Mineral Reserves Increased 44% to 5.4 Million
Ounces of Gold
360,000 Ounces of Average Annual Gold
Production from 2025-2030
Mine Life Extended to 14.5
Years with 280,000 Ounces of Average Annual Gold
Production
NPV5% of $625 million and IRR of 26% at $1,675/oz Gold
all dollar figures in US dollars, unless
otherwise indicated
VANCOUVER, BC, Oct. 19, 2022 /PRNewswire/ - Equinox Gold
Corp. (TSX: EQX) (NYSE American: EQX) ("Equinox Gold" or the
"Company") is pleased to announce the results of a Feasibility
Study for an expansion at the Company's 100%-owned Los Filos Mine
Complex ("Los Filos") located in Mexico. Current Los Filos operations consist
of both run-of-mine ("ROM") and crushed ore heap leach facilities.
With continued development of the Bermejal Underground deposit and
construction of a 10,000 tonnes per day ("t/d") carbon-in-leach
("CIL") processing plant, the Los Filos mine life would be extended
to 14.5 years with life-of-mine ("LOM") average annual production
increasing to 280,000 ounces ("oz") of gold (2023-2036) at all-in
sustaining costs1 ("AISC") of $1,081 per oz. Total LOM production is estimated
at 3.97 million oz of gold. Peak production during 2025-2030
averages 360,000 oz of gold per year. Using the base case
$1,675/oz gold price, the expansion
project has an after-tax net present value discounted at 5%
("NPV5%") of $625 million
with an internal rate of return ("IRR") of 26%.
Gold mineralization at Los Filos extends beyond the drilled
area, and it is expected that additional drilling along the contact
between intrusive and carbonate rock could identify further skarn
mineralization. With exploration success and conversion of Mineral
Resources to Mineral Reserves, considerable potential exists to
extend the Los Filos mine life beyond 2036.
LOS FILOS EXPANSION
HIGHLIGHTS
- After-tax NPV5% of $625
million at base case $1,675/oz
gold
- After-tax IRR of 26% at $1,675/oz
gold
- 5.4 million oz gold of Proven and Probable Mineral
Reserves
- 7.9 million oz gold of Measured & Indicated Resources
(exclusive of Reserves)
- 3.97 million oz LOM gold production
-
- 360,000 oz peak average annual gold production (2025-2030)
- 280,000 oz average annual gold production LOM (2023-2036)
- 1.22 million oz of gold produced from the heap leach with
average recovery of 55%
- 2.75 million oz of gold produced from the CIL plant with
average recovery of 88%
- 11.83 million oz LOM silver production
- $993 million after-tax LOM
cumulative net cash flow
- $981/oz average LOM cash
costs1
- $1,081/oz average LOM
AISC1
- $318 million initial capital cost
to build the CIL plant and associated infrastructure
- 14.5-year mine life with extension potential from Mineral
Resource conversion and exploration success
_________________________________________
|
1. Cash costs and
all-in sustaining costs are non-IFRS measures. See Non-IFRS and
Other Financial Measures.
|
|
The Feasibility Study includes an updated Mineral Reserve and
Mineral Resource estimate incorporating a revised mine plan and
101,407 metres of exploration drilling since October 31, 2018. Factoring 681,000 oz of mining
depletion over almost four years, Los Filos Mineral Reserves have
increased 44% over the 2018 estimate, with 193.2 million
tonnes ("Mt") of Proven & Probable Mineral Reserves grading
0.86 grams per tonne ("g/t") gold for 5.4 million oz of
contained gold. An additional 325.3 Mt of Measured &
Indicated Mineral Resources (exclusive of Mineral Reserves) grading
0.75 g/t gold for 7.9 million oz of contained gold, and
135.9 Mt of Inferred Mineral Resources grading 0.74 g/t
gold for 3.2 million oz of contained gold demonstrate the
potential for mine life extension with successful conversion of
Mineral Resources to Mineral Reserves. Refer to the detailed
Mineral Reserve and Mineral Resource tables that follow in this
news release.
Los Filos encompasses three main open-pit mining areas: Los
Filos, Guadalupe and Bermejal, and three underground mines: Los
Filos South, Los Filos North and Bermejal Underground. Bermejal
Underground development recommenced in Q2-2021 and the deposit has
been contributing higher-grade ore since mid-2022. Ore from all six
mining areas is currently processed on heap leach pads.
The Feasibility Study contemplates construction of a CIL plant
commencing in 2023 with an 18-month timeline for construction and
commissioning, which would allow higher-grade ore to be directed to
the CIL plant commencing in mid-2024. While the economic and
production estimates outlined in the Feasibility Study and in this
news release are predicated on that timeline, Equinox Gold has not
approved construction for the CIL plant.
