The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

Chevron Corp. (CVX) on Dec. 7 said its oil refinery in El Segundo, Calif., had resumed normal operations after a power interruption on Dec. 1 forced the shutdown of several processing units.

Syncrude on Dec. 6 said coker unit 8-1 shut on Nov. 22 for unplanned repairs at its Alberta, Canada oil-sands project was restarted at two-thirds of rated capacity.

Delek USA Holding's (DK) Lion Oil refinery in El Dorado, Arkansas experienced a fire at the platformer unit on Dec. 5, the company said on Dec. 7. The unit wasn't damaged and will be restarted later on Dec. 7.

Hovensa on Dec. 6 said scheduled fourth-quarter maintenance and upgrade projects have been completed at its oil refinery in St. Croix, part of the U.S. Virgin Islands. No units were shut down completely to conduct the work, the company said in early October, noting that there would be no impact on customers.

Nustar Energy LP's (NS) 13,800-barrel-a-day refinery in San Antonio, Texas, will resume normal operating rates by Dec. 7 following a small, brief fire on Nov. 30, company spokeswoman Mary Rose Brown said on Dec. 6.

Tesoro Corp. (TSO) on Dec. 5 said its Golden Eagle refinery in Martinez, Calif., was in the process of returning to normal operating rates following the Nov. 28 shutdown of an unspecified distillation unit.

 
   For more detailed information, search Dow Jones Newswires using 
the code N/REF. 
 
Operator   Refinery    Capacity   Description                   Restart 
                       (in 000s 
                       bbl/day) 
UNPLANNED 
 
CANADA 
 
Syncrude   Alberta     300.0  Coker unit restarted at two-       Dec 6 
                              thirds of rated capacity, the Co. 
s                             said on Dec 6. The unit was shut 
                              Nov. 22 for unplanned repair. 
 
CARIBBEAN 
 
EAST COAST 
 
Sunoco   Philadelphia  335.0  Girard Point Isomerization Unit    N/A 
         PA                   placed in circulation mode on 
                              Nov. 26 - filing. 
 
 
GULF COAST 
 
Delek    El Dorado      80.0  Platformer not damaged by Dec      Dec 7 
         AK                   5 fire; unit will restart Dec. 
                              7, the co. said. 
 
NuStar   San Antonio    13.8  Normal operating rate will re-     Dec 7 
         TX                   sume on Dec. 7 following small, 
                              brief fire on Nov. 30. 
 
 
Total    Port Arthur   174.0  Unit 890 shut on Nov. 29; No.      N/A 
         TX                   30 coker flare utilized. 
 
 
MIDWEST 
 
 
 
ROCKIES 
 
Sinclair  Sinclair      74.0  Refinery at reduced rates fol- 
          WY                  lowing fires at CDU on Sept. 3 
                              and Sept. 4. Repairs underway. 
                              Plant continues to operate at re- 
                              duced rates, sources said Nov. 11. 
 
WEST COAST 
 
Chevron  El Segundo    273.0  Refinery has resumed normal op-    Dec 7 
         CA                   erations following Dec 1 power 
                              snag the co. said on Dec 7. 
 
Tesoro   Martinez, CA  166.0  Plant returning to normal opera-   Dec 5 
                              tions on Dec 5 following Nov 28 
                              distillation unit shutdown. 
 
 
PLANNED 
 
CANADA 
 
CARIBBEAN 
 
Hovensa  St. Croix     350.0  Planned maintenance and capital    Dec 6 
                              project concluded, the co. 
                              said on Dec 6. 
 
EAST COAST 
 
Conoco   Trainer, PA   185.0  Crude processing halted; 
                              operations winding down, 
                              the company said on Sept. 30. 
                              The refinery will be 
                              shuttered in six months if 
                              not sold. 
 
Sunoco   Philadelphia  335.0  Refineries up for sale on          July 
         Marcus Hook   190.0  Sept. 6; Marcus Hook shut        2012 
                              Dec. 1 ahead of schedule 
                              due to poor refining econo- 
                              mics. Phila. to shut in July. 
 
