TORONTO, May 5, 2021 /CNW/ - Golden Star Resources
Ltd. (NYSE American: GSS) (TSX: GSC) (GSE: GSR) ("Golden
Star" or the "Company") reports its financial and operational
results for the first quarter ended March
31, 2021. All references herein to "$" are to United States dollars.
Q1 2021 HIGHLIGHTS:
- Q1 2021 production totaled 40.1 thousand ounces ("koz") from
Wassa, in line with Q1 2020 and Q4 2020 performance. The All-In
Sustaining Cost ("AISC") for the period of $1,100 per ounce ("/oz") was slightly higher than
expected as sales lagged production by 3%.
- Mining rates of 4,499 tonnes per day ("tpd") were in line with
guidance and the 3.0 grams per tonne ("g/t") grade was in line with
the reserve grade.
- Q1 2021 saw continued investment in infill drilling and
development at Wassa, ahead of future production expansion as
described in the new technical report on Wassa filed on
March 1, 2021 (the "Wassa Technical
Report"). Q1 2021 investing activities totaled $12.8 million ("m").
- Cash increased by $5.2m in Q1
2021 to total $66.1m, with net debt
reducing in Q1 2021 by $3.9m to
$39.5m.
- The Wassa Technical report demonstrated the significant growth
potential at Wassa by outlining a mineral reserve plan with a
six-year mine life and average annual production of 177koz of gold
at an AISC of $881/oz (excluding
corporate costs). The preliminary economic assessment ("PEA") of
the potential expansion of the Southern Extension zone in the Wassa
underground mine ("Wassa Underground") outlined a further 11-year
life extension, average annual production of 294koz and an AISC of
$778/oz (excluding corporate
costs).
- In-mine exploration drilling conducted during Q1 2021 continued
to deliver positive results adjacent to the current and planned
reserve mining areas. These intercepts demonstrate the potential to
increase the size of the Wassa ore body with extensions to the main
B-Shoot, the hanging wall zone and new foot wall targets.
Table 1 – Q1 2021 Performance Summary (Continuing
Operations unless otherwise stated)
1. See "Non-GAAP
Financial Measures"
|
|
Q1
2021
|
Q1
2020
|
%change
|
|
|
|
|
|
Production -
Wassa
|
Koz
|
40.1
|
40.3
|
(1)%
|
Production – Prestea
(discontinued operation)
|
Koz
|
-
|
9.6
|
(100)%
|
Total gold
produced
|
Koz
|
40.1
|
50.0
|
(20)%
|
Gold sold -
Wassa
|
Koz
|
38.9
|
36.5
|
7%
|
Gold sold - Prestea
(discontinued operation)
|
Koz
|
-
|
9.1
|
(100)%
|
Total gold
sold
|
Koz
|
38.9
|
45.6
|
(15)%
|
Average realized gold
price (inc. Deferred Revenue)
|
$/oz
|
1,669
|
1,481
|
17%
|
|
|
|
|
|
Cash operating cost
per ounce - Wassa1
|
$/oz
|
718
|
632
|
14%
|
Cash operating cost
per ounce - Prestea1
|
$/oz
|
-
|
1,778
|
(100)%
|
Cash operating
cost per ounce - Consolidated1
|
$/oz
|
718
|
860
|
(17)%
|
All-in sustaining cost
per ounce - Wassa1
|
$/oz
|
1,100
|
952
|
16%
|
All-in sustaining cost
per ounce - Prestea1
|
$/oz
|
-
|
2,172
|
(100)%
|
All-in sustaining
cost per ounce - Consolidated1
|
$/oz
|
1,100
|
1,201
|
(8)%
|
|
|
|
|
|
Gold
revenues
|
$m
|
65.0
|
54.1
|
20%
|
Adj.
EBITDA1
|
$m
|
27.2
|
21.2
|
28%
|
Adj.
income/(loss)/share attributable to shareholders -
basic1
|
$/share
|
0.04
|
0.02
|
100%
|
|
|
|
|
|
Cash provided by
operations before working capital
|
$m
|
23.3
|
17.1
|
36%
|
Changes in working
capital and taxes paid
|
$m
|
(13.0)
|
(9.6)
|
(36)%
|
Net cash used in
investing activities
|
$m
|
(12.8)
|
(12.4)
|
3%
|
Net cash provided by
financing activities
|
$m
|
7.7
|
0.1
|
7,600%
|
Free cash
flow1
|
$m
|
(2.5)
|
(4.9)
|
49%
|
|
|
|
|
|
Cash
|
$m
|
66.1
|
41.9
|
58%
|
Net Debt
|
$m
|
39.5
|
63.4
|
38%
|
Andrew Wray, Chief Executive
Officer of Golden Star,
commented:
"Q1 2021 was a steady quarter with the mining
rate at approximately 4,500tpd and the grade close to the
reserve grade. The group cash position increased to $66.1m at the end of the quarter, as the
operating cash flow together with $8.6m of net proceeds from the At The Market
equity program during the quarter more than offset the payment of
$13m of tax relating to Q4 2020 as
well as the continued capital investment in the business. These
funds will enable the continued investment in growth and
exploration and also leave us well positioned to meet our
obligations relating to the convertible debenture as they reach
maturity in August 2021.
The highlight of the quarter was the release of the Wassa
Technical Report that demonstrates a robust reserve mine plan
followed by production set out in the PEA which identified the
potential for significant growth of the Wassa operation to a rate
of approximately 300koz each year. We look forward to updating the
market on the infill drilling program and optimization studies as
these progress. These initiatives will unlock the delivery of the
Wassa expansion and identify further opportunities to improve the
economics and lessen the environmental impact of the mine in the
future.
Our 2021 guidance remains unchanged, production of 165-175koz is
expected to be delivered at an AISC of $1,000-1,075/oz. That implies a slight increase
in the quarterly production rate for the balance of 2021, which is
expected to result from an increase in grades. This also assumes
that the paste plant is fully commissioned over the next three
months as we address some inconsistencies in paste strength results
from the test stope. We continue to see this year as one focused on
increasing investment in development and drilling activities in
order to support further volume increases which are anticipated in
turn to provide production growth and enhanced cash flow
generation.
The increased budget that was allocated to exploration in 2021
is already starting to identify opportunities for expansion of the
Wassa underground resource. The continued success of the in-mine
drilling program is identifying additional mineralization around
existing and planned reserve infrastructure. This continued success
could see a reallocation of elements of the exploration budget to
allow for further drilling of these in-mine targets with the
ambition of accelerating the process for resource inclusion."
Q1 2021 RESULTS WEBCAST AND CONFERENCE CALL
The
Company will conduct a Q1 2021 results conference call and webcast
on Thursday May 6, 2021 at
10.00 am ET.
