two of the planned five workovers with assessment of production occuring during April 2024.

Q1 2024 production averaged a fairly steady 328 BOE per day gross (~62% oil) which was slightly below the budgeted volume of 346 BOE per day gross (65% oil) due to January winter storms and the Company received a cash flow distribution of A$0.7M in March 2024.

The Bighorn JV executed a ~10% sell-down (gross, ~7% net to 88 Energy) of the 2023 acquired acreage, in order to re-disk and accelerate development opportunities. The transaction realised acquisition payments of ~A$0.3M and the non-operated partners will contribute their share of the capital development costs coupled with a 25% carry of their ownership share on the five 2024 WP&B agreed workovers.

 

A blue and white chart with numbers and text Description automatically generated

 

Qualified Petroleum Reserves Evaluator Statement

The information in this evaluation that relates to Project Longhorn is based on, and fairly represents, information and supporting documentation prepared by Paul Griffith of consultants PJG Petroleum Engineers LLC. Mr Griffith holds a BSc. and a Master's in Petroleum Engineering, is a member of the Society of Petroleum Engineers (SPE) and has over 35 years of reservoir and petroleum engineering experience. Mr Griffith is not an employee of the Company. Mr Griffith has reviewed this document as to its form and context in which the reserves and the supporting information are presented and consent to its release.

The information in this evaluation that relates to the Umiat oil field has not changed since first reporting to the ASX on 11 January 2021, and fairly represents, information and supporting documentation prepared by technical employees of consultants Ryder Scott Company LP, under the supervision of Dr Stephen Staley, as stated in that announcement. Dr Staley is a Non-Executive Director of the Company. Dr Staley has more than 40 years' experience in the petroleum industry, is a Fellow of the Geological Society of London, and a qualified Geologist/Geophysicist who has sufficient experience that is relevant to the style and nature of the oil prospects under consideration and to the activities discussed in this document. Dr Staley has reviewed the information and supporting documentation referred to in this announcement and considers the resource and reserve estimates to be fairly represented and consents to its release in the form and context in which it appears. His academic qualifications and industry memberships appear on the Company's website and both comply with the criteria for "Competence" under clause 3.1 of the Valmin Code 2015. 

 

Reserves Cautionary Statement

Oil and gas reserves and resource estimates are expressions of judgment based on knowledge, experience and industry practice. Estimates that were valid when originally calculated may alter significantly when new information or techniques become available. Additionally, by their very nature, reserve and resource estimates are imprecise and depend to some extent on interpretations, which may prove to be inaccurate. As further information becomes available through additional drilling and analysis, the estimates are likely to change. This may result in alterations to development and production plans which may, in turn, adversely impact the Company's operations. Reserves estimates and estimates of future net revenues are, by nature, forward looking statements and subject to the same risks as other forward-looking statements.

 

Corporate

The Company held a General Meeting on 15 January 2024 and all 11 resolutions were passed without amendment on a poll.

 

Finance

As at 31 March 2024, the Company's cash balance is A$17.5M.

The ASX Appendix 5B attached to this quarterly report contains the Company's cash flow statement for the quarter. The material cash flows for the period were:

 

·      Exploration and evaluation expenditure of A$3.9M (December 2023 quarter: A$2.8M) predominantly related to the Hickory-1 flow test program. Approximately 20% of Hickory-1 flow test payments have been made, with the remainder expected to be paid in Q2 2024.

·      Administration, staff, and other costs of A$0.7M (December 2023 quarter: A$1.4M). Including fees paid to Directors and consulting fees paid to Directors of A$0.2M. 

·      Cost reduction initiatives commenced in the quarter targeting a reduction in salary and overhead costs.  Further business optimisation activities underway, aimed at preserving and enhancing value for shareholders and advancement of key projects.

 

Information required by ASX Listing Rule 5.4.3

A screenshot of a computer screen Description automatically generated

 

Pursuant to the requirements of the ASX Listing Rules Chapter 5 and the AIM Rules for Companies, the technical information and resource reporting contained in this announcement was prepared by, or under the supervision of, Dr Stephen Staley, who is a Non-Executive Director of the Company. Dr Staley has more than 40 years' experience in the petroleum industry, is a Fellow of the Geological Society of London, and a qualified Geologist / Geophysicist who has sufficient experience that is relevant to the style and nature of the oil prospects under consideration and to the activities discussed in this document. Dr Staley has reviewed the information and supporting documentation referred to in this announcement and considers the prospective resource estimates to be fairly represented and consents to its release in the form and context in which it appears. His academic qualifications and industry memberships appear on the Company's website, and both comply with the criteria for "Competence" under clause 3.1 of the Valmin Code 2015. Terminology and standards adopted by the Society of Petroleum Engineers "Petroleum Resources Management System" have been applied in producing this document.

