The company deems the information contained within this
announcement to constitute Inside Information as stipulated under
the Market Abuse Regulation (E.U.) No. 596/2014, as it forms part
of U.K. domestic law under the European Union (Withdrawal) Act
2018, as amended. Upon the publication of this announcement via a
regulatory information service, this information is considered to
be in the public domain.
Cadence Minerals
Plc
("Cadence Minerals",
"Cadence", or "the Company")
PFS Level Economic Study for
the Amapa Iron Ore Project Increases Net Present Value to US$1.97
Billion
Cadence Minerals (AIM: KDNC), the
AIM-quoted investment company, is pleased to announce an updated
Pre-Feasibility Study ("PFS") on the Amapá Iron Ore Project
("Amapá", "Project" or "Amapá Project"), in northern Brazil.
Cadence owns an equity stake of 34.6% in the Project. The updated
PFS is based on the Direct Reduction grade ("DR-grade") flow sheet
announced on
AIM: 26 November 2024.
Highlights:
· 73%[1] increase of post-tax
Net Present Value ("NPV10%") to US$1.97
billion and 56% internal
rate of return ("IRR").
· Average annual free cash
flow from start-up to closure is estimated to be
US$342 million.
· The Project is estimated to generate a total of US$9 billion
in gross revenues, US$4.9 billion in net operating profit and
US$4.6 billion in free cash flow
over its 15-year mine life.
· Revised processing plant design to produce 67.5% Iron ("Fe") DR-grade iron ore
concentrate at an average[2] rate of
5.5 million metric tonnes per
annum ("Mtpa").
· Free on Board
("FOB") C1 Cash Costs US$33.7 per dry metric ton ("DMT") at
the port of Santana. Cost and
Freight ("CFR") C1 Cash Costs US$61.9/DMT in China.
· Pre-production capital of US$377 million, and the payback period is reduced to 3 years
due to higher free cash flows.
Cadence CEO Kiran Morzaria
commented: "This significant update to
the Amapá Prefeasibility Study, which includes the DR-grade
concentrate flow sheet, reinforces our firm belief that the project
can add substantial value to Cadence. The increased net present
value of $1.97 billion and improved post-tax internal rate of
return reflect significant advancements in the project's robust
economics.
The Amapá Project represents a well-developed and largely
de-risked opportunity, featuring established mineral reserves,
advanced environmental permitting, and complete control of
integrated rail and port infrastructure. This ownership and control
of the infrastructure contribute to the project's low-cost base and
will enable the pursuit of regional expansion opportunities, with
substantial resources located within 30 kilometres of the existing
rail line. In addition to the DR-grade flow sheet, the project will
use 100% renewable energy sources. We anticipate this will help us
achieve one of the lowest carbon footprints in the region while
still delivering a robust and highly profitable
project.
We
are excited about the potential of the Amapá Iron Ore Project and
look forward to providing further updates on our
progress."
Chairman Andrew Suckling
added: "The Amapa Project is now emerging as a material "green iron"
project, backed by product quality and highly competitive economic
metrics. We are at this juncture due to the tireless efforts of the
Board and Project team, and I'd like to put on record my thanks and
gratitude to them and our shareholders and stakeholders. I look
forward to Amapa playing its part in "green steel" production
and the decarbonisation of the iron and steel
industry."
Table 1 Key Project Metrics (100% project
basis)
Metric
|
Unit
|
Revised PFS July 2024
|
Updated DR Grade PFS Nov 2024
|
Total ore feed to the
plant
|
Mt (dry)
|
176.93
|
176.93
|
Life of Mine
|
Years
|
15
|
15
|
Fe grade of ore feed to the
plant
|
%
|
39.34
|
39.34
|
Recovery
|
%
|
76.27
|
75.27
|
62.0% iron ore concentrate
production
|
Mtpa
|
0.95
|
-
|
65.4% iron ore concentrate
production
|
Mtpa
|
4.51
|
-
|
67.5% iron ore concentrate
production
|
Mtpa
|
-
|
5.52
|
C1 Cash Costs FOB
*
|
US$/DMT
|
33.50
|
33.75
|
C1 Cash Costs CFR **
|
US$/DMT
|
62.19
|
61.93
|
Pre-Production capital
investment***
|
US$M
|
343
|
377
|
Sustaining capital investment over
life of mine****
|
US$M
|
245
|
220
|
AISC Cash Costs FOB*****
|
US$/DMT
|
45.22
|
47.38
|
Platts TSI IODEX 65% Fe CFR
used
|
US$/DMT
|
118.75
|
120.00
|
Post-tax
NPV10%
|
US$M
|
1,145
|
1,977
|
Post-tax IRR
|
%
|
42
|
56
|
Project payback
|
Years
|
4
|
3
|
Total profit after tax (net
operating profit)
|
US$B
|
3.14
|
4.96
|
*
|
Means operating cash costs, including
mining, processing, geology, occupational health and safety
environment, rail, port and site G&A, divided by the tonnes of
iron ore concentrate produced. It excludes royalties and is quoted
on a FOB basis (excluding shipping to the customer).
