Interxion to Expand in Frankfurt, Amsterdam, Dublin & Copenhagen
03 Novembre 2015 - 1:00PM
Business Wire
Additional Capacity Scheduled to Become
Available in the Second Half of 2016
INTERXION HOLDING NV (NYSE:INXN), a leading European provider of
cloud and carrier-neutral colocation data centre services, today
announced that in response to continued customer demand it will
expand in four cities: new data centres will be built in Amsterdam,
Dublin and Copenhagen, and two expansion phases will be built in
Frankfurt. When fully built, the three new data centres will have a
maximum capacity of approximately 11,900 sqm. The additional
capacity from the four city expansion is approximately 6,800 sqm
and is scheduled to become operational in the second half of
2016.
“Interxion continues to experience solid demand for its highly
connected and multi-cloud data centre capacity across key markets
in Europe," said David Ruberg, Interxion’s Chief Executive
Officer. “We continue to deploy capital to expand capacity in
a disciplined manner in response to this demand. As a result,
we are today announcing additional capacity in four markets in
which there is strong demand for further platform roll outs by
cloud providers, and early cloud adoption by enterprises and
systems integrators.”
Interxion will expand its facilities in Frankfurt by
constructing the final two phases of its FRA10 data centre (FRA10.3
and FRA10.4), each new phase of which will provide approximately
1,200 sqm of equipped space. On completion, FRA10 will have
approximately 4,800 sqm of equipped space and access to
approximately 10MW of customer-available power. FRA10.3 and FRA10.4
are both scheduled to become available in the fourth quarter of
2016. Previously announced phases, FRA10.1 and FRA10.2, are
scheduled to become available in the first and second quarter of
2016, respectively. As previously announced, capital expenditure
associated with the full build-out of FRA10 is expected to be
approximately €92 million.
In Amsterdam, Interxion will build its eighth data centre (AMS8)
which, when fully constructed, will provide approximately 8,000 sqm
of equipped space and a total of approximately 15MW of
customer-available power. The build will be done in six phases,
each of which will provide approximately 1,300 sqm of equipped
space. The first two phases are scheduled to open by the fourth
quarter of 2016.
AMS8 will be located on Interxion’s Amsterdam campus at Schiphol
Rijk, which currently provides access to more than 40 carriers and
ISPs, as well as two Internet exchanges. The capital expenditure
associated with the first two phases is expected to be
approximately €50 million.
Interxion will build its third data centre in Dublin (DUB3).
When fully constructed, DUB3 will provide a total of approximately
2,300 sqm of equipped space in four phases and total
customer-available power of approximately 5MW. It will be built on
property owned by Interxion and will provide access to nearly 40
carriers and ISPs, as well as the Irish Internet Exchange which is
based at our existing Dublin campus. The first two phases of DUB3,
which will provide a total of approximately 1,200 sqm of equipped
space, are scheduled to open in the fourth quarter of 2016. Capital
expenditure associated with the first two phases of DUB3 is
expected to be approximately €28 million.
Interxion will build its second data centre in Copenhagen
(CPH2). When fully constructed, CPH2 will provide a total of
approximately 1,600 sqm of equipped space and a customer-power
density of approximately 1.5kW per sqm. CPH2 will be built on land
next to CPH1 that is owned by Interxion and it will provide access
to more than 40 carriers and ISPs as well as the two Internet
exchanges that are based in CPH1. The first phase of CPH2, of
approximately 500 sqm, is scheduled to open in the third quarter of
2016. Capital expenditure associated with the first phase of CPH2
is expected to be approximately €4 million.
The anticipated capital spend in 2015 for these projects is
included in the 2015 capital guidance previously provided by the
Company.
About Interxion
Interxion (NYSE:INXN) is a leading provider of carrier and
cloud-neutral colocation data centre services in Europe, serving a
wide range of customers through 40 data centres in 11 European
countries. Interxion’s uniformly designed, energy efficient data
centres offer customers extensive security and uptime for their
mission-critical applications.
With over 500 connectivity providers, 20 European Internet
exchanges, and most leading cloud and digital media platforms
across its footprint, Interxion has created connectivity, cloud,
content and finance hubs that foster growing customer communities
of interest. For more information, please
visit www.interxion.com.
Forward-looking statements
This communication contains forward-looking statements that
involve risks and uncertainties. There can be no assurance that
such statements will prove to be accurate and actual results and
future events could differ materially from those anticipated in
such forward-looking statements. Factors that could cause actual
results and future events to differ materially from Interxion’s
expectations include, but are not limited to, the difficulty of
reducing operating expenses in the short term, the inability to
utilise the capacity of newly planned data centres and data centre
expansions, significant competition, the cost and supply of
electrical power, data centre industry over-capacity, performance
under service level agreements, certain other risks detailed herein
and other risks described from time to time in Interxion’s filings
with the United States Securities and Exchange Commission (the
“SEC”).
Interxion does not assume any obligation to update the
forward-looking information contained in this report.
View source
version on businesswire.com: http://www.businesswire.com/news/home/20151103005889/en/
Interxion Holding NVInvestor Relations:Jim Huseby,
+1-813-644-9399IR@interxion.com
InterXion Holding NV (NYSE:INXN)
Graphique Historique de l'Action
De Sept 2024 à Oct 2024
InterXion Holding NV (NYSE:INXN)
Graphique Historique de l'Action
De Oct 2023 à Oct 2024