$2.3 billion
After-Tax NPV (8%) at Base Case metal prices
After-Tax IRR 19.5% at Base Case metal
prices
Cashflow over the first four years of
$965 million per year at Base Case
metal prices
Base case development contemplates 25-year
mine life
Extended Two-Phase development contemplates a
47-year mine life
Base Case metal prices: Cu: US$3.35/lb, Au: US$1,600/oz, Ag: US$24/oz, Mo: US$12/lb
VANCOUVER, BC, June 22, 2021 /PRNewswire/ - Western Copper and
Gold Corporation ("Western" or the "Company") (TSX: WRN) (NYSE
American: WRN) is pleased to release the results of its Preliminary
Economic Assessment (the "PEA", or "Study") on its wholly-owned
Casino copper-gold-molybdenum deposit in the Yukon ("Casino" or the "Project"). The
Study considered the Project being constructed as an open pit mine,
with a concentrator processing nominally 120,000 tonnes per day and
a gold heap leach facility processing nominally 25,000 tonnes per
day.
The Study supersedes all previous studies and incorporates the
updated mineral resource with an effective date of July 3, 2020. The Study also incorporates
outcomes of the Best Available Tailings Technology Study (the "BATT
Study") completed in 2018 with participation by First Nations, the
Yukon Environmental and Socio-economic Assessment Board ("YESAB")
and the Yukon Government. The design concept for the tailings
management facility ("TMF") also reflects the guidance received
from the Independent Engineering Review Panel.
The Study examines the development of the Casino Project, which
comprises the processing of 1.3 billion tonnes of mineralized
material for both the mill and heap leach, with deposition of mill
tailings and mine waste in the TMF facility consistent with the
design concepts considered during the BATT Study as a base case
development.
"I am extremely pleased with the results from this PEA", said
Paul West-Sells, President &
Chief Executive Officer. "This Study reaffirms Casino as one of the
very few long-life copper-gold projects with robust economics in a
top mining district, the Yukon. We look forward to continuing
working with our recent strategic investor, Rio Tinto, First
Nations and other stakeholders to advance this project through
additional engineering to feasibility."
In this news release, unless otherwise indicated, all further
references to "$" are to Canadian dollars and references to "US$"
are to United States dollars.
HIGHLIGHTS
|
Base
Case*
|
Payback period,
years
|
3.0
|
|
|
NPV pre-tax (8%
discount)
|
$3.62
billion
|
NPV after-tax (8%
discount)
|
$2.33
billion
|
|
|
LOM pre-tax free
cash flow
|
$13.0
billion
|
LOM after-tax free
cash flow
|
$9.1
billion
|
|
|
IRR pre-tax (100 %
equity)
|
23.3%
|
IRR after-tax
(100% equity)
|
19.5%
|
|
|
Initial Capital
Investment
|
$3.25
billion
|
Total mineralized
material mined
|
1.3 billion
tonnes
|
Mill mineralized
material
|
1.1 billion
tonnes
|
Heap leach
mineralized material
|
204 million
tonnes
|
|
|
Mill
operation
|
25 years
|
Heap leach
operation
|
23 years
|
LOM strip
ratio
|
0.38:1
|
Base Case metal prices: Cu: US$3.35/lb, Au: US$1,600/oz, Ag: US$24/oz, Mo: US$12/lb.
KEY CHANGES FROM THE PREVIOUS STUDY
The engineering design basis for this PEA is similar in most
respects to earlier studies but includes several significant design
improvements. The major changes include:
Tailings Management Facility
The TMF is sized to provide sufficient capacity to store
approximately 712 Mt of tailings and
500 Mt of mining waste rock and
overburden materials. The remaining 415
Mt of non-acid generating ("NAG") tailings will be used for
dam construction following classification with hydrocyclones and
dewatering screens. The TMF for the PEA includes design changes
based on the recommendations from the BATT Study. The key
changes to the TMF design concept include:
- Substantial reduction in the quantity of free-standing water
impounded during operations and a corresponding reduction of risk
associated with this facility.
- Closure by saturated NAG tailings cover limiting the need for a
flooded cover.
- A tailings dewatering facility to conserve additional coarse
sand material for dam construction. Surplus sand produced through
cycloning and screening operations will be used to buttress the
downstream slopes of the main embankment.
- Changes to the design of the starter dam to reduce construction
risk.