Toll Free (North America): +1
888 390 0546
Toronto Local and International: +1 416 764
8688
Toll Free (UK): 0800 652 2435
Conference
ID: 10172867
Webcast:
https://produceredition.webcasts.com/starthere.jsp?ei=1457692&tp_key=dbcf14841e
Following the conference call, a recording will be available on the
Company's website at: www.gsr.com.
KEY EVENTS – Q1 2021
Wassa Operational Performance and Infrastructure
Investment
- Throughout Q1 2021, the mining rate averaged 4,499tpd,
representing a 4% increase on the 4,324tpd achieved in Q1 2020 and
8% higher than the 4,175tpd achieved in Q4 2020.
- Underground mined grade averaged 3.0g/t, broadly in line with
the updated underground reserve grade of 3.1g/t (announced on
March 1, 2021).
- Processing of low-grade stockpiles continued during Q1 2021,
given the continued strength of the gold price. This initiative,
which utilizes latent capacity in our process plant without
compromising gold recovery rates, contributes additional cash flow,
albeit at a slightly higher AISC than achieved by the underground
mine. This initiative contributed 3koz of production during Q1
2021.
- Investment in infrastructure continued throughout Q1 2021 to
provide additional mining flexibility with the objective of
increasing mining rates. Capital expenditure totaled $9.8m during Q1 2021.
- Paste fill plant commissioning continued during Q1 2021. Some
commissioning delays were experienced during the quarter and
although the plant is performing to design, some results from the
quality assurance testing returned lower than expected fill
strengths in the test stope, which is currently under
investigation. Test work will continue into Q2 2021 and at this
point in time any delay during the quarter is not expected to
impact on the 2021 guidance. With secondary stopes planned in H2
2021, contingency plans are also being developed to help mitigate
further delays to the filling schedule.
Wassa Technical Report
- On March 1, 2021, the Company
filed the Wassa Technical Report which includes a mineral reserve
and resource update and a PEA providing an assessment of the
potential development of the southern extension of Wassa and the
increase in mining rates to fully utilize the available process
plant capacity.
- The mineral reserve plan outlines a six-year mine life with
annual production averaging 177koz of gold at an AISC of
$881/oz (excluding corporate costs),
for a post-tax net present value ("NPV") of approximately
$336m when using the consensus gold
pricing and a discount rate of 5%. The post-tax NPV is $121m when using a base case of $1,300/oz gold price.
- The PEA represents a conservative plan that excludes
exploration opportunities from its scope and adopts the current
mining practices and equipment to deliver a robust economic outcome
while minimizing execution risk. Opportunities to improve
productivity and reduce the environmental impact of the operation
through the application of technology will be evaluated in the next
phase of work.
- The PEA outlines an 11-year mine life from the inferred mineral
resource in the southern extension zone, with total gold production
of 3.5 million ounces and average annual gold production of 294koz,
representing an increase of approximately 75% on the current
production rate at an AISC (excluding corporate costs) of
$778/oz.
- Robust economics with a post-tax NPV at a discount rate of 5%
of approximately $783 million and an
internal rate of return of 53% at the consensus long term gold
price per ounce ($1,585/oz). The
post-tax NPV is $452m when using a
base case of $1,300/oz gold price.
These values are incremental to those in the reserve plan.
COVID-19 PANDEMIC
- During Q1 2021, our operations in Ghana experienced 29 suspected COVID-19 cases
with 23 confirmed cases as at quarter end. The Company's in-house
Polymerase Chain Reaction ("PCR") testing capability allows for
rapid diagnosis and management response. This significantly reduced
the number of people required to isolate as a result of contact
tracing, supporting business continuity throughout the pandemic. As
a major employer and therefore catalyst for rural economic stimulus
in the host communities, we understand that our continuing
operations are critical to the health and well-being of our
workforce and the thousands of people that they support, both
directly and indirectly. Given the relatively low number of
confirmed and suspected COVID-19 cases, the operational impact to
date has been limited. More information on our COVID-19 management
controls can be found at www.gsr.com/responsibility/COVID-19
- Wassa Underground mine continued to operate through the
challenges posed by the COVID-19 pandemic in Q1 2021. Access to
site for the expatriate operators was possible throughout the
quarter. The reducing COVID-19 case numbers in the UK allowed for
more regular access to the operation for the corporate team towards
the end of the quarter.
- On March 29, 2021, the Wassa
medical team received their first vaccination against COVID-19, as
part of the Ghana Health Services ("GHS") vaccination program.
Following the GHS program for frontline workers, a further 635
members of the workforce and the remaining medical team members
received their first COVID-19 vaccination in April 2021 as part of the wider Western Regional
program roll out.
- Ghana continued to experience
a decline in case rates in Q1 2021. The Ghana Health Services had
reported 91,709 known cases of COVID-19, with 1,334 active cases at
April 15, 2021. A total of 5,749
positive cases were confirmed in the Western Region, where the
Wassa mine is located, of which 36 are active cases at April 15, 2021.
- Supply chains for the shipment of dore to the refinery and for
the key consumables, including cyanide, lime, grinding media, fuel
and lubricants, have remained intact throughout the pandemic. All
supply chains are being continually monitored and alternative
suppliers have been identified for essential supply chains.
Safety and Health
- For continuing operations, the all-injury frequency rate
("AIFR") as at March 31, 2021 was
2.36 and the total recordable injury frequency rate ("TRIFR") was
0.51, based on a 12-month rolling average per million hours worked.
This compares favorably to the continuing operations AIFR of 4.05
and TRIFR of 0.70 at March 31,
2020.
At The Market Equity Program
- On October 28, 2020, the Company
entered into an At The Market ("ATM") sales agreement (the "Sales
Agreement") with BMO Capital Markets Corp. ("BMO") relating to
Golden Star common shares. In
accordance with the terms of the Sales Agreement, the Company may
distribute shares of common stock having a maximum aggregate sales
price of up to $50 million from time
to time through BMO as agent for the distribution of shares or as
principal. The proceeds from the Sales Agreement will be used for
discretionary growth capital at Wassa, exploration, general
corporate purposes and working capital.
- 2,628,719 shares of common stock had been sold under the Sales
Agreement as at March 31, 2021,
generating net proceeds of $8.6
million.
- From April 1 to May 5, 2021, a
further 558,910 shares were sold, generating net proceeds of
$1.8 million.
Changes to the Board of Directors
- Karen Akiwumi-Tanoh and
Gerard De Hert have been put forward
for election as directors of the Company at the forthcoming annual
general meeting on May 6, 2021 (the
"AGM"). Robert Doyle will not be
standing for re-election at the AGM. Mr. Doyle's retirement is in
line with Golden Star's board of
directors (the "Board") mandate of a maximum term limit of 10 years
for directors. Mona Quartey will
replace Mr. Doyle as chair of the audit committee of the
Board.
