Maxim Power Corp. ("
MAXIM" or the
"
Corporation") (TSX: MXG) announced today that it
is proceeding with the Corporation's project to expand M2 into a
combined cycle gas turbine (
“CCGT”) facility
through the installation of heat recovery technology. The CCGT
expansion project is anticipated to increase total generation
capacity from 204 MW to approximately 300 MW and improve
operational efficiency resulting in lower operating and maintenance
costs per MWh. The current estimated cost of the CCGT expansion
project is $125 million before financing costs. MAXIM anticipates
the expansion will commence commercial operations during December
2022.
The CCGT expansion project is being financed
with debt, existing cash, and cash flow from operations during the
construction period. As of this date, MAXIM forecasts it will have
sufficient liquidity to complete the CCGT expansion project.
EPC Contract
MAXIM, through a wholly owned subsidiary, has
entered into an Engineering, Procurement, and Construction
("EPC") contract for the CCGT expansion project.
The EPC Contractor is a joint venture between PCL Industrial
Management Inc. and Overland Contracting Canada Inc., a Black &
Veatch company, who are the same parties that constructed the
existing M2 simple cycle plant. The EPC Contractor has agreed to
complete and deliver the expanded plant as a fixed-price, turn-key
project. The EPC contract value is approximately $86 million and
the remaining cost of $39 million are owner's costs for activities
that MAXIM is responsible for.
M2 will continue to operate in simple cycle mode
during construction. Commissioning of the expanded facility is
expected to occur over a 3-month period during which there will be
periodic outages of the existing M2 plant while work is carried out
to connect this plant to the heat recovery technology.
Financing Arrangements
MAXIM has amended its senior secured credit
facility. The amended senior secured credit facility has been
arranged by ATB and Fiera Private Debt and the aggregate borrowing
base thereunder has been increased to $105 million to provide for
construction financing, of which $28.5 million is currently drawn,
$62.4 million is available for construction and the remainder
available for general corporate use and letters of credit. The
construction facilities of up to $62.4 million consist of two
non-revolving construction loans and a $5 million revolving credit
facility. The construction loans have amortization requirements
ranging from five to ten years commencing when construction of the
CCGT expansion is complete. All loans under the senior secured
credit facility mature on June 30, 2026.
MAXIM has also extended the maturity date of its
current subordinated convertible secured credit facility to provide
additional construction financing, if needed. Total capacity under
this credit facility is unchanged at $75 million of which $29.4
million is currently drawn. This facility matures on September 25,
2026.
About MAXIM
Based in Calgary, Alberta, MAXIM is one of
Canada’s largest truly independent power producers. MAXIM is now
focussed entirely on power projects in Alberta. Its core asset –
the 204 MW H.R. Milner Plant (“M2”), in Grande Cache, AB – is a
state-of-the-art natural gas-fired power plant that commissioned in
Q2, 2020. MAXIM is currently increasing the capacity of M2 to
approximately 300 MW and concurrently will realize an improvement
in the efficiency of the plant by investing in heat recovery
combined cycle technology. In addition, MAXIM continues to explore
additional development options in Alberta including its currently
permitted gas-fired generation project and the permitting of its
wind power generation project. MAXIM trades on the TSX under the
symbol “MXG”. For more information about MAXIM, visit our website
at www.maximpowercorp.com.
For further information please contact: Bob
Emmott, President and COO, (403) 263-3021.
Note Regarding Forward-Looking
Statements
This document contains forward-looking
information. This information relates to future events and the
Corporation’s future performance. All information and statements
contained herein that are not clearly historical in nature
constitute forward- looking information, and the words “may”,
“will”, “should”, “could”, “expect”, “plan”, “intend”,
“anticipate”, “believe”, “estimate”, “propose”, “predict”,
“potential”, “continue”, “aim”, "budget" or the negative of these
terms or other comparable terminology are generally intended to
identify forward-looking information. Such information represents
the Corporation’s internal projections, estimates, expectations,
beliefs, plans, objectives, assumptions, intentions or statements
about future events or performance. This information involves known
or unknown risks, uncertainties and other factors that may cause
actual results or events to differ materially from those
anticipated in such forward- looking information.
MAXIM believes that the expectations reflected
in this forward-looking information are reasonable; however, undue
reliance should not be placed on this forward-looking information,
as there can be no assurance that the plans, intentions or
expectations upon which they are based will occur. This press
release contains forward-looking information concerning, among
other things, the expected commissioning period for the CCGT
expansion, the expected completion date of the CCGT expansion, the
current cost estimates for the CCGT expansion, expected operational
disruptions at M2, the value of the EPC contract (prior to any
change orders) and MAXIM’s financing plans with respect to the CCGT
expansion. The reader is cautioned that such information, although
considered reasonable by the Corporation, may prove to be
incorrect. Actual results achieved during the forecast period will
vary from the information provided in this document as a result of
numerous known and unknown risks and uncertainties and other
factors. A number of risks and other factors could cause actual
results to differ materially from those expressed in the
forward-looking information contained in this document including,
but not limited to, continued compliance by MAXIM of its credit
agreements, liquidity, interest rates, the availability and cost of
financing, labor and services, the impact of increasing
competition, changes in laws, regulations and government policies
with respect to carbon taxation and the Corporation's ability to
access capital.
With respect to forward-looking information
contained in this document, the Corporation has made assumptions
regarding, among other things: the scope and design of the CCGT
expansion, that no change orders will be to cause the costs
associated with the CCGT expansion to vary, the timely receipt of
any required regulatory approvals and the ability of the
Corporation to obtain qualified staff, equipment and services in a
timely and cost efficient manner; that no construction delays will
occur with respect to the CCGT expansion; that the rules, laws,
regulations and policies described herein with respect to carbon
taxation will remain in effect in the manner provided herein; and
the ability of the Corporation to obtain financing on acceptable
terms when and if needed. Management of MAXIM has included the
above summary of assumptions and risks related to forward-looking
information included in this document in order to provide investors
with a more complete perspective on the Corporation’s future
operations. Readers are cautioned that this information may not be
appropriate for other purposes.
Readers are cautioned that the foregoing lists
of factors are not exhaustive. The forward-looking information
contained in this document are expressly qualified by this
cautionary statement. The forward-looking information contained
herein is made as of the date of this document and the Corporation
disclaims any intent or obligation to update publicly any such
forward-looking information, whether as a result of new
information, future events or results or otherwise, other than as
required by applicable Canadian securities laws.
Maxim Power (TSX:MXG)
Graphique Historique de l'Action
De Jan 2025 à Fév 2025
Maxim Power (TSX:MXG)
Graphique Historique de l'Action
De Fév 2024 à Fév 2025