|
**
|
This means the same as C1 Cash Costs
FOB; however, it includes shipping to the customer in China
(CFR).
|
***
|
Includes direct tax credit rebate
over 48 months
|
****
|
Includes both sustaining capital and
deferred capital expenditure, specifically, improvements to the
railway, the installation of a slurry pipeline and mine site to
rail load out
|
*****
|
Includes all the C1 Cash Cost, plus
royalties, pre-production capital investment and sustaining capital
investment over the life of the mine and is quoted on a FOB
basis
|
Introduction
The Project comprises an open-pit
iron ore mine, a processing and beneficiation plant, a railway
line, and an export port terminal. The Amapá Project is 100% owned
by DEV Mineração S.A. ("DEV") and its subsidiaries. DEV is owned by
Pedra Branca Alliance Pte. Ltd. ("PBA"), a joint venture ("JV")
between Cadence and Indo Sino Trade Pte Ltd ("Indo
Sino").
The Project ceased operations in
2014 after the port facility suffered a geotechnical failure, which
limited iron ore export. Before the cessation of operations, the
Project generated an underlying profit of US$54 million in 2012 and
US$120 million in 2011. Operations commenced in December 2007, and
in 2008, the Project produced 712 thousand tonnes of iron ore
concentrate. Production steadily increased, producing 4.8 Mt and
6.1 Mt of iron ore concentrate products in 2011 and 2012,
respectively.
Cadence and Indo Sino, through their
JV, acquired 100% of DEV's shareholding in 2022 through the
submission of a judicial restructuring plan approved by the
unsecured creditors. As part of this plan, DEV sought to redevelop
the Amapá Project. This strategy includes a plan to resume
operations after plant revitalisation and modifications, aimed at
improving product quality and increasing recovery, along with
recovery of the port, railway, and support areas.
It should be noted that Indo Sino
and Cadence have managed this PFS, and it represents an update to
the PFS published on
AIM: 3 January 2023 and the revised PFS
published on
AIM: 9 July 2024. In particular, this
updated PFS has been prepared to reflect the 67.5% Fe concentrate
flow sheet.
Location
The Project is in Amapá state. Amapá
is Brazil's second least populous state and the eighteenth largest
by area. Most of the Amapá state territory is rainforested, while
the remaining areas are covered with savannah and plains. The State
capital and largest city is Macapá (pop. circa 500,000), with the
municipality of Santana (pop. circa 120,000) located just 14km to
the southwest.
The Amapá mine is some 125km
northeast of the state capital, Macapá, and the port facility is
located on the Amazon River in the municipality of Santana, close
to Macapá, as shown in (Figure
1). The port site in Santana is located 170km from the mouth
of the Amazon River. The nearest populace centre to the Amapá mine
is Pedra Branca Do Amapari, some 11km west, with the larger town of
Serra do Navio 18 km northwest.
Figure 1 Location of the Amapá Project
Amapá Project Components
The Amapá Project PFS encompasses
four distinct but completely integrated operational components that
formed part of the original PFS. The four areas are:
Amapá Mining Complex: An
open-pit iron ore mine with various open pits, an iron ore
concentration and beneficiation plant, associated waste rock dumps,
and a tailings management facility.
Railway Line: Integrated 194 km
railway line connecting Serra do Navio to the port terminal at
Santana. The rail passes via Pedra Branca do Amapari (180 km from
the port), located 13 km from the Amapá mine and the
plant.