- This will mean an increase in the size of the Board to 10
directors, which will allow for a proper transition over the coming
year, prior to further rotation in accordance with our policies
next year when the Board is expected to go back to nine
members.
- As a result of these changes, the female representation on the
Board will increase to 40%, reflecting a continued commitment to
inclusion and diversity throughout the Company.
Sale of Prestea - Deferred Consideration Amendment
Agreement
- On March 28, 2021, the Company
and its wholly owned subsidiadry, Caystar Holdings ("Caystar"),
entered into an agreement (the "Amendment Agreement") with Future
Global Resources Limited ("FGR") and Blue International Holdings
Limited ("BIH"), to amend the sale and purchase agreement (the
"SPA") for the sale by Caystar, and the purchase by FGR, of all the
issued and outstanding share capital of Bogoso Holdings, the holder
of 90% interest in Bogoso-Prestea.
- The staged payments that form the deferred consideration were
reprofiled to allow time for FGR to complete the environmental
bonding process for Prestea. The deferred consideration payments
will now fall due as follows:
-
- The $5 million payment that was
due on March 30, 2021 will now be
payable by no later than May 31,
2021;
- The $10 million payment that was
due to be paid on July 31, 2021 will
be brought forward for payment by no later than May 31, 2021; and
- An amount of approximately $4.6
million (comprising the net working capital adjusted
balancing payment of approximately $4.3
million and fees of approximately $0.3 million for services provided by Caystar to
FGR pursuant to a transition agreement dated September 30, 2020) will continue to fall due by
no later than July 31, 2021.
Severance Claim
- On September 15, 2020, certain
employees of the Bogoso-Prestea operating entity ("GSBPL")
initiated proceedings before the courts in Ghana claiming that the completion of the
transaction contemplated by the SPA would trigger the termination
of their existing employments, entitling them to severance
payments. GSBPL retained defense legal counsel and vigorously
defended the claim given no employment contracts were severed,
amended or modified upon the completion of the sale transaction on
September 30, 2020, and GSBPL
continues to operate with existing employment contracts and
contractual terms being honored.
- On February 16, 2021, the court
ruled in favor of GSBPL that the plaintiffs' pleadings disclosed no
reasonable cause of action. Accordingly, the plaintiffs lacked the
requisite standing or capacity to institute the action. On
March 26, 2021, the plaintiffs filed
a notice of appeal.
RECENT EVENTS - Post Q1 2021 period end
Golden Star Oil Palm Plantations investment by Royal Gold
- On April 20, 2021, Golden Star
Oil Palm Plantations Limited ("GSOPP"), a wholly-owned non-profit
subsidiary of the Company, and RGLD Gold AG, a wholly-owned
subsidiary of Royal Gold, Inc.
("Royal Gold"), entered into an agreement providing for
Royal Gold's investment in the oil
palm plantations initiative, Golden
Star's award winning flagship sustainability project.
- In consideration of the long-standing relationship with the
Wassa mine, and by extension the Wassa operations host communities,
Royal Gold has committed to provide
financial support for the activities of GSOPP that benefit the
Wassa operational communities through an annual contribution of
$150,000 during each of the next five
years. Royal Gold made its first
contribution of $150,000 to GSOPP in
April 2021. The investment will be
used to accelerate development of the Company's innovative
sustainability initiative which is aimed at creating sustainable
alternative livelihoods, bringing additional economic stimulation
and a legacy of community development to the region. The proceeds
will support the further development of palm oil plantations around
Wassa as well as activities to grow GSOPP including assessment of
downstream processing opportunities.
- GSOPP is the Company's flagship sustainability and social
enterprise initiative. It develops and operates oil palm
plantations in communities proximate to the Company's gold mining
operations, located in the Western Region of Ghana, for the benefit of members of the host
communities. The program commits to ensuring that there is zero
deforestation during the creation of a high value agribusiness on
former subsistence farms and land that has previously been used for
mining activities. Since its inception in 2006, GSOPP has developed
plantations on over 1,500 hectares of land, which support over 700
families at levels of yield three times the smallholder average in
Ghana. The activities of GSOPP
also align with the Company's wider sustainability goals of
establishing high value post-mining land uses, self-funding
re-vegetation and creation of biomass to act as a carbon sink to
offset operational emissions.
2020 Corporate Responsibility Report
- The Company published its 2020 Corporate Responsibility Report
on April 30, 2021. The report has
been prepared in accordance with the Global Reporting Initiative
Standards (Core option), the United Nations Global Compact
reporting requirements, and the Sustainability Accounting Standards
Board's ("SASB") Metals and Mining Sustainability Accounting
Standard. The report and an ESG investor presentation are available
on the Company's website at: www.gsr.com/responsibility.
- Key highlights of the report include:
-
- Leading practices in the management of the COVID-19 pandemic
resulted in minimal impact to production and, more importantly, no
lives lost to COVID-19 and limited serious health outcomes across
the workforce.
- Sustained improvement in injury frequency rates across the
organization was marred by a fatal incident at Prestea in
March 2020.
- Wassa was recognized as the safest mine in Ghana, receiving the Best Performer in
occupational health and safety at the Ghana Mining Industry
Awards.
- Golden Star continues its
leading practice performance in malaria prevention, with 2020
recording the lowest case rates and days lost to malaria on Company
record.
- The Company achieved 100% conformance with its statutory
monitoring program requirements and above 99% alignment to relevant
quality standards.
- Consistent with our Inclusion and Diversity Policy launched in
March 2020, the Company maintained
its high rates of local content, with 99% of the workforce in
Ghana being Ghanaian nationals and
59% of the workforce hailing from local host communities.
FY 2021 PRODUCTION AND COST GUIDANCE
Table 2: FY 2021 Production and Cost Guidance
|
Unit
|
2021
Guidance
|
Production and
cost guidance
|
|
|
Gold
Production
|
(koz)
|
165-175
|
Cash Operating
cost1
|
($/oz)
|
660-700
|
AISC1
|
($/oz)
|
1,000-1,075
|
|
|
|
Capital expenditure
guidance
|
($m)
|
|
Sustaining
Capital2
|
($m)
|
26-28
|
Expansion
Capital2
|
($m)
|
19-22
|
Total Capital
Expenditure
|
($m)
|
45-50
|
|
|
|
Capitalized
exploration
|
($m)
|
4
|
Expensed
exploration
|
($m)
|
11
|
Total
Exploration
|
($m)
|
15
|
Total Capital and
exploration expenditure
|
($m)
|
60-65
|
Notes: 1.
