US Refinery Status: Tesoro Reports Power Outage -2-
10 Mars 2010 - 3:01PM
Dow Jones News
36,000-b/d HCU in West Plant March
set for 18 days of work in Mar;
delayed from Feb, the Co. said
on Jan 27.
Valero Norco, LA 250.0 Hydrocracker restarted Mar 9;
FCCU restarted Mar 1. Work
continues at other units including
crude and coker unit. Entire plant
was shut Feb 1 for turnaround.
Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Valero Port Arthur 325.0 44-days of work starts at late Feb.
Tx FCCU, co. said Jan. 10
77,000-b/d FCCU at reduced n/a
rates since mid-Dec for
economic reasons.
45,000 b/d HCU to undergo Spring
38 days of work in March.
Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a
rates since mid-Dec for
economic reasons.
MIDWEST
BP Toledo, OH 155.0 $400 million upgrade 2012
to start 2010.
Valero Memphis, TN 195.0 105K-B/D Crude unit, FCCU April
and alkylation unit will
shut in March for 45 days
planned maintenance, the co.
said on Jan 27.
Frontier El Dorado 135.0 Production expected to
KS fall by 700 b/d to 120,300 b/d
for February, Co. reported Feb. 8.
ROCKY MOUNTAIN
Western Bloomfield, 16.8 Co. announced plans Nov. 9
NM to idle plant and shift
production to Gallup plant.
Suncor Commerce 93.0 No. 2 Crude unit will shut for Mar 3
City, CO planned maintenance on Feb 28;
restart on Mar 3.
No. 1 Crude unit will shut for Mar 22
planned maintenance on Mar 6;
restart Mar 22.
Cryo Unit will shut for planned Apr 4
maintnenance Mar 20; restart
April 4.
Planned work at reformer unit Fall
deferred to Fall 2010 from Feb 2010
28 start date.
Tesoro Salt Lake 58.0 Major turnaround work will
Holly (NYSE:HOC)
Graphique Historique de l'Action
De Juin 2024 à Juil 2024
Holly (NYSE:HOC)
Graphique Historique de l'Action
De Juil 2023 à Juil 2024
Real-Time news about Holly Corp. (New York Stock Exchange): 0 recent articles
Plus d'articles sur Holly Corp.