Greg Smith,
President & CEO of Equinox Gold, commented: "The Feasibility
Study confirms a path to expand Los Filos to a large-scale,
long-life gold mine with a substantial reserve and resource
endowment and opportunity for further growth. We are pleased with
the results of the Feasibility Study; however, we have not made a
decision to proceed with the expansion. Any decision to proceed
with the Los Filos expansion will be made considering the operating
stability in the region, market conditions and availability and
cost of capital. Equinox Gold is currently focused on construction
of its Greenstone Mine in Ontario,
Canada, and advancing the permitting to expand its Castle
Mountain Mine in California,
USA."
OVERVIEW
Los Filos has produced 3.4 million oz of gold since the mine
commenced operations in 2005, with ore from all deposits processed
using heap leach facilities. The Feasibility Study contemplates
building and operating a 10,000 t/d CIL processing plant to operate
concurrently with the existing heap leach facilities. All
underground ore and higher-grade open-pit ore (generally above 0.5
g/t gold) would be directed to the CIL plant, with lower-grade ore
going onto the heap leach pads as either crushed or run-of-mine
stacked ore. Ore that contains higher levels of copper and sulphur
would also be directed to the CIL plant to optimize the economic
recovery of gold from all ore types.
Constructing and operating the CIL plant, compared to a heap
leach only scenario, extends the Los Filos mine life by
approximately four years and adds more than 1.1 million ounces of
gold to LOM production.
Los Filos Expansion
Highlights
Gold price (base
case)
|
$1,675/oz
|
Exchange rate (Mexican
Peso to US Dollar)
|
20:1
|
Average annual gold
production (LOM) (2023-2036)
|
280,000 oz
|
Peak average annual
gold production (2025-2030)
|
360,000 oz
|
Total gold production
(LOM)
|
3.97 million
oz
|
Heap leach
facilities
|
1.22 million
oz
|
CIL plant
|
2.75 million
oz
|
Proven & Probable
Mineral Reserves
|
5.35 million
oz
|
Gold grade (open pit
0.65 g/t, underground 3.94 g/t)
|
0.86 g/t
|
Measured &
Indicated Mineral Resources (exclusive of Mineral
Reserves)
|
7.90 million
oz
|
Gold grade (open pit
0.71 g/t, underground 3.65 g/t)
|
0.75 g/t
|
Open-pit strip
ratio
|
4.4:1
|
Average gold recovery
(heap leach / CIL)
|
55% / 88%
|
Ore stacked on heap
leach (average over LOM)
|
28,000 t/d (10
Mtpa)
|
CIL plant
throughput
|
10,000 t/d (3.65
Mtpa)
|
Initial mine life
(commencing H2 2022)
|
14.5 years
|
Initial capital costs
for CIL plant construction
|
$318 M
|
Non-sustaining capital
(including capitalized stripping) (LOM)
|
$400 M
|
Sustaining capital
(LOM)
|
$349 M
|
Cash costs (LOM,
including royalties)
|
$981/oz
|
AISC (LOM)
|
$1,081/oz
|
Net cumulative cash
flow (LOM, after tax)
|
$993 M
|
NPV5% (after
tax)
|
$625 M
|
IRR (after
tax)
|
26 %
|
ECONOMIC SENSITIVITIES
Using the base case gold price of $1,675/oz and incorporating only Proven &
Probable Mineral Reserves, the expansion project has an after-tax
NPV5% of $625 million and
an after-tax IRR of 26%. The expansion project economics are most
sensitive to fluctuations in the gold price, followed by changes in
operating costs and capital costs. Approximately 40% of capital
costs for the expansion project are priced in Mexican Pesos.
After-tax NPV5% Sensitivity to Economic Changes
($M)
Variation in
Parameter
|
Operating
Costs
|
Capital
Costs
|
Gold
Price
|
−15%
|
920
|
755
|
172
|
−10%
|
822
|
712
|
323
|
−5%
|
724
|
668
|
474
|
0 %
|
625
|
625
|
625
|
5 %
|
526
|
582
|
776
|
10 %
|
427
|
538
|
926
|
15 %
|
328
|
495
|
1,076
|
CAPITAL AND OPERATING
COSTS
Initial capital costs for construction of the CIL plant are
estimated at $318 million, which is
included in total LOM non-sustaining capital of $718 million. Closure and reclamation costs of
$51 million are also included in
non-sustaining capital. LOM sustaining capital is estimated at
$349 million.