Export Port Terminal: An
integrated industrial port site, privately owned and controlled by
DEV, is located in Santana. The terminal had the capacity for
loading the Supramax and Handymax vessels.
Transhipment Solution: A
Capesize vessel is partially loaded at the berth in Santana port
and topped off in the open ocean, 200 nautical miles from the
berth.
Updated Pre-Feasibility Study
As announced on
AIM: 26 November 2024, the Amapá Iron
Ore Project completed its metallurgy test work and successfully
produced a DR-grade iron ore concentrate. The updated PFS
investigates all the design, engineering, and business parameters
required to implement the DR-grade flow sheet at a rate of 5.5 Mtpa
(dry basis)/6.03 Mtpa (wet basis). This comprises the mine schedule
published in July 2024 and the processing plant and associated
infrastructure required for DR-grade concentrate
production.
Mining
Schedule
The improved flow sheet's annual
feed rate ("ROM") is 13.99 Mtpa (wet base). The mining schedule
prepared for the revised PFS published earlier in the year was
utilised for this purpose. The mine engineering and design work for
this PFS, including equipment requirements and mining strategy,
have been undertaken by Wardell Armstrong International. These
works have been conducted at the PFS level and incorporate an Ore
Reserve Estimate for open pit mining, which was prepared under the
guidelines of the JORC Code (2012). The Ore Reserve for the Amapá
Project is at 195.8 million tonnes, with an average grade of 39.34%
Fe and a cut-off grade of 25% Fe.
A Life of Mine ("LOM") production
plan was scheduled using the Deswik.Blend® Scheduler Optimiser. The
solids used in the mine schedule were based on the final pit
design, with a Selective Mining Unit of 100m x 200m x 4m. The LOM
schedule allows for 15 years of production with the current
economic values and cut-off of 25% Fe.
The resultant LOM strip ratio is
approximately 0.4:1 (tonnes waste: tonnes ore), and the average ore
mine delivered to the plant is 13.99 Mtpa. A site plan of the pits
and phases is outlined in (Figure
2).
Figure 2 Open Pit Design Phases
Processing
Plant
Pei Si Engineering Incorporated
conducted the test work and designed the flow sheet. The
metallurgical test work established that the optimal flow sheet
utilised a regrind, which feeds into a low-intensity magnetic
separator. This process produces two streams: the first stream goes
to a reverse flotation circuit, while the second stream is sent to
a high-intensity magnetic separator, followed by a second reverse
flotation circuit. As a result of the above, the following main
changes were made to the original PFS flow sheet published in
January 2023.
·
Removing the jigging circuit, with the iron being
recovered via the grinding, magnetic, and flotation circuits. This
improves the iron recovery rate.
·
Replacing hydrocyclone desliming with thickeners,
improving classification efficiency and lowering power
consumption.
·
The 67.5% flow sheet will remove the 62% product
stream, eliminating the spiral circuit. This will shorten the
process flow and reduce power consumption.
·
Adding a flow sheet to improve iron concentrates
from 65.4% to 67.5% via regrinding the material from the magnetic
separator, meaning finer particles can be further liberated,
improving iron concentrate grade to 67.5%.
·
Replacement of all slurry, water, and reagent
pumps involved in the beneficiation process.
·
Due to a single concentrate product, the conveyor
transport is replaced by a slurry pipeline and filtrate water
return pipeline, reducing operating and capital costs.
·
The particle size of the concentrate after the
tower mills is too fine to be filtered by the existing vacuum disc
filters. Therefore, horizontal press filters are required to ensure
the moisture content of the filter cake is no greater than
8%.
·
A train loading system will be built in the train
loading area.
An outline of the plant layout is
shown in (Figure
3)
Figure 3 DR-Grade Plant Layout
Cost
Estimates
To evaluate the project's economics,
an updated PFS financial model, which included the updated mining
schedule, capital costs ("CAPEX"), operational costs ("OPEX"), and
revised product price, was developed. All other aspects of the
financial analysis remained the same as per the revised PFS
published in July 2024.
