LONDON, 1 March 2024: Petro Matad
Limited, the AIM quoted Mongolian oil company provides the
following operational update.
Key
Company Updates
·
The Company has had its application for land
access for 2024 operations approved by the Matad District
Committee. A land use agreement is now being prepared which, once
signed, will allow 2024 operations to go ahead commencing with
completion operations on the Heron 1 well.
·
The Company continues to push the Government to
complete the regulatory formalities to confirm Block XX as State
Special Purpose Land and understands and shares the frustration
felt by shareholders. The continued refusal of the Provincial
Governor to sign off on a Tripartite Agreement which has already
been approved by the Ministry of Mining and Heavy Industry (MMHI)
and the Central Land Agency has been raised by the Company with all
relevant agencies and also at the highest levels in the Mongolian
Government.
·
Petro Matad is pleased to be the chosen contractor
for the two areas for which it submitted applications in the
2022/23 Exploration Tender Round. The award of new acreage
is now expected to be made after the 2024
Mongolian Parliamentary elections in the middle of this
year.
Operational Update
Block XX local level land use
approval: In light of the ongoing delays in the completion of the
process by which the Company's Exploitation Area is being confirmed
as State Special Purpose Land, the Company has engaged with the
District authorities to secure local level approval of land usage.
At a meeting of the Matad Citizens' Representatives Committee at
the end of February the Company's application for land use in 2024
was approved. This approval covers all the areas in which the
Company wishes to operate during the year. The approval means that
the land use agreement can now be prepared and signed by the
District authorities and by the Company and it will allow our
planned operational activities to go ahead whilst the Special
Purpose Certification process is completed. We are hopeful that the
Provincial authorities, who are holding up the Special Purpose
Certification of the Exploitation Area, will not disrupt in any way
the District's approval process, but we remain vigilant.
The Company is now stepping up the
planning for operations to complete the Heron 1 well for production
once the contractors re-mobilise after the winter hiatus and as
soon as they can make available their crews and equipment.
Discussions with PetroChina for transport, processing, storage,
export and sale of the Company's early production are also
ongoing.
State Special Purpose Certification
process status: A number of regulatory steps were required to be
completed by the Government covering the granting and management of
State Special Purpose Land. As reported previously, a key part of
this is a Tripartite Agreement between the Central Land Agency,
MMHI and the Governor of Dornod Province. The Governor is still
withholding his signature, now on the basis of a partial overlap of
the Block XX Exploitation Area with a provincial Protected Area as
he claims it breaches the principle of no overlaps in areas for
specific land use.
The Block XX PSC was signed in 2006
and the provincial Protected Area was not declared by the province
until 2014, so it is the province that is in beach of the no
overlap principle. Furthermore, the Land Law allows the central
Government to take such land for State Special Purpose use, so this
overlap should not be an obstruction to the certification process.
Heron 1 and the other locations that the Company wishes to work on
in 2024 are not within the overlapped area.
The Company has raised this issue
formally with government agencies and ministers including: the
Mineral Resources and Petroleum Authority of Mongolia, MMHI,
Ministry of Economic Development, Central Land Agency, Deputy Prime
Minister, Prime Minister and the President.
The Government needs to complete
this process and Petro Matad is pushing hard for this to be
done.
New acreage: As previously reported,
the Company was selected as the preferred contractor for the two
blocks for which it submitted applications. Despite setting an
aggressive timetable for completion of the negotiations and award
of the Production Sharing Contracts, the government is now not
expected to make the awards until after the 2024 parliamentary
elections which take place in the middle of this year. This new
timeframe is not critical as the Company intends to focus all of
its operational activity on Block XX in 2024.
Mike Buck, CEO of Petro Matad,
said:
"We are very
pleased that Matad Soum has approved our application for 2024 land
access and we are following up as a matter of priority to finalise
and sign the land use agreement. With that being said, we are
extremely frustrated with the continued delay to the State Special
Purpose Certification process and we continue to push to get this
resolved.
The diligent
efforts of our Government and Community Relations teams have
facilitated this progress on land access and we are grateful to the
Matad Citizens' Representatives Committee for its favourable
hearing of our application and for its approval."
Further operational updates will be provided in
due course.
- Ends -
Further
information please contact:
Petro Matad
Limited
|
|
Mike Buck, CEO
|
+976 7014 1099 / +976 7575 1099
|
|
|
Shore Capital
(Nominated Adviser and Broker)
|
Toby Gibbs
Rachel Goldstein
|
+44 (0) 20 7408 4090
|
Zeus (Joint
Broker)
Simon Johnson
Louisa Waddell
|
+44 (0) 20 3829 5000
|
FTI Consulting
(Communications Advisory Firm)
|
|
Ben Brewerton
Christopher Laing
|
+44 (0) 20 3727 1000
|
About Petro
Matad
Petro Matad is the parent company of a group
focussed on oil exploration, as well as future development and
production in Mongolia. At the current time, Petro Matad holds 100%
working interest and the operatorship of two Production Sharing
Contracts with the Government of Mongolia. Block XX has an area of
214 square kilometres in the far eastern part of the country and
Block V has an area of 7,937 square kilometres in the central
western part of the country.
Petro Matad Limited is incorporated in the Isle
of Man under company number 1483V. Its registered office is at
Victory House, Prospect Hill, Douglas, Isle of Man, IM1
1EQ.