Los Filos Life-of-Mine Capital
Costs
Item
|
Non-Sustaining Capital
Costs
($M)
|
Sustaining Capital
Costs ($M)
|
Total
Capital Costs ($M)
|
Open pit mobile
equipment and workshop
upgrade
|
125
|
133
|
252
|
Los Filos Open Pit -
capitalized stripping
|
112
|
-
|
112
|
Bermejal Open Pit -
capitalized stripping
|
77
|
-
|
77
|
Guadalupe Open Pit -
capitalized stripping
|
-
|
44
|
44
|
Los Filos Underground
development
|
-
|
16
|
16
|
Bermejal Underground
development
|
35
|
70
|
106
|
CIL
plant
|
318
|
-
|
318
|
Heap leach pad
expansion
|
-
|
86
|
86
|
Closure and
reclamation
|
51
|
-
|
51
|
Total
|
718
|
349
|
1,067
|
|
Note: Numbers may not
sum due to rounding.
|
|
Total LOM operating costs are estimated at $4,015 million. Approximately 83% of the LOM
operating costs are related to mining and processing, with the
remainder attributable to general and administrative costs, land
access payments and social collaboration payments to local
communities.
Los Filos Life-of-Mine Operating
Costs
Item
|
($M)
|
$/oz
|
Mining (Open pit and
Underground)
|
2,072
|
521
|
Open
pit
|
1,118
|
281
|
Underground
|
954
|
240
|
Processing
|
1,288
|
324
|
General and
administrative, community, and land access
|
655
|
165
|
Total operating
costs
|
4,015
|
1,010
|
Royalties
|
34
|
9
|
Refining and
transport
|
22
|
6
|
Silver
credits
|
(172)
|
(43)
|
Cash
costs
|
3,899
|
981
|
Sustaining
capital
|
349
|
88
|
Reclamation
costs
|
51
|
13
|
AISC
|
4,299
|
1,081
|
|
Note: Numbers may
not sum due to rounding.
|
|
LOS FILOS MINERAL RESERVES &
MINERAL RESOURCES
The mine plan is based on Proven & Probable Mineral Reserves
of 180.6 Mt grading 0.65 g/t gold for 3.8 million oz of contained
gold in the open pit deposits, and 12.6 million tonnes grading 3.94
g/t gold for 1.6 million oz of contained gold in the underground
deposits.
Los Filos Mineral Reserves
Statement (June 30, 2022)
Classification
|
Mining
Method
|
Tonnes
(kt)
|
Gold Grade
(g/t )
|
Contained Gold
(koz)
|
Silver Grade
(g/t)
|
Contained Silver
(koz)
|
Proven
|
Open Pit
|
35,154
|
0.74
|
837
|
5.0
|
5,677
|
Underground
|
299
|
4.15
|
40
|
13.7
|
132
|
Total
|
35,453
|
0.77
|
877
|
5.1
|
5,809
|
Probable
|
Open Pit
|
145,476
|
0.62
|
2,921
|
6.3
|
29,303
|
Underground
|
12,297
|
3.94
|
1,556
|
18.9
|
7,458
|
Total
|
157,773
|
0.88
|
4,477
|
7.2
|
36,761
|
Proven &
Probable
|
Open Pit
|
180,629
|
0.65
|
3,758
|
6.0
|
34,980
|
Underground
|
12,597
|
3.94
|
1,596
|
18.7
|
7,590
|
Total
|
193,226
|
0.86
|
5,354
|
6.9
|
42,570
|
|
Notes: Mineral Reserves
have been estimated in accordance with CIM Definition Standards
for Mineral Resources and Mineral Reserves (2014), which are
incorporated by reference in NI 43-101. The open pit Mineral
Reserve estimate was prepared under the oversight and review of Mr.
Eugene Tucker, P.Eng., and the underground Mineral Reserve estimate
was prepared under the oversite and review of Mr. Paul Salmenmaki,
P.Eng. Mr. Tucker and Mr. Salmenmaki are "Qualified Persons" as
defined by NI 43-101. Mineral Reserves are estimated using a
long-term gold price of $1,450 per troy oz and a long-term silver
price of $18 per troy oz for all mining areas. Mineral Reserves are
stated in terms of delivered tonnes and grade before process
recovery. Mineral Reserves are defined by pit optimization and are
based on variable break-even cut-offs as generated by process
destination and metallurgical recoveries. Metal recoveries are
variable dependent on metal head grades as outlined in the
Technical Report. Open pit dilution is applied at 5% at a zero
grade for Au and Ag for Bermejal Open Pit and Guadalupe Open Pit,
and 7% at zero grade for Au and Ag for Los Filos Open Pit. Open pit
mining recovery is applied at 95% for Bermejal Open Pit and
Guadalupe Open Pit, and 93% for Los Filos Open Pit. Heap leach
process recovery varies based on rock type. The Qualified Persons
responsible for this item of the Technical Report are not aware of
any mining, metallurgical, infrastructure, permitting or other
relevant factors that could materially affect the Mineral Reserve
estimates. Effective date of Mineral Reserves is June 30, 2022.