- Added a HDS water treatment facility to provide mitigation for
potential water surplus conditions, However, surplus water is not
expected under design operating conditions.
Updated Mineral Resource
The updated mineral resource, released in July 2020, was used as the basis of the
PEA. For the purposes of the Study, only the measured and
indicated mineral resources were considered as mill or heap leach
feed. Inferred mineral resources in the pit are considered to
be waste as there are limited inferred mineral resources in the
designed pit.
Note that the Study reports on mineral resources, not mineral
reserves. Mineral resources that are not mineral reserves do
not have demonstrated economic viability.
Heap Leach Gold Recovery
New column testing on various lithology samples representing the
feed to the heap leach indicated that the gold recovery in the heap
leach could be increased from 66% to 70%.
Access Road
Costing for the access road was adjusted to incorporate the
commitment from the Yukon and
Federal government to fund portions of the access road. More
detail can be found in the Western news release dated September 5, 2017.
Airstrip
The proposed airstrip has been relocated along the access road
to limit the potential impact on caribou habitat.
FINANCIAL RESULTS
The Study indicates that the potential economic returns from the
Project justify its further development and securing the required
permits and licenses for operation.
The financial results of the Study were developed under
commodity prices that were based on analyst projections of
long-term metal prices and CAN$:US$ exchange rate ("Base Case"
prices).
Note that an exchange rate of CAN$:US$ of 0.80 was used for the
capital cost estimation for all metal price scenarios.
The following table summarizes the financial results:
|
Base
Case
|
Copper
(US$/lb)
|
3.35
|
Molybdenum
(US$/lb)
|
12.00
|
Gold
(US$/oz)
|
1,600
|
Silver
(US$/oz)
|
24.00
|
Exchange Rate
(C$:US$)
|
0.80
|
|
|
NPV
pre-tax (5% discount, $millions)
|
5,790
|
NPV
pre-tax (8% discount, $millions)
|
3,620
|
IRR
pre-tax (100% equity)
|
23.3%
|
|
|
NPV
after-tax (5% discount, $millions)
|
3,900
|
NPV
after-tax (8% discount, $millions)
|
2,330
|
IRR
after-tax (100% equity)
|
19.5%
|
|
|
LOM pre-tax free
cash flow ($millions)
|
13,000
|
LOM after-tax free
cash flow ($millions)
|
9,070
|
|
|
Payback period
(years)
|
3.0
|
Net Smelter
Return ($/t milled)
|
28.14
|
Copper Cash
Cost* (US$/lb)
|
(1.13)
|
*C1 cash costs, net of by-product credits.
The financial results of the Study are significantly influenced
by copper and gold prices, as is shown in the tables below:
Copper Price
(US$/lb)*
|
$2.50
|
$3.00
|
$3.35
|
$4.00
|
$4.50
|
$5.00
|
NPV pre-tax (8%)
($M)
|
2,290
|
3,070
|
3,620
|
4,630
|
5,410
|
6,190
|
NPV after-tax (8%)
($M)
|
1,400
|
1,950
|
2,330
|
3,040
|
3,590
|
4,140
|
IRR
pre-tax
|
18.5%
|
21.4%
|
23.3%
|
26.6%
|
29.0%
|
31.3%
|
IRR
after-tax
|
15.4%
|
17.9%
|
19.5%
|
22.3%
|
24.3%
|
26.2%
|
Payback
(years)
|
3.7
|
3.2
|
3.0
|
2.7
|
2.5
|
2.3
|
Gold Price
(US$/oz)*
|
$1200
|
$1400
|
$1600
|
$1800
|
$2000
|
$2200
|
NPV pre-tax (8%)
($M)
|
2,580
|
3,100
|
3,620
|
4,130
|
4,650
|
5,170
|
NPV after-tax (8%)
($M)
|
1,600
|
1,960
|
2,330
|
2,700
|
3,060
|
3,430
|
IRR
pre-tax
|
19.3%
|
21.3%
|
23.3%
|
25.2%
|
27.1%
|
29.0%
|
IRR
after-tax
|
16.1%
|
17.8%
|
19.5%
|
21.1%
|
22.7%
|
24.3%
|
Payback
(years)
|
3.5
|
3.2
|
3.0
|
2.8
|
2.6
|
2.5
|
*All other metal prices except those noted are the same as the
Base Case.