The CAPEX estimate is based on the
layout for all areas of the Project and is supported by mechanical
equipment lists and engineering drawings. The costs for these items
have been derived from informal vendor quotes for the equipment and
materials or consultant engineering databases. Parts of the CAPEX
estimate are after tax (with the duties and taxes deemed
recoverable calculated separately), include contingency, and
exclude escalation. The CAPEX estimate includes all the direct and
indirect costs, local taxes and duties and appropriate
contingencies for the facilities required to bring the Project into
production, as defined by a PFS-level engineering study. As this is
a PFS, the cost accuracy is estimated at ± 25% and has a base date
of June 2022 and November 2024. Pre-production, deferred and
sustaining summaries of the capital cost estimates are provided
below. Pre-production CAPEX has increased due to the equipment
required to achieve the DR-grade product. However, the variance in
the total CAPEX has been reduced. This is a result of producing one
product stream, which uses a slurry pipeline to transport the
concentrate from the mine to the rail loadout station rather than a
conveyor.
Table 2 Pre-Production Capital Cost
Estimates
Description
|
Revised PFS July 2024 (US$M)
|
Updated DR Grade PFS
Nov 2024 (US$M)
|
Direct Capex Mining
|
2.8
|
2.8
|
Direct Capex Beneficiation
Plant
|
104.4
|
133.7
|
Direct Capex Rail
|
28.5
|
28.5
|
Direct Capex Port
|
113.9
|
113.9
|
Sub-total Direct Capex
|
249.6
|
278.9
|
Sub-total Indirect Capex
|
55.7
|
56.4
|
Environment and Community
Cost
|
7.1
|
6.8
|
Deduct Tax Credit
|
-14.6
|
-14.0
|
Contingency
|
44.7
|
49.2
|
Pre-Production Capex Costs
|
343.2
|
377.5
|
Table 3 Deferred, sustaining, and closure capital costs over
LOM.
Description
|
Revised PFS July 2024 (US$M)
|
Updated DR Grade PFS
Nov 2024 (US$M)
|
Railway (2nd
Phase)
|
20.0
|
20.0
|
Tailings Storage Facility
|
9.8
|
9.8
|
Pipeline Construction /
Conveyor
|
60.5
|
33.6
|
Pipeline Construction -
EIA/RIMA
|
0.4
|
0.3
|
Contingency
|
-
|
9.6
|
Stay in Business
|
90.7
|
84.4
|
Closure Costs
|
62.8
|
62.8
|
Total Deferred Capital Costs
|
244.5
|
220.5
|
OPEX for the Project has been
prepared based on the Project physicals, detailed estimates of the
consumption of key consumables based on those physicals, and the
unit cost of consumables.
The periods considered are annual,
and production follows the production plan produced by DEV, based
on a yearly output of 5.5 Mtpa of DR-grade (dry basis) / 6.03 Mtpa
(wet basis). OPEX comprises physicals, labour, reagents and
operating consumables, freight and power costs, mobile equipment,
utilities, maintenance and mining contract costs, external
contractor costs, environmental, and miscellaneous/other General
and Administrative (G&A) expenses. OPEX estimates were prepared
or advised by independent consulting engineers. The estimate is
supported by engineering, benchmarking, and pricing of key
consumables and costs derived from past production figures and
informal quotes from suppliers. The table below illustrates the
operating costs developed by discipline during the PFS. The project
FOB and CFR average cash cost per tonne of dry product over the LOM
is summarised below. Overall cash costs have been reduced primarily
due to the use of the slurry pipeline, which has reduced the plant
costs. Mining costs have increased due to the lower recovery
rate.
Table 4 FOB and CFR average cash cost per tonne of dry product
over the LOM
Cash
Cost Per Discipline
|
Revised PFS July 2024
|
Updated DR Grade PFS
Nov 2024
|
|
US$/DMT
|
US$/DMT
|
Mine
|
16.73
|
17.65
|
TSF
|
0.08
|
0.09
|
Beneficiation Plant, Pipeline,
Transfer & Rail Loading
|
10.94
|
10.50
|
Rail Freight
|
2.43
|
2.26
|
Port
|
1.55
|
1.52
|
G & A
|
1.77
|
1.74
|
FOB
Cash Costs
|
33.50
|
33.75
|
Marine Logistics
|
28.70
|
28.18
|
CFR
Cash Costs
|
62.20
|
61.93
|
DR-GRade Pricing
Mechanism
Steel contributes about 8% of global
carbon emissions, potentially reaching 12% by 2035. The industry is
shifting from traditional Blast Furnace and Basic Oxygen Furnace
("BF/BOF") methods to Direct Reduced Iron and Electric Arc Furnace
("DRI/EAF") processes to promote greener production. While BF/BOF
emits around 2.2 tons of CO2 per ton of steel, DRI/EAF
can reduce this to 0.3-1 per ton with hydrogen. Wood Mackenzie
projects EAF's share will grow from 28% to 38% by 2033, supported
by significant government funding to reduce emissions and increase
DRI/EAF capacity.