See "Non-GAAP Financial Measures".
|
2. Expansion capital
are those costs incurred at new operations and costs related to
major projects at existing operations where these projects will
materially increase production. All other costs relating to
existing operations are considered sustaining capital.
|
FY 2021 Production Guidance
- Wassa production guidance remains unchanged at 165-175koz in
2021, based on the following assumptions:
-
- The processing of low grade stockpiles is expected to continue
throughout 2021 with a little under 1,000tpd of stockpiled material
expected to be processed at a grade of approximately 0.6g/t. This
initiative remains subject to gold prices sustaining near current
levels.
- We expect mining rates for 2021 to be in excess of 4,500tpd, in
line with the 4,469tpd achieved in 2020. The investment in drilling
and development in 2020 and 2021 will unlock further increases in
the mining rates in the future.
- Underground mined grades are expected to remain in line with
the average grade achieved in 2020 and the recently updated reserve
grade. The grade achieved during Q1 2021 was a little below the
2020 performance.
- The 2020 infill drilling program has resulted in 80% of the
2021 mine plan comprising of ounces from the measured resource
category.
- The paste fill strength issues encountered in the recently
filled test stope are expected to be resolved during Q2 2021.
Cost Guidance
- The $660/oz to $700/oz cash operating cost guidance for 2021
remains unchanged.
- The 2021 AISC guidance of $1,000-1,075 also remains unchanged. Q1 2021
performance and the higher than budgeted gold price result in an
expectation of delivery of the upper half of the guidance
range.
Capital Expenditure
- The capital programs at Wassa are expected to total
$45m to $50m in 2021.
- Activities will focus on drilling and development.
- In order to ensure a robust balance sheet through the repayment
of the 7% convertible debentures in August
2021, and to allow for a ramp up in drilling and development
activities, 40% of the spend is budgeted for H1 2021 and the
remaining 60% during H2 2021.
- Sustaining capital is expected to total $26m to $28m, of
which;
-
- $16m is allocated to capitalized
development
- $4m to $5m to the expansion of the tailing storage
facilities
- Expansion capital is expected to total $19m to $22m, of
which;
-
- $7m to $8m is allocated to capitalized drilling,
- $7m to ventilation infrastructure
and $4m to capitalized
development.
Genser Lease Liability
In accordance with IFRS 16 - Leases, the completion of the
construction of the Genser Energy Ghana ("Genser") thermal power
plant resulted in the inclusion of a non-cash $33.5 million right-to-use asset addition to
property, plant and equipment and the recognition of a
corresponding lease liability during Q1 2021. An element of the
cost of power supplied by the Genser plant is accounted for as
depreciation of the capital asset and as a finance cost.
Approximately $20/oz of the power
cost is not being allocated to cash operating costs or AISC in
comparison with 2020.
2021 Exploration Budget
- A $15m exploration budget has
been approved for 2021 which will be invested as follows:
-
- $7m will be invested in and
around the Wassa mine. This work will include the continued wide
spaced drilling up-dip and down-dip of the current resources and
reserves as well as drill testing of seven targets to the south and
east of the main Wassa deposit.
- The balance of the budget was expected to be allocated to the
regional exploration program. This is currently being reviewed
following the in-mine drilling success achieved through Q4 2020 and
Q1 2021 which could result in some of the regional exploration
budget being reallocated to further drilling of these in-mine
targets.
SUMMARY OF CONSOLIDATED OPERATIONAL RESULTS – Q1 2021
Wassa Operational Overview
Gold production from Wassa was 40.1koz in Q1 2021, in line with
the 40.3koz produced during Q1 2020. Higher processing volumes were
driven by the processing of low-grade stockpile tonnes which
impacted on overall processed grade.
Recovery
The recovery was 95.3% for Q4 2021, remaining consistent with Q1
2020, despite the increase in the volume of low grade stockpiles
processed which resulted in a 13% reduction in the blended grade
processed.
Wassa Underground
Wassa Underground produced 36.9koz of gold (approximately 92% of
Wassa's total production) in the first quarter of 2021, compared to
the 39.9koz produced in Q1 2020. Wassa Underground mining rates
averaged 4,499tpd in Q1 2021, 4% higher than the mining rate of
4,324tpd achieved in Q1 2020 and 8% higher than 4,175tpd in Q4
2020.
The underground grade averaged 2.96g/t during the quarter,
slightly higher than Q1 2020 and broadly in line with the reserve
grade.
Wassa Main
Pit/Stockpiles
Low grade stockpiles from the Wassa main pit of 119.1kt with an
average grade of 0.71 g/t were blended with the Wassa Underground
ore during Q1 2021 and yielded 3.2koz of gold, compared to 0.5koz
in Q1 2020. There has been no material impact on recoveries and the
Company will continue to opportunistically process low grade
stockpiles in 2021 should the current gold price environment
continue.
Unit costs
The unit cost performance remained robust during Q1 2021. The
mining unit cost of $33.2/t of ore
mined was 4% higher than in Q1 2020 and in line with Q4 2020
performance. Higher plant throughput benefited processing costs
which totaled $17.2/t of ore
processed, 13% lower than the $19.7/t
achieved in Q1 2020 and 19% lower than Q4 2020.
Costs per ounce
Cost of sales per ounce increased 17% to $994/oz in Q1 2021, relative to Q1 2020, due to
increased mine operating costs, royalties and depreciation costs
and a reduction in operating costs to metal inventory credit partly
offset by higher gold ounces sold.
Cash operating cost per ounce increased 14% to $718 for Q1 2021 compared to Q1 2020 mainly due
to:
- higher processing costs associated with increased plant
throughput from low grade stockpiles
- higher labor costs driven by year-on-year inflationary
increases
- increased maintenance on drill rigs, haul trucks and processing
plant
The above increases were in part offset by an increased sold
ounce base relative to Q1 2020.
AISC per ounce increased 15% to $1,100 in Q1 2021 compared to Q1 2020 due to a
combination of:
- increased cash operating costs as outlined above
- increased royalties resulting from the higher prevailing gold
price
- higher sustaining capital expenditure
The above factors were also offset by the higher gold sales.
Projects update
- The instability of the grid power supply that caused
operational challenges during H2 2020 has now largely been
addressed by the commissioning of the Genser power plant. This
captive supply significantly reduced the reliance on grid power
during the quarter and provided the operation with a stable supply
at an attractive power cost, following the successful commissioning
towards the end of January.
- Paste fill plant commissioning continued during Q1 2021
including underground infrastructure, reticulation system, dump
valve and shotcreting equipment and batch plant. Some commissioning
delays were experienced during the quarter, including impacts of
the Covid-19 pandemic, with the commissioning team required to
isolate for two weeks due to positive cases and contact tracing.