Higher grade material is fed to the concentrator during the
first four years of the concentrator operation. This factor,
combined with the concurrent heap leach facility operation, results
in higher yearly cash flows and other metrics during this period
and contributes significantly to the Project's financial
performance.
|
Years
1-4
|
Life of
Mine
|
Average Annual
Pre-tax Cash Flow ($millions)
|
1,081
|
645
|
Average Annual
After-tax Cash Flow ($millions)
|
965
|
528
|
Average Net Smelter
Return (NSR) ($/t ore milled)
|
41.92
|
28.14
|
% of Revenue -
Copper
|
50
|
47
|
% of Revenue -
Gold
|
37
|
36
|
% of Revenue -
Silver
|
3
|
3
|
% of Revenue -
Molybdenum
|
10
|
14
|
CAPITAL COSTS
Total initial capital investment in the Project is estimated to
be $3.25 billion, which represents
the total direct and indirect cost for the complete development of
the Project, including associated infrastructure and power
plant. The following table shows how the initial capital is
distributed between the various components.
Cost
Item
|
Total
($M)
|
Process Plant and
Infrastructure
|
|
Project Directs including freight
|
1,777
|
Project Indirects
|
390
|
Contingency
|
412
|
Subtotal
|
2,579
|
Mining
|
|
Mine Equipment
|
409
|
Mine Preproduction
|
211
|
Subtotal
|
620
|
Owner's Costs
|
52
|
Total Initial
Capital Costs
|
3,251
|
Sustaining Capital
|
719
|
Total Life of Mine
Capital Costs
|
3,970
|
OPERATING COSTS
Operating costs for the milling operation were calculated per
tonne of material processed through the mill over the life of
mine:
|
LOM
|
|
($/tonne)
|
Milling
|
$5.72
|
General &
Administrative
|
$0.45
|
Total
|
$6.17
|
Heap leach operating costs were calculated per tonne of material
processed through the heap leach over the life of the heap
leach.
|
LOM
|
|
($/tonne)
|
Heap Leach
Operation
|
$1.30
|
ADR/SART
|
$4.67
|
Total
|
$5.98
|
Mining costs were calculated to average $1.93 per tonne of material moved and
$3.10 per tonne of mineralized
material.
|
($/tonne)
|
Cost per tonne
material (material moved)
|
$1.93
|
Cost per tonne mill
feed (mill + heap material)
|
$3.10
|
Cost per tonne mill
feed
|
$3.66
|
The combined mining and milling costs are $9.84 per tonne material milled for the life of
mine, which compares favorably to the life-of-mine net smelter
return of $28.14 per tonne at Base
Case metal prices.
DEVELOPMENT PLAN
The Study evaluates the development of the Casino deposit as a
conventional open pit mine, concentrator complex, and heap leach
operation. The initial production will focus on the deposit's oxide
cap as a heap leach operation to recover gold and silver in doré
form. The main sulphide deposit will be processed using a
conventional concentrator to produce copper-gold-silver and
molybdenum concentrates. Key metrics of the processing plant
are shown below:
|
Years
1-4
|
Life of
Mine
|
Strip
ratio
|
0.28
|
0.38
|
Nominal
Throughput
|
|
|
Mill (tpd)
|
120,000
|
120,000
|
Heap (tpd)
|
25,000
|
25,000
|
Average Annual
Metal Production
|
|
|
Copper
(Mlbs)
|
252
|
178
|
Gold
(kozs)
|
339
|
231
|
Silver
(kozs)
|
1,570
|
1,360
|
Molybdenum
(Mlbs)
|
16.5
|
16.6
|
Average Annual
Mill Feed Grade
|
|
|
Copper (%)
|
0.312
|
0.197
|
Gold (g/t)
|
0.360
|
0.226
|
Silver
(g/t)
|
2.039
|
1.702
|
Molybdenum
(%)
|
0.026
|
0.022
|
Average Annual
Heap Leach Grade*
|
|
|
Gold (g/t)
|
0.359
|
0.259
|
Silver
(g/t)
|
2.271
|
1.95
|
Copper
(%t)
|
0.039
|
0.034
|
Recovery
(Mill)
|
|
|
Copper (%)
|
84.5
|
86.6
|
Gold (%)
|
67.6
|
67.1
|
Silver (%)
|
55.3
|
53.1
|
Molybdenum
(%)
|
65.9
|
71.3
|
Recovery
(Heap)
|
|
|
Gold (%)
|
70.0
|
70.0
|
Copper (%)
|
18.0
|
18.0
|
Silver (%)
|
26.0
|
26.0
|
Annual Concentrate
Production
|
|
|
Cu (dry
ktonnes)
|
408
|
288
|
Mo (dry
ktonnes)
|
13
|
13
|
Average
Concentrate Grade
|
|
|
Copper Concentrate
|
|
|
Cu (%)
|
28.0
|
28.0
|
Au (g/t)
|
25.9
|
24.9
|
Ag (g/t)
|
119.8
|
147.1
|
Molybdenum Concentrate
|
|
|
Mo (%)
|
56.0
|
56.0
|
*Heap leach first four years grades taken from the start of the
heap leach.