Tonnage and grade measurements are in metric units. Contained gold
and silver ounces are reported as troy ounces. Underground
Mineral Reserves are reported based on a variable net processing
return cut-off value varying between $65.8 and $96.6/t Underground
dilution is assigned an average of 10% at a zero grade for gold and
silver. Underground mining recovery is set to 97%. Numbers may not
sum due to rounding. Additional details regarding the Mineral
Reserve estimation, classification, reporting parameters, key
assumptions and associated risks for Los Filos are provided in the
Feasibility Study. In addition, Mineral Reserves and Mineral
Resources may be materially affected by legal, political,
environmental and other risks, including the factors identified in
the Company's Annual Information Form dated March 24, 2022 for the
year ended December 31, 2021. Both documents are available on SEDAR
at www.sedar.com and on EDGAR at www.sec.gov/edgar.
|
|
Los Filos Mineral Resources
Statement (June 30, 2022) (Exclusive
of Mineral Reserves)
Area
|
Classification
|
Tonnes
(kt)
|
Gold
Grade (g/t)
|
Contained Gold
(koz)
|
Silver Grade
(g/t)
|
Contained
Silver (koz)
|
Bermejal /
Guadalupe
Open Pit
|
Measured
|
9,898
|
0.76
|
243
|
6.4
|
2,034
|
Indicated
|
184,152
|
0.59
|
3,492
|
7.6
|
45,186
|
Measured &
Indicated
|
194,050
|
0.60
|
3,734
|
7.6
|
47,220
|
Inferred
|
44,292
|
0.55
|
777
|
9.8
|
13,932
|
Bermejal
Underground (below
$1,500 pit shell)
|
Measured
|
-
|
-
|
-
|
-
|
-
|
Indicated
|
998
|
3.97
|
127
|
16.3
|
522
|
Measured &
Indicated
|
998
|
3.97
|
127
|
16.3
|
522
|
Inferred
|
1,501
|
4.98
|
241
|
22.7
|
1,093
|
Los Filos Open
Pit
|
Measured
|
35,327
|
1.09
|
1,238
|
6.4
|
7,315
|
Indicated
|
90,544
|
0.79
|
2,290
|
6.5
|
18,857
|
Measured &
Indicated
|
125,870
|
0.87
|
3,528
|
6.5
|
26,172
|
Inferred
|
87,552
|
0.68
|
1,914
|
7.7
|
21,657
|
Los Filos
Underground
|
Measured
|
2,081
|
4.13
|
276
|
22.8
|
1,527
|
Indicated
|
2,326
|
3.09
|
231
|
25.7
|
1,920
|
Measured &
Indicated
|
4,407
|
3.58
|
507
|
24.3
|
3,446
|
Inferred
|
2,590
|
3.67
|
306
|
27.5
|
2,287
|
Total
|
Measured
|
47,306
|
1.15
|
1,757
|
7.2
|
10,876
|
Indicated
|
278,020
|
0.69
|
6,140
|
7.4
|
66,485
|
Measured &
Indicated
|
325,326
|
0.75
|
7,897
|
7.4
|
77,360
|
Inferred
|
135,935
|
0.74
|
3,237
|
8.9
|
38,969
|
|
Notes: Mineral
Resources are exclusive of Mineral Reserves and have been estimated
in accordance with CIM Definition Standards for Mineral
Resources and Mineral Reserves (2014), which are incorporated
by reference in NI 43-101. The Mineral Resource estimate was
prepared under the oversight and review of Mr. Ali Shahkar, P.Eng.,
a "Qualified Person" as defined by NI 43-101. Mineral
Resources that are not Mineral Reserves do not have a demonstrated
economic viability. Mineral Resources are reported to a gold price
of $1,550/oz. Open pit Mineral Resources are defined within pit
shells that use variable mining and recovery estimates depending on
the geometallurgical domain and whether mineralization is projected
to report to crush-leach or is considered typical run-of-mine for
processing requirements. Open pit Mineral Resources are reported to
a gold cut-off grade of 0.2 g/t. Open pit Mineral Resources use
variable mining costs of $1.27-$1.43/t and variable processing
costs of $3.40-$12.81/t. Recovery ranges from 50% to 85% depending
on ore treatment method. Underground Mineral Resources use variable
mining costs of $57.21-$93.12/t and variable processing costs of
$9.53-$11.64/t, and a process recovery of 90%-95%. Underground
Mineral Resources are reported to a gold cut-off grade: Los Filos
South Underground, 1.71 g/t gold; Los Filos North Underground, 2.05
g/t gold; Bermejal underground 2.71 g/t gold. Quantity of material
is rounded to the nearest 1,000 tonnes; grades are rounded to two
decimal places for gold, one decimal place for silver. Numbers may
not sum due to rounding. Additional details regarding the Mineral
Resource estimation, classification, reporting parameters, key
assumptions and associated risks for Los Filos are provided in the
Feasibility Study. In addition, Mineral Reserves and Mineral
Resources may be materially affected by legal, political,
environmental and other risks, including the factors identified in
the Company's Annual Information Form dated March 24, 2022 for the
year ended December 31, 2021. Both documents are available on SEDAR
at www.sedar.com and on EDGAR at www.sec.gov/edgar.