The plant is performing to design, however, some results of quality
assurance testing returned lower than expected fill strengths in
the test stope, which is currently under investigation. Test work
will continue into Q2 2021 and at this point in time this delay is
not expected to impact on the 2021 guidance. With secondary stopes
planned in H2 2021, contingency plans are also being developed in
the event of further delays to the filling schedule.
Capital expenditures
- Capital expenditures for Q1 2021 totaled $9.6m, in line with expenditure in Q1 2020. The
Wassa management team continued to focus its efforts on critical
development spend in order to support the medium-term growth of the
underground operation including:
-
- sustaining capital on capitalized underground development
activities of $3.1m
- expansion of the TSF of $2.0m
- growth capital on exploration drilling of $1.4m related primarily to Wassa up-dip and
down-dip extensions
- development costs for increased future production of
$0.9m
- infill drilling of the PEA areas from 570 Level ("570 DDD") of
$0.7m
Wassa underground drilling
During Q1 2021, the Wassa
underground drilling program totaled 14,440 metres for a total cost
(drilling and assay) of $1.9m.
Three underground rigs focussed on converting existing indicated
resources to measured resources inside the mine, while two rigs
focussed on inferred to indicated resource conversion south of the
existing measured and indicated resources, in the PEA area. This
drill program is separate to the exploration budget and flows
through the operating costs and capital investing activities.
- Resource infill drilling - During Q1 2021, the program focussed
on conversion of indicated resources to measured resources, with a
total of 8,590 metres drilled for a total cost of $1.1m. This program is expensed and is expected
to total 33,500 metres during 2021 for a budget of $4.2m.
- Infill drilling of the Southern Extensions (PEA mining areas) -
During Q1 2021, the program focused on conversion of inferred
resources to indicated resources in Panel 4. Drilling totaled 5,850
metres for a cost of $0.7m. This
program is capitalized and is expected to total 38,600 metres
during 2021, for a total program cost of $5.3m. This drilling takes place from the 570
diamond drill decline.
EXPLORATION
During Q1 2021, $2.2 million was
invested in exploration at Wassa and the regional HBB licenses, of
which $1.4m of Wassa in-mine
exploration was capitalized and the remaining balance was expensed.
The 2021 exploration budget totals $15m, of which $4m
is expected to be capitalized and $11m expensed.
Wassa – In-mine exploration
During Q1 2021, two
surface drill rigs continued the testing of targets up-dip and
down-dip of the existing Wassa reserve. Following on from the five
holes and 3,417 meters drilled during Q4 2020, a total of nine
holes were completed for 6,348 meters during Q1 2021. The initial
up-dip and down-dip program is expected to total 10,000 metres in
2021.
The following table presents a summary of the results of
exploration drilling at Wassa during Q1 2021:
Table 3: Q1 2021 Exploration Drilling Results Identify
Extensions of the Wassa Underground Mineralization
Hole
ID
|
Azimuth
|
Dip
|
From
(metres)
|
To
(metres)
|
Drilled Width
(metres)
|
Estimated
True Width
(metres)
|
Grade Au
(g/t)
|
Drilling
target
|
BSDD20-006
|
89.1
|
-55.7
|
240.0
|
243.0
|
3.0
|
2.6
|
1.7
|
Up-dip
|
BSDD20-006
|
88.8
|
-54.2
|
494.0
|
497.0
|
3.0
|
2.1
|
2.2
|
Up-dip
|
BSDD20-006
|
89.0
|
-53.7
|
507.0
|
519.0
|
12.0
|
8.5
|
1.17
|
Up-dip
|
BSDD21-005D1
|
83.7
|
-71.3
|
456.0
|
463.0
|
7.0
|
5.7
|
1.72
|
Down-dip
|
BSDD21-005D1
|
79.4
|
-72.0
|
522.0
|
527.0
|
5.0
|
3.7
|
4.63
|
Down-dip
|
BSDD21-001
|
No Significant
Intersections
|
Up-dip
|
BSDD21-002
|
95.0
|
-61.2
|
386.0
|
409.0
|
23.0
|
17.0
|
3.66
|
Down-dip
|
Including
|
95.0
|
-61.2
|
394.0
|
397.0
|
3.0
|
2.2
|
11.92
|
Down-dip
|
Including
|
95.1
|
-61.1
|
402.0
|
406.0
|
4.0
|
3.0
|
4.78
|
Down-dip
|
BSDD21-003
|
91.0
|
-58.8
|
206.0
|
213.2
|
7.2
|
5.5
|
2.78
|
Up-dip
|
BSDD21-003
|
90.7
|
-58.4
|
248.0
|
252.0
|
4.0
|
3.4
|
1.81
|
Up-dip
|
BSDD21-003
|
91.4
|
-57.8
|
301.5
|
305.5
|
4.0
|
3.3
|
3.53
|
Up-dip
|
BSDD21-004
|
81.5
|
-70.4
|
702.0
|
704.0
|
2.0
|
1.5
|
6.78
|
Down-dip
|
BSDD21-004
|
83.0
|
-70.5
|
792.2
|
799.2
|
7.0
|
5.8
|
3.8
|
Down-dip
|
BSDD21-005
|
76.9
|
-73.9
|
74.0
|
76.0
|
2.0
|
1.8
|
9.74
|
Down-dip
|
BSDD21-005
|
75.4
|
-74.4
|
153.7
|
156.0
|
2.3
|
1.8
|
13.3
|
Down-dip
|
BSDD21-006
|
86.6
|
-67.7
|
581.0
|
587.0
|
6.0
|
3.6
|
1.8
|
Down-dip
|
The up-dip drilling, testing the extensions of gold
mineralization above the existing and planned mining stopes, was
completed during the quarter. The results include the following
highlights:
- BSDD21-003 (up-dip) intercepting 5.5 metres at 2.8g/t,
3.4 metres at 1.8g/t and 3.3 metres at 3.5g/t. These mineralized
intercepts are c.150 metres up-dip of the previous surface drilling
which has intercepted similar widths and grades.
Down-dip drilling is expected to continue in Q2 2021. The
results gathered during Q1 2021 included the following
highlights:
- BSDD21-002 (down-dip) intercepting 17 metres at 3.7g/t
which is an isolated hanging wall zone of mineralization which will
require further follow up drilling.
- BSDD21-004 (down-dip) intercepting 5.8 metres at 3.8g/t,
which was drilled c.150 metres below BSDD21-002, on section 20000N,
did not intersect the HW zone but did intercept the projected
extension of the main B Shoot mineralization c.300 metres below the
current reserve. This hole is important in that it demonstrates
that the B Shoot mineralization extends below the current reserve
therefore warranting further drilling in this area.