INFRASTRUCTURE
A new 132-km all-weather access road will be developed,
extending from the end of the existing Freegold Road and generally
following the alignment of the existing "Casino Trail" to the mine
site. The Study contemplated that concentrates will be transported,
stored and loaded on ships via upgraded facilities provided by the
Port of Skagway, Alaska. The
Project operating cost estimate includes the anticipated
concentrate handling service charges based on use of the upgraded
facilities.
SECOND PHASE DEVELOPMENT
The Study also examined extending the operation after treating
the first 1.3 billion tonnes of mineralized material (Phase I) for
approximately 25 years (Phase II) for a total life-of-mine of 47
years. The extended operation is achieved using the original
concentrator and associated infrastructure at the same nominal
processing rate of 120,000 tonnes per day. An additional 1 billion
tonnes of mineralized material would be processed by the mill
during the extended operation. A secondary TMF would be constructed
downstream of the original TMF to accommodate the additional
tailings and waste rock associated with extended operations.
The indicative capital requirements and economic performance
indicators for the extended operations scenario is as shown
below. As this table shows, the differences between Phase I
capital costs and the combined Phase I + Phase II capital costs are
the additional sustaining capital to construct the secondary TMF
facility and the mine equipment required to support the Project
through the additional years of mine life.
Cost
Item
|
Phase I
Total ($M)
|
Phase I +
II
Total
($M)
|
Process Plant and
Infrastructure
|
|
|
Project Directs including freight
|
1,777
|
1,777
|
Project Indirects
|
390
|
390
|
Contingency
|
412
|
412
|
Subtotal
|
2,579
|
2,579
|
Mine
|
|
|
Mine Equipment
|
409
|
419
|
Mine Preproduction
|
211
|
206
|
Subtotal
|
620
|
625
|
Owner's Costs
|
52
|
52
|
Total Initial
Capital Cost
|
3,251
|
3,256
|
Sustaining Capital
|
719
|
1,808
|
Total Life of Mine
Capital Costs
|
3,970
|
5,064
|
The net present value and internal rate of return for developing
the two-phase project are not significantly different from those
for developing the single-phase project, however, the life-of-mine
and life-of-mine cash flow increase significantly. Highlights
from developing the Phase I + II development at Base Case metal
prices are shown below:
|
Phase I
Development
|
Phase I + II
Development
|
NPV pre-tax* (8%
discount)
|
$3.62
billion
|
$3.70
billion
|
NPV after-tax* (8%
discount)
|
$2.33
billion
|
$2.38
billion
|
|
|
|
LOM pre-tax free
cash flow*
|
$13.0
billion
|
$17.2
billion
|
LOM after-tax free
cash flow*
|
$9.1
billion
|
$12.0
billion
|
|
|
|
IRR pre-tax* (100
% equity)
|
23.3%
|
23.1%
|
IRR after-tax*
(100% equity)
|
19.5%
|
19.3%
|
|
|
|
Total mineralized
material mined
|
1.3 billion
tonnes
|
2.4 billion
tonnes
|
Mill mineralized
material
|
1.1 billion
tonnes
|
2.1 billion
tonnes
|
Heap leach
mineralized material
|
204 million
tonnes
|
240 million
tonnes
|
Average annual
mill feed grades
|
|
|
Copper (%)
|
0.197
|
0.163
|
Gold (g/t)
|
0.226
|
0.192
|
Silver
(g/t)
|
1.70
|
1.507
|
Molybdenum
(%)
|
0.022
|
0.018
|
Average annual
heap leach grades*
|
|
|
Gold (g/t)
|
0.259
|
0.245
|
Silver
(g/t)
|
1.95
|
1.87
|
Copper
(g/t)
|
0.034
|
0.034
|
|
|
|
Mill
operation
|
25 years
|
47 years
|
Heap leach
operation
|
23 years
|
33 years
|
LOM waste:ore
ratio
|
0.38:1
|
0.47:1
|
*Based on Base Case metal prices: Cu: US$3.35/lb, Au: US$1,600/oz, Ag: US$24/oz, Mo: US$12/lb
STAKEHOLDER ENGAGEMENT
The Project is located within the traditional territory of
Selkirk First Nation. Aspects of the Project impact the traditional
territories of the Little Salmon/Carmacks First Nation, Tr'ondëk
Hwëch'in, Kluane First Nation and
White River First Nation. The nearest communities are the
Village of Carmacks and
Pelly Crossing, and the Project is
200 km upstream of Dawson City
along the Yukon River.