Due to its strong slag rejection
capabilities, the BF/BOF process efficiently processes a wide range
of iron ore grades. In contrast, the EAF is sensitive to
impurities, making low-grade iron ore with high impurity levels
problematic for yield and increasing electricity consumption and
slag production. Thus, the EAF requires iron ore with over 67%
purity and gangue elements like SiO2 and
Al2O3 below 2.5%, as shown in (Figure 4).
Figure 4 Summary of Iron Ore Content and
Gangue[3]
The drive to decarbonise industries
and the rise in DRI and EAF steel production are increasing demand
for DR-grade pellet feed, like that envisaged to be produced at
Amapá. CRU, a globally recognised consulting firm, estimates that
2050 demand for DR-grade pellet feed is expected to reach 310
million tonnes. In Europe, regulatory pressures to cut emissions
further drive demand. However, a significant supply shortfall of
about 100 million tonnes is anticipated, necessitating new DR-Grade
iron ore projects.
Iron ore is primarily traded on a
CFR or FOB basis. CFR transactions transfer ownership upon
unloading at the destination and include shipping costs. Due to the
lack of transparent indices for products like Amapá's, the industry
recommends using a comparable index with adjustments. The Platts
TSI IODEX 65% Fe CFR China is the closest benchmark for assessing
Amapá's DR-Grade product, with an additional premium for the
DR-grade material.
The 65% Fe Index for the updated PFS
was evaluated using various methods. Price forecasts available in
the public domain from Wood Mackenzie (US$92.50/DMT), CRU
(US$96.00/DMT), and Fastmarkets (US$120.00/DMT) were considered.
Historically, the 3-year trailing price averages US$152.20/DMT, and
the 5-year average is US$135.70/DMT1. Based on these
considerations, Amapá has used US$120.00/DMT, an increase of
US$1/DMT compared to the Project's previously published
PFS.
It is generally agreed that DR-grade
iron ores should command a premium over the 65% Fe Index. It is
anticipated that the Amapá DR-Grade, given its beneficial
properties, will qualify for this premium. One recognised industry
assessment technique for product premiums involves utilising a
Value in Use ("VIU") methodology. This approach entails determining
a premium or discount by considering Fe, SiO2, and
Al2O3 variations compared to the 65% Fe. Amapá has used the premium
attributed to the Kamistiatusset Iron Ore Property ("Kami") in
Newfoundland as a guide to determine and assist the Value in Use
(VIU) analysis. This analysis suggests a premium of about
US$24.8/DMT, though this may not fully account for green premiums
or carbon savings.
Table 5 Comparative product specification between Kami and
Amapá iron ore projects.
Product
|
TFe%
|
SiO2%
|
Al2O3%
|
P%
|
TiO2%
|
CaO%
|
MgO%
|
US$ Premium /
DMT
|
Amapá Concentrate
|
67.5
|
0.6
|
0.84
|
0.08
|
0.02
|
0.03
|
0.03
|
27.6
|
Kami Concentrate
|
67.6
|
2.1
|
0.25
|
0.02
|
0.03
|
0.3
|
0.35
|
24.8
|
Project Financial
Analysis
A PFS financial model was developed
to evaluate the project's economics. Summary results from the
financial model outputs, including financial analysis, are
presented in tables within this section. The financial model
considers 100% equity funding for the Project, although, in
reality, the financing of the Project will be a mix of debt and
equity. However, the existing obligations in terms of principal
repayment and current interest liabilities payable have been
included in the financial model.
The product change and increased
premium associated with DR-grade iron ore concentrate are primary
economic drivers to changes in the financial model compared to the
revised PFS published in July 2024.
Table 6 Summary of key financial information for the
Project.