- BSDD21-005D1 (down-dip) intercepting 3.7 metres at 4.6
g/t c.150 metres down dip of BSDD20-005M which intersected 18.1 metres grading 3.6
g/t , c.65 metres below the existing reserve which now extends this
mineralization over 200 metres below the current planned stoping.
Further infill drilling will be evaluated upon completion of all of
the down dip drilling in Q2 2021.
Exploration programs for Q2 2021 will continue testing the
down-dip extensions of mineralization. Once the drilling down-dip
below the existing reserve has been completed, follow-up drilling
will be conducted to further test significant up-dip intersections,
reducing the 200 metres spacing of this initial program to 50
metres. This tighter drill spacing has been planned around the
significant intersection on section 19200N, BSDD20-003 which
intersected 20.9 metres grading 6.9 g/t. Should the closer drill
spacing on this target continue to intersect significant widths and
grades then additional resources, close to the existing underground
infrastructure, could be added.
Wassa – Near-mine exploration
The diamond and reverse circulation drill testing of seven
additional targets outside of the main Wassa deposit will commence
in Q2 2021. In addition to the reverse circulation and diamond
drilling on other targets, initial air core drilling of a soil
anomaly south east of the Wassa trend will be conducted.
HBB – Regional exploration
Exploration work testing 11 prioritized targets along the HBB
trend commenced in Q1 2021. Community sensitization and crop
compensation commenced on two of the southern targets. Air core
drill pads were constructed at the Seikrom target in preparation of
the rig arrival in Q2 2021. In addition to drill pad and access
construction, line cutting ahead of the ground geophysics programs
commenced. The geophysics crews are scheduled to arrive in Q2
2021.
FINANCIAL PERFORMANCE SUMMARY
Please see the separate financial statements and management's
discussion and analysis for the detailed discussion on the
financial results for the three months ended March 31, 2021.
Table 4 – Financial Performance Summary (continuing
operations) - Three months ended March 31,
2021
1. See "Non-GAAP
Financial Measures"
|
|
Q1 2021
|
Q1
2020
|
%
change
|
|
|
|
|
|
Realized gold price -
spot sales
|
$/oz
|
1,780
|
1,612
|
10%
|
Realized gold price -
Streaming agreement1
|
$/oz
|
784
|
628
|
25%
|
Realized gold
price – Consolidated
|
$/oz
|
1,669
|
1,481
|
13%
|
|
|
|
|
|
Gold
revenues
|
$m
|
65.0
|
54.1
|
20%
|
Cost of
sales
|
$m
|
31.4
|
26.0
|
21%
|
Depreciation and
amortization
|
$m
|
7.3
|
5.1
|
43%
|
Mine operating
profit
|
$m
|
26.3
|
23.0
|
14%
|
|
|
|
|
|
Corporate general and
administrative expense
|
$m
|
5.0
|
5.2
|
(4)%
|
Exploration
expense
|
$m
|
0.8
|
0.7
|
14%
|
Share based
compensation expense
|
$m
|
0.6
|
0.9
|
(33)%
|
Other
expenses
|
$m
|
2.9
|
0.6
|
383%
|
Gain on fair value of
derivative financial instruments, net
|
$m
|
(7.2)
|
(4.1)
|
76%
|
Income before finance
and tax
|
$m
|
24.3
|
19.6
|
24%
|
EBITDA
|
$m
|
31.6
|
24.7
|
28%
|
Adj.
EBITDA
|
$m
|
27.2
|
21.2
|
28%
|
|
|
|
|
|
Finance
Expense
|
$m
|
3.7
|
3.6
|
3%
|
Tax
expense
|
$m
|
9.7
|
8.2
|
18%
|
Net income
|
$m
|
10.8
|
7.7
|
40%
|
Net income per
share
|
$/share
|
0.08
|
0.06
|
33%
|
Adj. income per
share attributable to shareholders -
basic1
|
$/share
|
0.04
|
0.02
|
100%
|
|
|
|
|
|
Cash provided by
operations before working capital
|
$m
|
23.3
|
17.1
|
36%
|
Changes in working
capital and taxes paid
|
$m
|
(13.0)
|
(9.6)
|
(36)%
|
Net cash used in
investing activities
|
$m
|
(12.8)
|
(12.4)
|
3%
|
Net cash provided by
financing activities
|
$m
|
7.7
|
0.1
|
7,600%
|
|
|
|
|
|
Free cash
flow
|
$m
|
(2.5)
|
(4.9)
|
49%
|
Notes: 1.
Includes cash proceeds and deferred revenue
|
Discussion on Q1 2021 Financials
- Realized gold price - Including the unwinding of the
deferred revenue from the streaming agreement with RGLD Gold AG,
the realized gold price averaged $1,669/oz. The realized gold price for spot sales
of $1,780/oz in Q1 2021 compared
favorably to the $1,612/oz achieved
in Q1 2020.
- Revenue totaled $65m in Q1
2021, 20% higher than $54.1m in Q1
2020 due to a 13% increase in the average realized gold price and a
7% increase in gold ounces sold.
- Depreciation increased to $7.3m during the quarter as a result of the
higher capital base attributable to the completion of the
infrastructure projects at the end of FY 2020, which included the
paste fill plant. Depreciation is expected to continue at this
elevated level and increase in line with the production rate.
- Corporate general and administrative expense amounted to
$5m in Q1 2021, a 4% decrease
compared to $5.2m.
- Gain on fair value of derivative financial liabilities
totaled $7.2m during Q1 2021, this
included:
-
- Hedging - During Q1 2021, a number of the original hedge
contracts matured with no realized losses associated with the
contracts during Q4 2020, however, the Company recognized an
unrealized gain of $4.8m during the
quarter. At the end of Q1 2021, the outstanding zero cost collars
totaled 76.6koz with a floor price of $1,600/oz and a ceiling of $2,176/oz in 2021 and $2,188/oz in 2022. These positions mature at a
rate of 10.9koz per quarter to December
2022.
- 7% Convertible debentures - The fair value of the
convertible derivative reduced by $2.4m during the quarter. The convertibles mature
in August 2021 and the Company
intends to repay the facility using its current cash and available
liquidity.
- EBITDA from continuing operations amounted to
$31.6m for Q1 2021, 28% higher than
the $24.7m achieved in Q1 2020 as a
result of the increased gold price and higher gold sales.