|
|
LOS FILOS MINE PLAN
Open pit mining will remain owner-operated with conventional
load, haul, drill and blast. Loading is currently undertaken by
250-tonne shovels and large front-end loaders, and haulage by
136-tonne trucks. A larger mining fleet composed mainly of
180-tonne electric-drive trucks and 400-tonne face shovels is
proposed to progressively replace the existing mining equipment as
it reaches the end of its useful life, accounting for $125 million of costs considered growth capital
and $133 million of sustaining
capital costs over the mine life. Over the estimated 14.5-year mine
life, total open-pit material moved is estimated at 982.4 Mt, with
180.6 Mt of ore and 801.7 Mt of waste for an open-strip ratio of
4.4:1. The mine plan contemplates 34.8 Mt of open pit ore at an
average grade of 1.53 g/t gold going to the CIL plant, 24.6 Mt at
an average grade of 0.67 g/t gold going to crush heap leach and
121.2 Mt at an average grade of 0.39 g/t gold going to ROM heap
leach, for total gold production from all open-pit sources of 2.56
million oz.
Mining methods for the underground deposits vary depending on
the ore type and ground conditions. In the Los Filos Underground,
mining methods include overhand cut and fill in narrow areas,
overhand drift and fill in wider areas, and longhole open stoping
in areas with vertical ore body continuity and good rock
conditions. In the Bermejal Underground, oxide ore will be mined
using overhand drift and fill, which constitutes the majority of
the deposit, and underhand drift and fill will be used to mine ore
in intrusive host rock.
Los Filos Underground production is expected to average 960 t/d
until the end of its mine life in 2025. Bermejal Underground stope
development with multiple headings is expected to advance by
approximately 180 metres per month, which is equivalent to
approximately 250 t/d per stope mining horizon. A second portal
will provide two points of access by 2025, at which point Bermejal
Underground is expected to operate at steady-state production of
2,740 t/d (1 Mt/a) from 2025 to 2032. Los Filos Underground mining
is owner-operated. Bermejal Underground is mined by a
contractor.
For its remaining mine life Los Filos Underground is expected to
contribute 1.2 Mt of ore at an average grade of 3.50 g/t gold.
Bermejal Underground is expected to contribute 11.4 Mt of ore at an
average grade of 3.99 g/t gold. Underground ore will go to crush
heap leach until the CIL plant is operating at which point all
underground ore will be directed to the CIL plant, for total gold
production from all underground sources of 1.41 million oz over the
remaining 14.5-year mine life.
LOM mining costs are estimated at $1.38/t for open-pit mining, including
capitalized waste stripping, and $75.70/t for underground mining.
Los Filos Annual Ore Production by
Mine
PRODUCTION SCHEDULE
The combined open pit and underground mine plan is focused on
optimizing project value by allocating ore to ROM leach, crush
leach or the CIL plant to optimize economic gold recovery. Since
the metallurgical recovery and operating costs for each mined block
of open-pit ore will be variable depending on rock type, sulphur
grade, copper grade, and processing destination, daily ore control
decisions (e.g., selecting the optimal processing destination) will
be guided by mining software that determines the maximum profit for
each block, rather than by a fixed cut-off grade. The combined mine
plan results in a mine life that extends until 2036.
Los Filos Gold Ounces Produced by Processing
Destination and Source
The LOM plan shows average recoveries of 55% from heap leach
processing and 88% from the CIL plant. LOM production averages
280,000 oz per year commencing in 2023, with peak production
averaging 360,000 oz per year from 2025-2030. LOM AISC averages
$1,081/oz of gold sold. A substantial
decrease in AISC from mid-2024 correlates with the increase in
ounces produced as a result of the commissioning of the CIL
plant.
Los Filos Annual Gold Production &
AISC
PROCESSING
Heap Leach
Two large geosynthetic-lined heap leach pads are in operation,
divided into two sections, one for crushed ore and the other for
ROM ore. ROM ore is currently stacked on Pad 1 and crushed ore on
Pad 2. Pads 1 and 2 cover 2,515,000 m² and 721,000 m²,
respectively, for a total area of 3,236,000 m² . Stacked ore is
fully leached after 120 days for crushed and 180 days for ROM
ores.
Pregnant leach solution from the heap leach pads will continue
to be processed in the existing ADR (adsorption, desorption and
recovery) plant. The ADR plant is a conventional carbon-in-column
adsorption facility associated with an elution circuit, carbon
regeneration circuit and gold refinery that produces a gold-silver
doré product.