 

This announcement has been authorised by the Board.

 

Media and Investor Relations:

 

88 Energy Ltd

Ashley Gilbert, Managing Director

Tel: +61 (0)8 9485 0990

Email:investor-relations@88energy.com




Fivemark Partners, Investor and Media Relations


Michael Vaughan

Tel: +61 (0)422 602 720



EurozHartleys Ltd


Dale Bryan

Tel: +61 (0)8 9268 2829



Cavendish Capital Markets Limited

Tel: +44 (0)207 220 0500

Derrick Lee

Tel: +44 (0)131 220 6939

Pearl Kellie

Tel: +44 (0)131 220 9775



 

1.   Refer announcement released to ASX on 21 December 2023 regarding Project Peregrine 12-month suspension until 30 November 2024

 

 

 

Information required by ASX Listing Rule 5.4.3 - Lease Schedules as at 31 March 2024

 

A screenshot of a data Description automatically generated

 

Appendix 5B

Mining exploration entity or oil and gas exploration entity
quarterly cash flow report

Name of entity

88 Energy Limited

ABN

 

Quarter ended ("current quarter")

80 072 964 179


31 March 2024

 

Consolidated statement of cash flows

Current quarter
$A'000

Year to date (3 months)
$A'000

 

1.

Cash flows from operating activities

-

-

 

1.1

Receipts from customers

 

1.2

Payments for

-

-

 


(a)   exploration & evaluation

 


(b)   development

-

-

 


(c)   production

-

-

 


(d)   staff costs

(399)

(399)

 


(e)   administration and corporate costs

(406)

(406)

 

1.3

Dividends received (see note 3)

-

-

 

1.4

Interest received

37

37

 

1.5

Interest and other costs of finance paid

-

-

 

1.6

Income taxes paid

-

-

 

1.7

Government grants and tax incentives

-

-

 

1.8

Other

-

-

 

1.9

Net cash from / (used in) operating activities

(768)

(768)

 


 

2.

Cash flows from investing activities

-

-

 

2.1

Payments to acquire or for:

 


(a)   entities

 


(b)   tenements

(153)

(153)

 


(c)   property, plant and equipment

-

-

 


(d)   exploration & evaluation

(3,851)

(3,851)

 


(e)   investments

-

-

 


(f)    other non-current assets

-

-

 

2.2

Proceeds from the disposal of:

-

-

 


(a)   entities

 


(b)   tenements

-

-



(c)   property, plant and equipment

-

-

 


(d)   investments

-

-

 


(e)   other non-current assets

-

-

 

2.3

Cash flows from loans to other entities

-

-

 

2.4

Dividends received (see note 3)

-

-

 

2.5

Other - Joint Venture Contributions

Other - Distribution from Project Longhorn

Other - Return of Bond

2,874

715

-

2,874

715

-

 

2.6

Net cash from / (used in) investing activities

(415)

(415)

 


 

3.

Cash flows from financing activities

-

-

 

3.1

Proceeds from issues of equity securities (excluding convertible debt securities)

 

3.2

Proceeds from issue of convertible debt securities

-

-

 

3.3

Proceeds from exercise of options

-

-

 

3.4

Transaction costs related to issues of equity securities or convertible debt securities

-

-

 

3.5

Proceeds from borrowings

-

-

 

3.6

Repayment of borrowings

-

-

 

3.7

Transaction costs related to loans and borrowings

-

-

 

3.8

Dividends paid

-

-

 

3.9

Other (provide details if material)

-

-

 

3.10

Net cash from / (used in) financing activities

-

-

 


 

4.