- Adjusted EBITDA totaled $27.2m, representing a 28% increase on the
$21.2m achieved in Q1 2020. The
adjustments applied include:
-
- The gain on fair value of financial instruments of $(7.2)m (Q1 2020 - $(4.1)m)
- Other expenses of $2.9m (Q1 2020
- $0.6m)
- Adjusted net income attributable to Golden Star shareholders (see "Non-GAAP
Financial Measures" section) was $4.4m or $0.04
basic income per share in Q1 2021 compared to $2.2m or $0.02
basic income per share in Q1 2020. This was impacted by the higher
depreciation charge and gold sales being lower than production
during the quarter. Adjusted net income attributable to
Golden Star shareholders reflects
adjustments for non-recurring and abnormal items which are mostly
non-cash in nature, including:
-
- The gain on fair value of financial instruments of $(7.2)m
- Other expenses of $0.5m
- Loss allowance on deferred consideration on the sale of Prestea
$2.1m
- Working capital and taxes paid - The working capital
balances were neutral during Q1 2021 with a change of $0.1m. $13.2m of
income tax liabilities, relating to Q4 2020, were paid during the
quarter.
- Investing activities - Net cash used in investing
activities totaled $12.8m which
includes the following cash flows:
-
- Additions to mining interests $9.8m
- Change in accounts payable and deposits on mine equipment and
material $2.8m which is largely the
payment of capital investments accrued for in Q4 2020
- Net cash from financing activities totaled $7.7m. This includes the $8.6m of net proceeds from the ATM program
received during the quarter.
- Free cash flow - During Q1 2021, continuing operations
incurred a free cash outflow of $2.5m
as a result of gold sales being 1.2koz lower than production,
significant capital investment during the quarter and the
$13.2m tax payment relating to Q4
2020.
Financial position
The Company held $66.1m of cash
and cash equivalents and $105.6m of
debt, for net debt of $39.5m as at
March 31, 2021. The net debt position
improved by $3.9m during Q1 2021
primarily as a result of the $5.3m
increase in the cash position following the use of the ATM program
during the quarter. The table below summarizes the financial
position of the Company:
Table 5 – Financial Position - Three months ended
March 31, 2021
|
|
Q1
2021
|
Q1
2020
|
%
change
|
|
|
|
|
|
Summary of debt
facilities
|
|
|
|
|
Macquarie Credit
Facility
|
$m
|
55.1
|
57.7
|
(5)%
|
Convertible
Debentures
|
$m
|
50.5
|
47.6
|
6%
|
Gross Debt
Position
|
$m
|
105.6
|
105.3
|
-
|
|
|
|
|
|
Cash
Position
|
$m
|
66.1
|
41.9
|
58%
|
Net
Debt
|
$m
|
39.5
|
63.4
|
(38)%
|
Company Profile:
Golden Star is an established
gold mining company that owns and operates the Wassa underground
mine in Ghana, West Africa.
Listed on the NYSE American, the Toronto Stock Exchange and the
Ghana Stock Exchange, Golden Star is
focused on delivering strong margins and free cash flow from the
Wassa mine. As the winner of the Prospectors & Developers
Association of Canada 2018
Environmental and Social Responsibility Award, Golden Star remains committed to leaving a
positive and sustainable legacy in its areas of operation
Statements Regarding Forward-Looking Information
Some
statements contained in this news release are "forward-looking
statements" within the meaning of the Private Securities Litigation
Reform Act of 1995 and "forward looking information" within the
meaning of Canadian securities laws. Forward looking statements and
information include but are not limited to, statements and
information regarding: present and future business strategies and
the environment in which Golden Star
will operate in the future, including the price of gold,
anticipated costs and ability to achieve goals; gold production,
cash operating costs, AISC and capital expenditure estimates and
guidance for 2021, and the Company's achievement thereof; the
sources of gold production at Wassa during 2021; the processing of
low grade stockpiles at Wassa for the remainder of the year;
expected grade and mining rates for 2021; the ability to improve
recovery; the ability to achieve production growth; the ability to
improve cash generation; the ability to increase the size of the
Wassa ore body; the commissioning of the paste fill plant project
and timing thereof; the improvements to be realized through the
delivery of a range of operational initiatives; the ability to
improve the scale of operations and margin at Wassa; the expected
allocation of the Company's capital expenditures; implementation of
the Company's exploration programs and the timing thereof; the
anticipated exploration activities for 2021; the ability to expand
the Company and its production profile through exploration and
development activities; the potential impact of the COVID-19
pandemic on the Company's operations and the ability to mitigate
such impact; the securing of adequate supply chains for key
consumables; the ability to continue to ship gold across borders
and to refine doré at the South African refinery; the receipt by
Golden Star of the deferred
consideration from the sale of Bogoso-Prestea, and the potential
amount and timing thereof; the anticipated effectiveness of the
hedging program over the next 12 months; and the Company having
sufficient cash available to support its operations and mandatory
expenditures for the next twelve months. Generally, forward-looking
information and statements can be identified by the use of
forward-looking terminology such as "plans", "expects", "is
expected", "budget", "scheduled", "estimates", "forecasts",
"intends", "anticipates", "believes" or variations of such words
and phrases (including negative or grammatical variations) or
statements that certain actions, events or results "may", "could",
"would", "might" or "will be taken", "occur" or "be achieved" or
the negative connotation thereof. Investors are cautioned that
forward-looking statements and information are inherently uncertain
and involve risks, assumptions and uncertainties that could cause
actual facts to differ materially. Such statements and information
are based on numerous assumptions regarding present and future
business strategies and the environment in which Golden Star will operate in the future.
Forward-looking information and statements are subject to known and
unknown risks, uncertainties and other important factors that may
cause the actual results, performance or achievements of
Golden Star to be materially
different from those expressed or implied by such forward-looking
information and statements, including but not limited to: gold
price volatility; discrepancies between actual and estimated
production; mineral reserves and resources and metallurgical
recoveries; mining operational and development risks; liquidity
risks; suppliers suspending or denying delivery of products or
services; regulatory restrictions (including environmental
regulatory restrictions and liability); actions
by governmental authorities; the speculative nature of gold
exploration; ore type; the global economic climate; share price
volatility; the availability of capital on reasonable terms or at
all; risks related to international operations, including economic
and political instability in foreign jurisdictions in which
Golden Star operates; risks related
to current global financial conditions; actual results of current
exploration activities; environmental risks; future prices of gold;
possible variations in mineral reserves and mineral resources,
grade or recovery rates; mine development and operating risks; an
inability to obtain power for operations on favourable terms or at
all; mining plant or equipment breakdowns or failures; an inability
to obtain products or services for operations or mine development
from vendors and suppliers on reasonable terms, including pricing,
or at all; public health pandemics such as COVID-19, including
risks associated with reliance on suppliers, the cost, scheduling
and timing of gold shipments, uncertainties relating to its
ultimate spread, severity and duration, and related adverse effects
on the global economy and financial markets; accidents, labor
disputes and other risks of the mining industry; delays in
obtaining governmental approvals or financing or in the completion
of development or construction activities; litigation risks; and
risks related to indebtedness and the service of such indebtedness.
