TIDMAYM 
 
Anglesey Mining plc     LSE:AYM 
 
18 March 2011 
 
LIM files Technical Report on its DSO iron ore projects in Labrador and Quebec 
 
Anglesey Mining plc's 41% owned associate Labrador Iron Mines Holdings Limited 
("LIM") or (the "Company") (TSX: LIM) reports the filing on SEDAR (the official 
website that provides access to most Canadian public securities documents and 
information filed by public companies) of a Technical Report addressing the ongoing 
exploration and development of its DSO iron ore projects on the Company's various 
deposits in Western Labrador and North Eastern Quebec. 
 
The Technical Report has been prepared as a result of additional metallurgical 
testwork and process design and following the completion of the construction of 
the Silver Yards processing plant facility and other associated infrastructure 
and the commencement of initial mining at the James deposit. 
 
The Report proposes various additions to the Silver Yards plant as a result of 
the recent metallurgical testwork and discusses a preliminary production 
schedule for the current resources together with the future development of the 
further twelve deposits containing historic resources through to the year 2028. 
The Report also makes recommendations for further exploration on the various 
deposits and other associated work required to advance the deposits towards 
production. 
 
The Technical Report notes the recent new resource estimates for the Houston 
and Denault deposits as a result of additional exploration drilling carried out 
in 2010. [See LIM Press Release dated February 11, 2011 and Houston Technical 
Report filed on SEDAR February 21, 2011.  See also LIM Press Release dated 
March 4, 2011 and Denault Technical Report filed on SEDAR March 14, 2011]. 
 
LIM has now defined 37 million tonnes of current NI 43-101 compliant direct 
shipping hematite iron ore resources at the first four deposits that it intends 
to develop.  In addition, a further 125 million tons of historical resources 
exist on LIM's other properties that were defined by IOC during their 
historical operations in the area. 
 
The current resource estimates for the James, Redmond, Houston and Denault 
deposits are summarized in following table. 
 
Total NI 43-101 Compliant Resources, Labrador and Quebec 
 
Area         Classification        Tonnes (x1000)  Fe%   P%    Mn%  SiO2% Al2O3% 
James1       Indicated             8,098,000       57.7  0.027 0.7  14.1  0.5 
James1       Inferred              111,000         53.6  0.036 0.1  19.9  0.5 
Redmond 2B1  Indicated             849,000         59.86 0.12  0.37 5.05  2.09 
Redmond 2B1  Inferred              30,000          57.27 0.133 0.64 5.87  4.09 
Redmond 51   Indicated             2,084,000       54.95 0.048 1.17 10.97 0.81 
Redmond 51   Inferred              78,000          52.34 0.068 1.95 10.84 0.96 
Houston2     Measured              10,439,000      58.93 0.060 0.91 11.34 0.78 
Houston2     Indicated             9,060,000       57.55 0.060 0.96 13.48 0.68 
Houston2     Inferred              1,024,000       55.8  0.055 1    16.5  0.5 
Denault3     Measured              4,456,000       55.1  0.077 2.4  7.5   1.1 
Denault3     Indicated             1,928,000       54.2  0.074 2.3  9.0   1.0 
Denault3     Inferred              369,000         53.9  0.069 2.7  9.4   0.9 
Total        Measured & Indicated  36,914,000      57.41 0.06  1.09 11.71 0.75 
Total        Inferred              1,612,000       55.07 0.06  0.76 14.64 0.68 
 
 
"Technical Report Resource Estimation of the James, Redmond 2B and Redmond 5 
Mineral Deposits Located in Labrador, Canada for Labrador Iron Mines Limited" 
by Maxime Dupéré, geo, of SGS Geostat Ltd. dated December 18, 2009; [SEDAR 
filed December 23, 2009]. 
 
See Technical Report on the Houston Iron Ore Deposit Western Labrador, Province 
of Newfoundland and Labrador, Canada" by T. N. McKillen, B.A.(Mod), M.A., 
M.Sc., P.Geo, D. William Hooley, B.Sc(Eng.), FAusIMM and Daniel Dufort, 
(P.Eng.) concerning the Houston property in Labrador dated February 21, 2011; 
[SEDAR filed February 21, 2011]. 
 