Western is committed to developing and operating the Project in
a safe, ethical and socially responsible manner. Western has been
consulting extensively on the Project since 2008, and First Nations
and their technical advisors have participated directly in the
refinement of the tailings and mine waste strategy at the Project,
as reflected in the design presented in the PEA.
Since 2006, Western has spent over $75
Million in Yukon advancing
the Project, working with over 50 different Yukon and First Nations joint venture
companies. Western is active in the local community, with
longstanding support and sponsorship of over 30 local organizations
and charities.
As the Project is further refined, Western will continue to seek
feedback from and partnerships with local First Nations and
communities and is committed to developing the Project with First
Nations' and local community input.
LOOKING FORWARD
Based on the positive results of the Study, Western plans to
advance the Project to establish a mineral reserve estimate for the
Project with the ultimate objective of submitting an application
for environmental assessment under the Yukon Environmental and
Socioeconomic Assessment Act, the first step in the permitting
process.
CONFERENCE CALL
Western will hold a conference call and webcast on
Tuesday, June 22, 2021 at
8 am Pacific Time
(11 am Eastern Time) to discuss the
Study.
Webcast access:
http://services.choruscall.ca/links/westerncopperandgold20210622.html
Telephone access:
Vancouver local and
International 1-604-638-5340
Toll Free North
America:
1-800-319-4610
An archived recording of the conference call will be available
by dialing 1-604-638-9010 or 1-800-319-6413 within North America, passcode is 7194. The
webcast and presentation slides will be archived on the Company's
website www.westerncopperandgold.com.
TECHNICAL REPORT & QUALIFIED PERSONS
M3 Engineering & Technology Corporation ("M3), a
full-service Engineering, Procurement, Construction &
Management firm, is recognized for its experience in copper
processing and capabilities in the development and construction of
mines and mineral processing plants. A National Instrument
43-101 (NI 43-101) compliant technical report prepared by the
following Qualified Persons will be posted on the Company's website
(www.westerncopperandgold.com) as well as on SEDAR (www.sedar.com),
and on EDGAR within 45 days:
- Daniel Roth, P.Eng. of M3 –
Overall scientific and technical information, with a focus on
project infrastructure, capital costs, and the economic
analysis.
- Laurie Tahija, MMSA-QP, of M3 –
Metallurgy, recovery methods, and process operating costs.
- Michael G. Hester, F Aus IMM, of
Independent Mining Consultants – Resource estimation, mining
methods and mining costs.
- Carl Schulze, P.Geo., of Aurora
Geosciences – History, geology, exploration, drilling, and
sampling.
- Caroline J. Vallat, P.Geo., of
GeoSpark Consulting Inc. – Data verification.
- Daniel Friedman, P.Eng., of
Knight Piésold Ltd. – Tailings and heap leach facilities.
The Qualified Persons have reviewed and approved the scientific,
technical, and economic information contained in this news
release.
ABOUT WESTERN COPPER AND GOLD CORPORATION
Western Copper and Gold Corporation is developing the Casino
Project, Canada's premier
copper-gold mine in the Yukon
Territory and one of the most economic greenfield
copper-gold mining projects in the world. For more
information, visit www.westerncopperandgold.com.
