Maxim Power Corp. Provides M2 Operations Update, CCGT Project Update and Updated Investor Presentation
24 Décembre 2021 - 1:34AM
Maxim Power Corp. ("MAXIM" or the "Corporation") (TSX: MXG)
provides an update on its 204 MW Milner 2 (“M2”) operations, the
combined cycle gas turbine (“CCGT”) expansion of M2 project, and
updated Investor Presentation.
M2 OPERATIONS UPDATE
As previously reported, M2 initiated a routine
planned maintenance outage on November 9, 2021 and also performed
work to integrate several critical components of the CCGT expansion
of M2. The outage was completed on November 30, 2021 and M2
returned to normal operation on December 1, 2021.
M2 CCGT PROJECT UPDATE
As a result of work performed during the planned
maintenance outage in November, M2 has successfully increased its
maximum electrical interconnection capacity with the Alberta
Electric System Operator to 300 MW to facilitate the CCGT expansion
of M2, which is not anticipated to be in commercial operation until
December 2022. In the meantime, MAXIM is authorized to operate the
legacy 144 MW H.R. Milner facility (“M1”) in tandem with the M2
facility, up to a combined total output of 300 MW. MAXIM has
successfully demonstrated two-unit operation from both M1 and M2
with each unit operating as stand-alone power plants. This
significant milestone confirms the interconnection is complete to
allow for the CCGT expansion of M2. MAXIM notes that M1 as a
stand-alone power plant is subject to federal greenhouse gas
regulations which limit the annual hours of operation from the
unit. MAXIM does not anticipate fully utilizing the M1 unit up to
its authorized maximum operating hours.
Progress continues on the engineering and
construction of the CCGT expansion of M2 and as of this date the
project remains on schedule with no change to the previously
reported estimated project costs of $135 million.
At this time, MAXIM forecasts it has sufficient
liquidity to complete the CCGT expansion of M2 and will fund the
project using cash on hand, operating cashflows and available funds
through the existing senior and subordinated credit facilities, as
required.
UPDATED INVESTOR
PRESENTATION
An updated investor presentation has been
prepared for readers and can be accessed through MAXIM’s website in
the Investors section.
About MAXIM
Based in Calgary, Alberta, MAXIM is one of
Canada’s largest truly independent power producers. MAXIM is now
focused entirely on power projects in Alberta. Its core asset – the
204 MW H.R. Milner Plant, M2, in Grande Cache, AB – is a
state-of-the-art natural gas-fired power plant that commissioned in
Q2, 2020. MAXIM is currently increasing the capacity of M2 to
approximately 300 MW and concurrently will realize an improvement
in the efficiency of the plant by investing in heat recovery
combined cycle technology. In addition, MAXIM continues to explore
additional development options in Alberta including its currently
permitted gas-fired generation project and the permitting of its
wind power generation project. MAXIM trades on the TSX under the
symbol “MXG”. For more information about MAXIM, visit our website
at www.maximpowercorp.com. For further information please
contact:
Bob Emmott, President and COO, (403)
263-3021
Kyle Mitton, CFO and Vice President, Corporate
Development, (403) 263-3021
This press release contains forward-looking
statements and forward-looking information (collectively "forward
looking information") within the meaning of applicable securities
laws relating to MAXIM's plans and other aspects of MAXIM's
anticipated future operations, management focus, objectives,
strategies, financial, operating and production results.
Forward-looking information typically uses words such as
"anticipate", "believe", "project", "expect", "goal", "plan",
"intend", "may", "would", "could" or "will" or similar words
suggesting future outcomes, events or performance. The
forward-looking statements contained in this press release speak
only as of the date thereof and are expressly qualified by this
cautionary statement. Specifically, this press release contains
forward-looking information concerning, among other things, the
expected run time of M1, the expected completion date of the CCGT
expansion of M2, the current cost estimates for the CCGT expansion
of M2 and MAXIM’s financing plans with respect to the CCGT
expansion.
Management has included the forward-looking
statements above and a summary of assumptions and risks related to
forward-looking statements provided in this press release in order
to provide readers with a more complete perspective on MAXIM's
future plans and operations and such information may not be
appropriate for other purposes.
MAXIM's actual results, performance or
achievement could differ materially from those expressed in, or
implied by, these forward-looking statements and, accordingly, no
assurance can be given that any of the events anticipated by the
forward-looking statements will transpire or occur, or if any of
them do so, what benefits that MAXIM will derive there from.
Readers are cautioned that the foregoing lists of factors are not
exhaustive. These forward-looking statements are made as of the
date of this press release and MAXIM disclaims any intent or
obligation to update publicly any forward-looking statements,
whether as a result of new information, future events or results or
otherwise, other than as required by applicable securities
laws.
Maxim Power (TSX:MXG)
Graphique Historique de l'Action
De Oct 2024 à Nov 2024
Maxim Power (TSX:MXG)
Graphique Historique de l'Action
De Nov 2023 à Nov 2024