"Technical Report and Resources Estimate on the Denault Iron Ore Deposit 
Province of Québec Canada" by T. N. McKillen, B.A.(Mod), M.A., M.Sc., P.Geo; 
dated March 11, 2011 [SEDAR filed March 14, 2011]. 
 
 
The historical resources referred to in this document are based on work 
completed and estimates prepared by the Iron Ore Company of Canada ("IOC") 
prior to 1983 and were not prepared in accordance with NI 43-101.  These 
historical estimates are not current and do not meet NI 43-101 Definition 
Standards. A qualified person has not done sufficient work to classify the 
historical estimate as current mineral reserves.  These historical results 
provide an indication of the potential of the properties and are relevant to 
ongoing exploration. The historical estimates should not be relied upon. 
 
Preliminary Development Schedule 
 
LIM intends to develop all these resources in five separate stages.  The first 
four stages will see the various deposits treated in three beneficiation 
plants, to be built adjacent to several of the deposits that comprise the 
Central, South Central and North Central Zones. 
 
Stage 1 incorporates the James and Redmond deposits at the Silver Yards plant 
which is now constructed and where production is expected to commence in the 
spring of 2011. This stage also contemplates the treatment of other nearby 
deposits (Central Zone) and is expected to continue until 2021. 
 
Stage 2 contemplates a new plant at the Redmond Mine site initially treating 
Houston ore, commencing in 2013, and will continue until about 2022 (South 
Central Zone). Stage 3 is based on a third plant near Howse, (North Central 
Zone) which will treat ore from Barney and Howse, commencing in 2015 and will 
continue until about 2028. Stage 4 treating ore from the southern deposits 
Sawyer Lake and Astray Lake (South Zone) through the Redmond plant will 
continue until about 2028.  Stage 5 based on ore from the Northern deposits 
(North Zone) will follow the first 4 stages. 
 
Overall production of saleable iron ore product is planned to commence at 
around 1.5 million tonnes annually (mta) in 2011 and will build up to about 5 
mta by 2015 and, based on the future development of all other deposits, stages 
1 to 4 will continue at this level until about 2028 when stage 5 is expected to 
commence. 
 
Only the James and Redmond Deposits and the Silver Yards plant have completed 
environmental assessment and permitting. Further environmental assessment and 
permitting will be required for all the other deposits. Detailed mine design 
and metallurgical testwork has been carried out on those deposits that will 
form the basis of production for the initial years but further exploration, 
testwork and design is required for all the remaining resources. A Feasibility 
Study has not been completed on any of these Projects. 
 
The first plant at Silver Yards and mine construction at James are essentially 
complete and initial production is expected in the spring of 2011. 
 
Plant Upgrade and Expansion 
 
Based on the current testwork, a program of plant enhancement on the Silver 
Yards plant is now planned for 2011 and 2012 with the objective to increase 
both the plant throughput and recovery. 
 
The current Silver Yards plant installation (Phase I) consists of a washing and 
screening plant to produce lump and sinter fines. The plan for the first year 
is to only wash and screen the higher grade blue ore material, while higher 
silica blue and yellow ore will be stockpiled for later treatment. 
 
It is intended that the Silver Yards plant will be upgraded and expanded to 
improve recoveries, treat lower grade and higher silica ores and increase 
throughput and output. 
 
Phase II will consist of the installation of a fines recovery system and pan 
filter.  This installation will be completed during the summer of 2011 and 
should commence operation in September 2011. 
 
Phase III of the Silver Yards Plant will be the installation of an additional 
line which will increase the plant throughput capacity and improve recoveries. 
 
This work is currently being planned and will entail the installation of jigs 
to upgrade the final products and the installation of a magnetic separation 
stage on the slimes fraction to produce ultra-fines. Testing and design of the 
Phase III expansion is currently in progress and, dependent on the results of 
that program, the Phase III expansion should be installed for operation in 
mid-2012.  The additional line when installed will initially be used to process 
the higher silica ore and the yellow ore will also be processed when the 
equipment in Phase 3 is fully installed. 
 