Item
Over Life of Mine
|
Unit
|
RevisedPFS July 2024
|
Updated DR GradePFS
Nov 2024
|
Gross revenue
|
US$M
|
9,389
|
11,242
|
Freight (Maine Logistics)
|
US$M
|
(2,351)
|
(2,188)
|
Net
Revenue
|
US$M
|
7,038
|
9,054
|
Operating costs
|
US$M
|
(2,744)
|
(2,621)
|
Royalties and taxes (excluding
income tax)
|
US$M
|
(373)
|
(460)
|
EBITDA
|
US$M
|
3,922
|
5,973
|
EBIT
|
US$M
|
3,547
|
5,586
|
Net Taxes and Interest
|
US$M
|
(390)
|
(621)
|
Net
Operating Profit
|
US$M
|
2,144
|
4,964
|
Initial, Sustaining capital costs
& repayments
|
US$M
|
(645)
|
(656)
|
Free Cash Flow
|
US$M
|
2,672
|
4,696
|
Item
|
Unit
|
RevisedPFS June 2024
|
Updated DR Grade PFS
Nov 2024
|
Life of mine
|
Years
|
15
|
15
|
Discount rate
|
%
|
10
|
10
|
NPV10%
|
US$M
|
1,145
|
1,977
|
IRR
|
%
|
42
|
56
|
Project Payback
|
Years
|
4
|
3
|
Project Sensitivity
Analysis
A sensitivity analysis was performed
on key parameters within the financial model to assess the impact
of changes on the project's post-tax NPV (debt-free). To examine
the sensitivity of the Project base case NPV, each cost factor's
economic and operational conditions were independently varied
within a range of +/-25%, and discount rates were changed within
the 8%-15% range.
Project sensitivity analysis
demonstrates that the Amapá Project is most sensitive to a change
in iron ore concentrate price, followed by logistics costs (marine
shipment charges) and operating costs. It was least sensitive to
deviation in CAPEX (Figure
5)
Figure 5 Project Sensitivity Analysis
(NPV10%)
Cadence Ownership
As of the end of November 2024,
Cadence's total investment in the Amapá Project is approximately
US$14.3 million, and its equity stake in the project stands at
34.6%.
For further information
contact:
|
|
Cadence Minerals plc
|
+44
(0) 20 3582 6636
|
Andrew Suckling
|
|
Kiran Morzaria
|
|
|
|
Zeus
(NOMAD & Broker)
|
+44
(0) 20 3829 5000
|
James Joyce
|
|
Darshan Patel
|
|
Fortified Securities - Joint Broker
|
+44
(0) 20 3411 7773
|
Guy Wheatley
|
|
|
|
Brand Communications
|
+44
(0) 7976 431608
|
Public & Investor
Relations
|
|
Alan Green
|
|
Qualified Person
Kiran Morzaria B.Eng. (ACSM), MBA,
has reviewed and approved the information contained in this
announcement. Kiran holds a Bachelor of Engineering (Industrial
Geology) from the Camborne School of Mines and an MBA (Finance)
from CASS Business School.
Cautionary and
Forward-Looking Statements
Certain statements in this announcement are or may be
considered forward-looking. Forward-looking statements are
identified by their use of terms and phrases such as "believe",
"could", "should", "envisage", "estimate", "intend", "may", "plan",
"will", or the negative of those variations or
comparable expressions including references to assumptions. These
forward-looking statements are not based on historical facts but
rather on the Directors' current expectations and assumptions
regarding the company's future growth results of operations
performance, future capital, and other expenditures (including the amount, nature,
and sources of funding thereof) competitive advantages business
prospects and opportunities. Such forward-looking statements reflect
the Directors' current beliefs and assumptions and are based on
information currently available to the Directors. Many
factors could cause actual results to differ materially from the
results discussed in the forward-looking statements, including
risks associated with vulnerability to general economic and
business conditions, competition, environmental and other
regulatory changes actions by governmental authorities, the
availability of capital markets reliance on crucial personnel
uninsured and underinsured losses and other factors many of which
are beyond the control of the company. Although any forward-looking
statements contained in this announcement are based upon what the
Directors believe to be reasonable assumptions. The company cannot
assure investors that results will be consistent with such
forward-looking statements.