As of June 2022, approximately 260
Mt of ore have been stacked on the heap leach pads. There is
sufficient storage capacity for the LOM crushed ore on Pad 2;
however, Pad 1 will not have enough storage capacity to store all
the LOM ROM ore. A third pad (Pad 3) will be constructed at the
southern end of Pad 2 to provide 63.5 Mt of additional storage for
ROM ore. This new pad will be constructed in three phases, starting
with the first phase in 2023. In addition to Pad 3, an "interliner"
is proposed to be constructed on top of portions of Pads 1, 2 and 3
once the pads have been filled to their design capacity. The
interliner will provide 82 Mt of additional storage capacity for
ROM ore and CIL tailings. The interliner will be built in two
phases, with the first phase required by 2031. Leach pad expansions
account for $86 million of the LOM
sustaining capital. The current and planned heap leach pad
infrastructure will be sufficient to support mining operations for
the LOM plan.
CIL Plant
The CIL plant design is based on a robust metallurgical
flowsheet developed for optimum recovery, while taking into account
capital costs and operating costs. As the CIL plant is an addition
to an existing operation, existing site services (power, water,
etc.) will be used, where appropriate, to supply the new
facilities. The process of the new CIL plant includes crushing,
milling, gravity, carbon in leach, carbon regeneration, thickening,
and filtration of the CIL tailings for dry-stack storage. A
second ADR plant will be built to recover gold from the loaded
carbon of the CIL process.
Key project design criteria for the plant are:
- Capacity to treat 10,000 t/d (3.65 Mt/a) of varying blends of
the main ore types as determined by the LOM production
schedule
- Crushing plant utilization of 75% and CIL and tailings
filtration plant utilization of 91.3%, supported by the
incorporation of surge capacity and standby equipment where
required
- The grinding plant will grind ores to P80 0.075 mm and leach
them in a CIL circuit for 40 hours to extract an estimated 90.6%
contained gold and 38.8% contained silver
- The grinding flowsheet includes gravity concentration
- Gold will be recovered from the loaded carbon in a 10-tonne
batch ADR plant
- CIL plant tailings will be thickened, filtered and delivered by
conveyors to a filtered tailings storage facility
Overall processing costs are estimated to average $7.76/t for crush heap leach, $2.85/t for ROM heap leach and $13.25/t for CIL processing. As with most gold
ore processing plants, the three largest cost components are
cyanide, grinding media and power.
TAILINGS
A total of 45.7 Mt of tailings will be generated from fine
grinding the various ores during the CIL process. The tailings will
be filtered through a series of pressure filter presses to achieve
a high degree of dewatering, with the resultant tailings cake
disposed of in a filtered tailings storage facility on the eastern
side of Pad 1, which is close to the planned location of the
tailings filter plant.
INFRASTRUCTURE
The majority of infrastructure requirements for expansion at Los
Filos are already in place, including heap leach facilities, an ADR
plant, water storage and distribution, maintenance workshop,
laboratory, site administration buildings, warehouse and workforce
facilities. New infrastructure required includes the 10,000 t/d CIL
plant, a new 40 MW electric substation, an extension of the 115kV
high voltage transmission line to the new substation, an upgrade of
the mobile equipment workshop, additional waste rock storage
facilities, and an expansion of the heap leach pads.
Water usage for the Los Filos Mine Complex is currently 1.0
Mm3/a and the permit allows for 1.2 Mm3/a of
extraction. An application to increase the water permit to 2.2
Mm3/a is in process.
Additional power will be required to operate the CIL plant. The
current capacity of its existing electrical substation is 20 MW to
satisfy a demand of up to 14 MW peak demand. The CIL plant will
consume additional energy beyond the capacity of the existing
substation; therefore, a larger, 40 MW substation is proposed to
provide electrical energy to the expanded mine. An application was
made to CENACE (Mexico's federal
electricity commission utility) for the additional energy
required, and CENACE completed a study to confirm energy
availability and electrical infrastructure upgrades. The study will
be updated once a final decision to advance the CIL plant is
made.
LABOUR
As Los Filos is currently in operation, existing management,
operating and maintenance labour will support the new CIL
operations and maintenance teams. There is abundant skilled labour
in the region. The Los Filos workforce is typically around 1,500
employees and contractors, drawn primarily from the nearby
communities of Carrizalillo, Mezcala and Xochipala. Non-union personnel fill primarily
administration and supervisory roles. Other roles, including
maintenance, operators, and process plant personnel, are filled
with union personnel or contractors. The underground and open pit
operations personnel and ADR plant personnel operate on two shifts
per day. The Feasibility Study contemplates the need for an
additional 114 positions to support CIL plant operations.
TECHNICAL REPORT
PREPARATION
Equinox Gold retained AMC Mining Consultants, Lycopodium
Minerals Canada Ltd., Paul Sterling,
and StruthersTech Technical Solutions Ltd. to jointly prepare with
the Equinox Gold Technical Services group a Technical Report on Los
Filos. The Technical Report provides an update of a previous study
dated March 11, 2019. The Technical
Report also provides an update on the ownership status of the
project, Mineral Resources, Mineral Reserves and project
economics.