South Central Zone 
 
The South Central Zone comprises the Houston and Malcolm deposits.  The Houston 
deposits located in Labrador some 20kms south-east of Silver Yard currently 
comprises 19.5 million tonnes of compliant resource. 
 
It was originally planned to treat Houston ore at the Silver Yards plant but 
the increased Houston resource suggests that a new stand-alone plant to treat 
Houston and other nearby deposits should be constructed.  Subject to completion 
of environmental assessment and permitting, this plant is now planned to be 
built adjacent to the site of the currently permitted Redmond mine and to 
commence production in 2013. 
 
The Houston deposits remain open and an additional drill program will take 
place in 2011 with the aim of increasing the size of these deposits and 
enhancing the resource estimate. 
 
Capital Costs Estimate 
 
The additional capital costs for the Silver Yards plant projects are estimated 
to be $3 million in 2011 for additional processing equipment to improve fines 
recovery and approximately $35 million in 2012 for plant expansion and 
enhancement. 
 
The initial capital cost of the Houston Mine Project for mine site preparation, 
overburden removal and road construction is estimated to be approximately $5 
million in 2012/2013. 
 
The capital cost of the new Redmond Plant is estimated to be approximately $35 
million in 2012/13 based on the actual cost incurred by LIM on the construction 
of the Silver Yard plant but modified to incorporate the single line design now 
planned for the Redmond plant. An additional $8 to $10 million is estimated for 
the cost of re-laying the Redmond rail spur line. These cost estimates are 
subject to final permitting and detailed engineering and design. 
 
Operating Cost Estimates 
 
The average operating costs for the James-Redmond Silver Yards Project are 
estimated to be in the range of approximately CAD$50 per tonne, with all mining 
and processing activities carried out by contractors, and with rail 
transportation and port handling costs collectively accounting for 
approximately half of the total operating costs.  The year 2011 is considered 
to be a start-up year and initial unit operating costs are expected be about 
10% higher than average. 
 
Qualified Persons 
 
The authors of the Technical Report (T.N. McKillen, D.W. Hooley and D. Dufort) 
are either directors and/or officers of LIM and/or its subsidiaries. The 
authors are "qualified persons" within the meaning of National Instrument 
43-101 - Standards of Disclosure for Mineral Projects of the Canadian 
Securities Administrators and have approved this Press Release. The authors are 
not independent as described in section 1.4 of NI 43-101. D.W. Hooley approves 
the contents of this Press Release. 
 
About Labrador Iron Mines Holdings Limited (LIM) 
 
LIM's Schefferville Area project involves the development of twenty direct 
shipping iron ore deposits in western Labrador and north-eastern Quebec near 
Schefferville, Quebec. The Company's properties are part of the historic 
Schefferville area iron ore district where mining of adjacent deposits was 
previously carried out by the Iron Ore Company of Canada from 1954 to 1982. 
 
Labrador Iron Mines contemplates mining in stages, the first phase of Stage 1 
comprising the James and Redmond deposits, which are located in close proximity 
to existing infrastructure, and for which all operating permits have been 
issued and plant construction and mine development is nearing completion. 
 
For further information, please view the Company's website at 
www.labradorironmines.ca. 
 
About Anglesey Mining plc 
 
Anglesey Mining with its LSE main board listing is primarily focused on its 41% 
interest in Labrador Iron Mines (TSX:LIM). In addition to any new projects that 
may be brought forward the company owns 100% of Parys Mountain in North Wales 
with an historical resource in excess of 7 million tonnes at over 9% combined 
copper, lead and zinc. 
 
For further information, please contact: 
 
Bill Hooley, Chief Executive +44 (0) 1492 541981 
 
Ian Cuthbertson, Finance Director +44 (0) 1248 361333 
 
Emily Fenton / Charlie Geller, 
Tavistock Communications +44 (0) 20 7920 3155 / +44 (0) 7788 554035 
 
 
 
END 
 

Anglesey Mining (LSE:AYM)
Graphique Historique de l'Action
De Juin 2024 à Juil 2024 Plus de graphiques de la Bourse Anglesey Mining
Anglesey Mining (LSE:AYM)
Graphique Historique de l'Action
De Juil 2023 à Juil 2024 Plus de graphiques de la Bourse Anglesey Mining