Although Golden Star has attempted
to identify important factors that could cause actual results to
differ materially from those contained in forward-looking
information and statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can
be no assurance that future developments affecting the Company will
be those anticipated by management. Please refer to the discussion
of these and other factors in management's discussion and analysis
of financial conditions and results of operations for the year
ended December 31, 2020, and in our
annual information form for the year ended December 31, 2019 as filed on SEDAR
at www.sedar.com. The forecasts contained in this press
release constitute management's current estimates, as of the date
of this press release, with respect to the matters covered thereby.
We expect that these estimates will change as new information is
received. While we may elect to update these estimates at any time,
we do not undertake any estimate at any particular time or in
response to any particular event.
Non-GAAP Financial Measures
In this press release, we use the terms "cash operating cost",
"cash operating cost per ounce", "all-in sustaining costs", "all-in
sustaining costs per ounce", "adjusted net (loss)/income
attributable to Golden Star
shareholders", "adjusted (loss)/income per share attributable to
Golden Star shareholders", "cash
provided by operations before working capital changes", and "cash
provided by operations before working capital changes per share -
basic".
"Cost of sales excluding depreciation and amortization" as found
in the statements of operations includes all mine-site operating
costs, including the costs of mining, ore processing, maintenance,
work-in-process inventory changes, mine-site overhead as well as
production taxes, royalties, severance charges and by-product
credits, but excludes exploration costs, property holding costs,
corporate office general and administrative expenses, foreign
currency gains and losses, gains and losses on asset sales,
interest expense, gains and losses on derivatives, gains and losses
on investments and income tax expense/benefit.
"Cost of sales per ounce" is equal to cost of sales excluding
depreciation and amortization for the period plus depreciation and
amortization for the period divided by the number of ounces of gold
sold (excluding pre-commercial production ounces sold) during the
period.
"Cash operating cost" for a period is equal to "cost of sales
excluding depreciation and amortization" for the period less
royalties, the cash component of metals inventory net realizable
value adjustments, materials and supplies write-off and severance
charges, and "cash operating cost per ounce" is that amount divided
by the number of ounces of gold sold (excluding pre-commercial
production ounces sold) during the period. We use cash operating
cost per ounce as a key operating metric. We monitor this measure
monthly, comparing each month's values to prior periods' values to
detect trends that may indicate increases or decreases in operating
efficiencies. We provide this measure to investors to allow them to
also monitor operational efficiencies of the Company's mines. We
calculate this measure for both individual operating units and on a
consolidated basis. Since cash operating costs do not incorporate
revenues, changes in working capital or non-operating cash costs,
they are not necessarily indicative of operating profit or cash
flow from operations as determined under IFRS. Changes in numerous
factors including, but not limited to, mining rates, milling rates,
ore grade, gold recovery, costs of labor, consumables and mine site
general and administrative activities can cause these measures to
increase or decrease. We believe that these measures are similar to
the measures of other gold mining companies, but may not be
comparable to similarly titled measures in every instance.
"All-in sustaining costs" commences with cash operating costs
and then adds the cash component of metals inventory net realizable
value adjustments, royalties, sustaining capital expenditures,
corporate general and administrative costs (excluding share-based
compensation expenses and severance charges), and accretion of
rehabilitation provision. For mine site all-in sustaining costs,
corporate general and administrative costs (excluding share-based
compensation expenses and severance charges) are allocated based on
gold sold by each operation. "All-in sustaining costs per ounce" is
that amount divided by the number of ounces of gold sold (excluding
pre-commercial production ounces sold) during the period. This
measure seeks to represent the total costs of producing gold from
current operations, and therefore it does not include capital
expenditures attributable to projects or mine expansions,
exploration and evaluation costs attributable to growth projects,
income tax payments, interest costs or dividend payments.
Consequently, this measure is not representative of all of the
Company's cash expenditures. In addition, the calculation of all-in
sustaining costs does not include depreciation expense as it does
not reflect the impact of expenditures incurred in prior periods.
Therefore, it is not indicative of the Company's overall
profitability. Share-based compensation expenses are also excluded
from the calculation of all-in sustaining costs as the Company
believes that such expenses may not be representative of the actual
payout on equity and liability based awards.
The Company believes that "all-in sustaining costs" will better
meet the needs of analysts, investors and other stakeholders of the
Company in understanding the costs associated with producing gold,
understanding the economics of gold mining, assessing the operating
performance and the Company's ability to generate free cash flow
from current operations and to generate free cash flow on an
overall Company basis. Due to the capital intensive nature of the
industry and the long useful lives over which these items are
depreciated, there can be a disconnect between net earnings
calculated in accordance with IFRS and the amount of free cash flow
that is being generated by a mine. In the current market
environment for gold mining equities, many investors and analysts
are more focused on the ability of gold mining companies to
generate free cash flow from current operations, and consequently
the Company believes these measures are useful non-IFRS operating
metrics ("non-GAAP measures") and supplement the IFRS disclosures
made by the Company. These measures are not representative of all
of Golden Star's cash expenditures
as they do not include income tax payments or interest costs.
Non-GAAP measures are intended to provide additional information
only and do not have standardized definitions under IFRS and should
not be considered in isolation or as a substitute for measures of
performance prepared in accordance with IFRS. These measures are
not necessarily indicative of operating profit or cash flow from
operations as determined under IFRS.
"Adjusted net (loss)/income attributable to Golden Star shareholders" is calculated by
adjusting net (loss)/income attributable to Golden Star shareholders for (gain)/loss on fair
value of financial instruments, share-based compensation expenses,
severance charges, loss/(gain) on change in asset retirement
obligations, deferred income tax expense, non-cash cumulative
adjustment to revenue and finance costs related to the Streaming
Agreement, and impairment. The Company has excluded the non-cash
cumulative adjustment to revenue from adjusted net income/(loss) as
the amount is non-recurring, the amount is non-cash in nature and
management does not include the amount when reviewing and assessing
the performance of the operations. "Adjusted (loss)/income per
share attributable to Golden Star
shareholders" for the period is "Adjusted net (loss)/income
attributable to Golden Star
shareholders" divided by the weighted average number of shares
outstanding using the basic method of earnings per share.
For additional information regarding the Non-GAAP financial
measures used by the Company, please refer to the heading "Non-GAAP
Financial Measures" in the Company's Management Discussion and
Analysis of Financial Condition and Results of Operations for the
year ended December 31, 2020 and the
three months ended March 31, 2021,
which are available at www.sedar.com.
View original content to download
multimedia:http://www.prnewswire.com/news-releases/golden-star-resources-reports-results-for-the-first-quarter-2021-301284906.html
SOURCE Golden Star Resources Ltd.