The Qualified Persons ("QPs") are Gary
Methven, P.Eng., of AMC Mining Consultants; Paul Salmenmaki, P.Eng., of AMC Mining
Consultants; Mo Molavi, P.Eng., of
AMC Mining Consultants; Eugene
Tucker, P.Eng., of AMC Mining Consultants; Glenn Bezuidenhout, FSAIMM, of Lycopodium
Minerals Canada Ltd.; Paul Sterling,
P.Eng., independent consultant; Riley
Devlin, P.Eng., of StruthersTech Technical Solutions Ltd.;
and Kelly Boychuk, P.Eng.,
Ali Shahkar, P.Eng., and
Travis O'Farrell, P.Eng., all of
Equinox Gold. The Mineral Resource estimates were prepared by
Equinox Gold geologists under the supervision of Ali Shahkar and were reviewed by AMC Mining
Consultants prior to use for the Feasibility Study. The Mineral
Reserves, mine plan and mining sections of the study were prepared
by or under the supervision of AMC Mining Consultants. The
metallurgical testwork, process design and process plant
information were prepared by or under the supervision of
Paul Sterling and Lycopodium
Minerals Canada. The study is being summarized into a technical
report that will be filed within 45 days on the Company's website
at www.equinoxgold.com, on SEDAR at www.sedar.com and on EDGAR at
www.sec.gov/edgar, in accordance with National Instrument
43-101.
QUALIFIED PERSONS
The technical content of this news release has been reviewed and
approved by the QPs who were involved with preparation of the NI
43-101 Updated Technical Report for the Los Filos Mine Complex,
Guerrero State, Mexico.
For readers to fully understand the information in this release
they should read the technical report in its entirety when it is
available on SEDAR, including all qualifications, assumptions,
exclusions and risks. The technical report is intended to be read
as a whole and sections should not be read or relied upon out of
context.
ABOUT EQUINOX GOLD
Equinox Gold is a growth-focused Canadian mining company with
seven operating gold mines, construction underway at a new project,
and a clear path to achieve one million ounces of annual gold
production from a pipeline of development and expansion projects.
Equinox Gold operates entirely in the Americas with one property in
Canada, two properties in
the United States, one in
Mexico and four in Brazil. Equinox Gold's common shares are
listed on the TSX and the NYSE American under the trading symbol
EQX. Further information about Equinox Gold's portfolio of assets
and long-term growth strategy is available at www.equinoxgold.com
or by email at ir@equinoxgold.com.
EQUINOX GOLD CONTACTS
Greg Smith, President and Chief
Executive Officer
Rhylin Bailie, Vice President,
Investor Relations
Tel: +1 604-558-0560
Email: ir@equinoxgold.com
CAUTIONARY NOTES AND
FORWARD-LOOKING STATEMENTS
Technical Information
Doug Reddy, M.Sc., P.Geo.,
Equinox Gold's Chief Operating Officer, and Scott Heffernan, M.Sc., P.Geo., Equinox Gold's
EVP Exploration, are Qualified Persons under National Instrument
43-101 for Equinox Gold and have reviewed and approved the
technical content of this document.
Cautionary Note to U.S. Readers Concerning Estimates of
Mineral Reserves and Mineral Resources
Disclosure regarding the Company's mineral properties,
including with respect to mineral reserve and mineral resource
estimates included in this news release, was prepared in accordance
with National Instrument 43-101 – Standards of Disclosure for
Mineral Projects ("NI 43-101"). NI 43-101 is a rule developed by
the Canadian Securities Administrators that establishes standards
for all public disclosure an issuer makes of scientific and
technical information concerning mineral projects. NI 43-101
differs significantly from the disclosure requirements of the
Securities and Exchange Commission (the "SEC") generally applicable
to U.S. companies. Accordingly, information contained in this press
release is not comparable to similar information made public by
U.S. companies reporting pursuant to SEC disclosure
requirements.
Non-IFRS and Other Financial Measures
This news release includes certain measures with no
standardized meaning under International Financial Reporting
Standards ("IFRS"), namely: all-in sustaining costs ("AISC"); cash
costs; AISC per oz sold; and sustaining and non-sustaining capital
expenditures. Such measures are "non-GAAP financial measures",
"non-GAAP ratios", "supplementary financial measures" or "capital
management measures" (as such terms are defined in National
Instrument 52-112 – Non-GAAP and Other Financial Measures
Disclosure). Equinox Gold believes these measures, while not
a substitute for measures of performance prepared in accordance
with IFRS, provide investors an improved ability to evaluate the
underlying performance of the Company. These measures do not have
any standardized meaning prescribed under IFRS, and therefore may
not be comparable to the information provided by other
issuers. Please see the information under the heading
Non-IFRS Measures in Equinox Gold's Management's Discussion and
Analysis (MD&A) for the year ended December 31, 2021, which section is incorporated
by reference in this news release for a description of the non-IFRS
financial measures noted above. The MD&A may be found on SEDAR
at www.sedar.com and on EDGAR at
www.sec.gov/EDGAR.
