BRITISH ENERGY MONTHLY OUTPUT FIGURES - JUNE 1997
June figures for output sold to customers from British
Energy's power stations are given in the table below, together
with comparisons for the previous year.
1996 1997
JUNE YEAR TO DATE JUNE YEAR TO DATE
STATION TWh TWh TWh TWh
Hinkley
Point B 0.52 2.18 0.82 2.53
Hunterston B 0.41 1.54 0.82 2.37
Dungeness B 0.52 1.68 0.45 1.76
Heysham 1 0.68 1.82 0.81 2.26
Hartlepool 0.78 2.32 0.74 2.05
Torness 0.76 2.43 0.52 2.10
Heysham 2 0.76 2.49 0.46 2.10
Sizewell B 0.74 2.48 0.80 2.55
Total Sales
to Customers 5.17 16.94 5.42 17.72
Points to note - June 1997
* Single reactor refuelling outages completed at Dungeness B and Torness.
* Low-load refuelling completed on both reactors at Hinkley Point B and both
reactors at Hunterston B.
* One reactor at Heysham 2 was on its statutory maintenance and inspection
outage throughout the month, with work continuing on schedule. This
statutory outage is due for completion in July.
* One reactor at Torness commenced its statutory outage, as planned on 13
June.
Contact: Doug McRoberts 0131 527 2020 (Media Enquiries)
Anne Campbell 0171 389 3406 (Media Enquiries)
Paul Heward 0131 527 2250 (Investor Relations)
END
Brit Energy Csh (LSE:BGYA)
Graphique Historique de l'Action
De Mai 2024 à Juin 2024
Brit Energy Csh (LSE:BGYA)
Graphique Historique de l'Action
De Juin 2023 à Juin 2024
Real-Time news about Brit Energy Csh (London Stock Exchange): 0 recent articles
Plus d'articles sur British Energy PLC