On behalf of the board,
"Paul West-Sells"
Dr. Paul
West-Sells
President and CEO
Western Copper and Gold Corporation
Cautionary Disclaimer Regarding Forward-Looking Statements
and Information
Mineral resources that are not mineral reserves do not have
demonstrated economic viability. Therefore, investors are cautioned
not to assume that all or any part of an inferred mineral resource
could ever be mined economically. It cannot be assumed that all or
any part of "measured mineral resources," "indicated mineral
resources," or "inferred mineral resources" will ever be upgraded
to a higher category. The mineral resource estimates contained
herein may be subject to legal, political, environmental or other
risks that could materially affect the potential development of
such mineral resources. See the technical report, once filed, for
more information with respect to the key assumptions, parameters,
methods and risks of determination associated with the foregoing.
The PEA is preliminary in nature, includes inferred mineral
resources that are considered too speculative geologically to have
the economic considerations applied to them that would enable them
to be categorized as mineral reserves, and there is no certainty
that the PEA will be realized.
This news release contains certain forward-looking statements
concerning anticipated developments in Western's operations in
future periods. Statements that are not historical fact are
"forward-looking statements" as that term is defined in
the United States Private
Securities Litigation Reform Act of 1995 and "forward-looking
information" as that term is defined in National Instrument 51-102
("NI 51-102") of the Canadian Securities Administrators
(collectively, "forward-looking statements"). Certain
forward-looking information should also be considered
future-oriented financial information ("FOFI") as that term is
defined in NI 51-102. The purpose of disclosing FOFI is to provide
a general overview of management's expectations regarding the
anticipated results of operations and capital expenditures and
readers are cautioned that FOFI may not be appropriate for other
purposes. Forward-looking statements are frequently, but not
always, identified by words such as "expects", "anticipates",
"believes", "intends", "estimates", "potential", "possible" and
similar expressions, or statements that events, conditions or
results "will", "may", "could" or "should" occur or be achieved.
These forward-looking statements may include, but are not limited
to, statements regarding: mineral resource estimation; mine plan
and operations; internal rate of return; sensitivities; net present
value; potential recoveries; design parameters; economic potential;
processing mineralized material; the potential of robust economics
at Casino; advancing the Project through additional engineering and
towards the next step in permitting and submission of an
environmental and socio-economic effects statement; key changes to
the TMF design; increases to the gold recovery in the heap leach;
potential economic returns from the Project; estimated initial
capital investment costs; estimated operating costs; estimated
mining costs; development of the airstrip and all weather access
road; anticipated concentrate handling service charges; developing
and operating the Project in a safe, ethical and
socially-responsible manner; plans for further development and
securing the required permits and licenses for further studies to
consider operation; market price of precious and base metals; or
other statements that are not statement of fact. The material
factors or assumptions used to develop forward-looking statements
include prevailing and projected market prices and foreign exchange
rates, exploration estimates and results, continued availability of
capital and financing, construction and operations, the Company not
experiencing unforeseen delays, unexpected geological or other
effects, equipment failures, permitting delays, and general
economic, market or business conditions and as more specifically
disclosed throughout this document, and in the AIF and Form
40-F.
Forward-looking statements are statements about the future
and are inherently uncertain, and actual results, performance or
achievements of Western and its subsidiaries may differ materially
from any future results, performance or achievements expressed or
implied by the forward-looking statements due to a variety of
risks, uncertainties and other factors. Such risks and other
factors include, among others, risks involved in fluctuations in
gold, copper and other commodity prices and currency exchange
rates; uncertainties relating to interpretation of drill results
and the geology, continuity and grade of mineral deposits;
uncertainty of estimates of capital and operating costs, recovery
rates, production estimates and estimated economic return; risks
related to joint venture operations; risks related to cooperation
of government agencies and First Nations in the development of the
property and the issuance of required permits; risks related to the
need to obtain additional financing to develop the property and
uncertainty as to the availability and terms of future financing;
the possibility of delay in construction projects and uncertainty
of meeting anticipated program milestones; uncertainty as to timely
availability of permits and other governmental approvals; and other
risks and uncertainties disclosed in Western's AIF and Form 40-F,
and other information released by Western and filed with the
applicable regulatory agencies.
Western's forward-looking statements are based on the
beliefs, expectations and opinions of management on the date the
statements are made, and Western does not assume, and expressly
disclaims, any intention or obligation to update or revise any
forward-looking statements whether as a result of new information,
future events or otherwise, except as otherwise required by
applicable securities legislation. For the reasons set forth above,
investors should not place undue reliance on forward-looking
statements.
View original content to download
multimedia:http://www.prnewswire.com/news-releases/western-copper-and-gold-announces-positive-pea-on-casino-301317146.html
SOURCE Western Copper and Gold Corporation