Forward-looking Statements
This news release contains certain forward-looking
information and forward-looking statements within the meaning of
applicable securities legislation and may include future-oriented
financial information. Forward-looking statements and
forward-looking information in this news release relate to, among
other things: the strategic vision for the Company and expectations
regarding exploration potential, production capabilities and future
financial or operational performance of Los Filos; the Company's
ability to successfully advance its growth and development
projects, including the expansion of the Bermejal underground and
construction of the CIL Plant at Los Filos, the expansion at Castle
Mountain and the construction of Greenstone; the Company's production and cost
expectations; and the conversion of Mineral Resources to Mineral
Reserves. Forward-looking statements or information generally
identified by the use of the words "will", "continue", "expected",
"potential", "estimate", "on track" and similar expressions and
phrases or statements that certain actions, events or results
"could", "would" or "should", or the negative connotation of such
terms, are intended to identify forward-looking statements and
information. Although the Company believes that the expectations
reflected in such forward-looking statements and information are
reasonable, undue reliance should not be placed on forward-looking
statements since the Company can give no assurance that such
expectations will prove to be correct. The Company has based these
forward-looking statements and information on the Company's current
expectations and projections about future events and these
assumptions include: Equinox Gold's ability to achieve the
exploration, production, cost and development expectations for Los
Filos and its other operations and projects; prices for gold
remaining as estimated; currency exchange rates remaining as
estimated; availability of funds for the Company's projects and
future cash requirements; prices for energy inputs, labour,
materials, supplies and services; the Company's working history
with the workers, unions and communities at Los Filos; no
labour-related disruptions and no unplanned delays or interruptions
in scheduled construction, development and production, including by
blockade or industrial action; construction of Greenstone being completed and performed in
accordance with current expectations; expansion projects at Los
Filos and Castle Mountain being completed and performed in
accordance with current expectations; Mineral Reserve and Mineral
Resource estimates and the assumptions on which they are based; all
necessary permits, licenses and regulatory approvals are received
in a timely manner; tonnage of ore to be mined and processed; ore
grades and recoveries; capital, decommissioning and reclamation
estimates; and the Company's ability to comply with environmental,
health and safety laws and other regulatory requirements. While the
Company considers these assumptions to be reasonable based on
information currently available, they may prove to be incorrect.
Accordingly, readers are cautioned not to put undue reliance on the
forward-looking statements or information contained in this news
release.
The Company cautions that forward-looking statements and
information involve known and unknown risks, uncertainties and
other factors that may cause actual results and developments to
differ materially from those expressed or implied by such
forward-looking statements and information contained in this news
release and the Company has made assumptions and estimates based on
or related to many of these factors. Such factors include, without
limitation: fluctuations in gold prices; fluctuations in prices for
energy inputs, labour, materials, supplies and services;
fluctuations in currency markets; operational risks and hazards
inherent with the business of mining (including environmental
accidents and hazards, industrial accidents, equipment breakdown,
unusual or unexpected geological or structural formations,
cave-ins, flooding and severe weather); inadequate insurance, or
inability to obtain insurance to cover these risks and hazards;
employee relations; relationships with, and claims by, local
communities and indigenous populations; the Company's ability to
obtain all necessary permits, licenses and regulatory approvals in
a timely manner or at all; changes in laws, regulations and
government practices, including environmental, export and import
laws and regulations; legal restrictions relating to mining; risks
relating to expropriation; increased competition in the mining
industry; and those factors identified in the section titled "Risks
and Uncertainties" in the Company's MD&A dated March 23, 2022 for the year ended December 31, 2021, and in the section titled
"Risks Related to the Business" in the Company's Annual Information
Form dated March 24, 2022 for the
year ended December 31, 2021, all of
which are available on SEDAR at www.sedar.com and on EDGAR at
www.sec.gov/edgar. Forward-looking statements and information
are designed to help readers understand management's views as of
that time with respect to future events and speak only as of the
date they are made. Except as required by applicable law, the
Company assumes no obligation to publicly announce the results of
any change to any forward-looking statement or information
contained or incorporated by reference to reflect actual results,
future events or developments, changes in assumptions or changes in
other factors affecting the forward-looking statements and
information. If the Company updates any one or more forward-looking
statements, no inference should be drawn that the Company will make
additional updates with respect to those or other forward-looking
statements. All forward-looking statements and information
contained in this news release are expressly qualified in their
entirety by this cautionary statement.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/equinox-gold-announces-updated-feasibility-study-for-los-filos-expansion-301653142.html
SOURCE Equinox Gold Corp.