Net increase / (decrease) in cash and cash equivalents for the period



 

4.1

Cash and cash equivalents at beginning of period

18,183

18,183

 

4.2

Net cash from / (used in) operating activities (item 1.9 above)

(768)

(768)

 

4.3

Net cash from / (used in) investing activities (item 2.6 above)

(415)

(415)

 

4.4

Net cash from / (used in) financing activities (item 3.10 above)

-

-

 

4.5

Effect of movement in exchange rates on cash held

502

502

 

4.6

Cash and cash equivalents at end of period

17,502

17,502

 

 

5.

Reconciliation of cash and cash equivalents
at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts

Current quarter
$A'000

Previous quarter
$A'000

5.1

Bank balances

17,502

18,182

5.2

Call deposits

-

-

5.3

Bank overdrafts

-

-

5.4

Other (provide details)

-

-

5.5

Cash and cash equivalents at end of quarter (should equal item 4.6 above)

17,502

18,182

 

6.

Payments to related parties of the entity and their associates

Current quarter
$A'000

6.1

Aggregate amount of payments to related parties and their associates included in item 1

214

6.2

Aggregate amount of payments to related parties and their associates included in item 2

-

Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an explanation for, such payments.

6.1       Payments relate to Director and consulting fees paid to Directors. All transactions involving directors and associates were on normal commercial terms.

 

7.

Financing facilities

Note: the term "facility' includes all forms of

financing arrangements available to the entity.

Add notes as necessary for an understanding of

the sources of finance available to the entity.

Total facility amount at quarter end
$US'000

Amount drawn at quarter end
$US'000

7.1

Loan facilities

-

-

7.2

Credit standby arrangements

-

-

7.3

Other (please specify)

-

-

7.4

Total financing facilities

-

-


 


7.5

Unused financing facilities available at quarter end

-

7.6

Include in the box below a description of each facility above, including the lender, interest rate, maturity date and whether it is secured or unsecured. If any additional financing facilities have been entered into or are proposed to be entered into after quarter end, include a note providing details of those facilities as well.


 

8.

Estimated cash available for future operating activities

$A'000

8.1

Net cash from / (used in) operating activities (item 1.9)

(768)

8.2

(Payments for exploration & evaluation classified as investing activities) (item 2.1(d))

(3,851)

8.3

Total relevant outgoings (item 8.1 + item 8.2)

(4,619)

8.4

Cash and cash equivalents at quarter end (item 4.6)

17,502

8.5

Unused finance facilities available at quarter end (item 7.5)

-

8.6

Total available funding (item 8.4 + item 8.5)

17,502




8.7

Estimated quarters of funding available (item 8.6 divided by item 8.3)

3.8

Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as "N/A". Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.

8.8

If item 8.7 is less than 2 quarters, please provide answers to the following questions:


8.8.1     Does the entity expect that it will continue to have the current level of net operating cash flows for the time being and, if not, why not?


Answer: n/a


8.8.2     Has the entity taken any steps, or does it propose to take any steps, to raise further cash to fund its operations and, if so, what are those steps and how likely does it believe that they will be successful?


Answer: n/a


8.8.3     Does the entity expect to be able to continue its operations and to meet its business objectives and, if so, on what basis?


Answer: n/a

 


Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.

 

Compliance statement

1        This statement has been prepared in accordance with accounting standards and policies which comply with Listing Rule 19.11A.

2        This statement gives a true and fair view of the matters disclosed.

 

 

Date:                18 April 2024

 

 

Authorised by:  By the Board

(Name of body or officer authorising release - see note 4)

 

Notes

1.          This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity's activities for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is encouraged to do so.

2.          If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.

3.          Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.

4.          If this report has been authorised for release to the market by your board of directors, you can insert here: "By the board". If it has been authorised for release to the market by a committee of your board of directors, you can insert here: "By the [name of board committee - eg Audit and Risk Committee]". If it has been authorised for release to the market by a disclosure committee, you can insert here: "By the Disclosure Committee".

5.          If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying with recommendation 4.2 of the ASX Corporate Governance Council's Corporate Governance Principles and Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been properly maintained, that this report complies with the appropriate accounting standards and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a sound system of risk management and internal control which is operating effectively.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDEALLPFLPLEEA
88 Energy (LSE:88E)
Graphique Historique de l'Action
De Nov 2024 à Déc 2024 Plus de graphiques de la Bourse 88 Energy
88 Energy (LSE:88E)
Graphique Historique de l'Action
De Déc 2023 à Déc 2024 Plus de graphiques de la Bourse 88 Energy