GULF COAST 
 
Conoco   Belle Chasse 247.0   Refinery up for sale a 
Phillips LA                   Nov. 29 Bloomberg News 
                              report said. 
 
CVR      Wynnewood     54.0   Maintenance turnaround for up      4Q 
Energy   OK                   to 40 days starting in 3Q 2013.    2012 
 
Holly    Artesia, NM  100.0   Crude runs will be reduced by      Early 
Frontier                      50% during 30 days of major turn-  2012 
                              maintenance in early 2012, the Co. 
                              said on Aug. 5. 
 
Motiva   Port Arthur   285.0  Expansion project to increase      1Q 
         TX                   throughput capacity by 325,000     2012 
                              b/d, to 610,000-b/d, slowed. 
                              Completion now seen 1Q 
                              2012, from 2010. 
 
Valero   McKee    TX    170.0 Vacuum unit turnaround planned for 
                              first half of 2012, company said. 
 
                              Expansion project announced 
                              March 2011 to increase crude oil 
                              throughput by 25,000 b/d to 
                              195,000 b/d. 
 
Valero   Houston,TX    88.0   Seven weeks of FCCU maintnance    end-March 
                              starting in Feb. 2012 the Co. 
                              said on Nov. 1, 2011. 
 
Valero   Norco, LA     185.0  Ten weeks of work planned for      mid-April 
                              the crude and coker units start-   2012 
                              ing Feb. 2012, co said on Nov. 1, 
                              2011. 
 
Valero   Norco, LA     185.0  Hydrocracker project will pro-     2013 
                              ceed and be completed in late 
                              2013, the co. said on 7/27/10. 
 
                              Upgrade project to build           2012 
                              a new diesel hydrotreater 
                              unit moved from 2010 to 
                              4Q 2012. 
 
Valero   Port Arthur   325.0  Hydrocracker project will pro-     2012 
         TX                   ceed and be completed in late 
                              2012. 
 
MIDWEST 
 
CVR      Coffeyville   115.7  Second phase of turnaround work    Q1 
         KS                   planned for Feb. 2012; first       2012 
                              phase concluded in Nov. 2011. 
 
CVR      Wynnewood      54.0  30-40 days maintenance planned     Q3 
         OK                   in 3rd Q 2013, the co. said on     2013 
                              Nov. 3, 2011. 
 
Holly    Tulsa, OK     125.0  The entire refinery will be shut   Late 
Frontier                      while West Plant section under-    2012 
                              goes major turnaround maintenance 
                              in late 2012, the Co. said on 
                              Aug. 5, 2011. 
 
Husky    Lima, OH      160.0  15-days of maintenance planned at 
Energy                        at aromatics unit in the fall 
                              of 2012. 
 
Husky    Toledo, OH    140.0  Two turnarounds planned in 4Q      4thQ 
Energy                        2011; one for two weeks, one for   2011 
                              25 days. The plant will run at 
                              90% of capacity during work, 
                              the co. said on Nov. 3, 2011. 
 
Marathon Canton, OH     78.0  Chemical release reported on       N/A 
                              Nov. 26 due to unit shutdown 
                              for planned maintenance, the 
                              co. said on Nov. 27. 
 
Tesoro   Mandan, ND     58.0  Total crude-oil processing capa-   2nd Q 
                              city to increase by 17% to 68,000   2012 
                              b/d by 2nd quarter 2012. 
 
Valero   Memphis, TN   180.0  Five weeks of maintenance on       early-April 
                              crude unit starting in March.       2012 
                              2012, co. said on Nov. 1, 2011. 
 
WEST COAST 
 
BP       Carson, CA    265.0  Planned flaring will occur be-     Dec 27 
                              tween Nov 27 and Dec 27, a 
                              filing to regulators said. 
                              Flaring associated with planned 
                              maintenance, a source said. 
 
 
Chevron  El Segundo    280.0  Planned flaring event will be- 
         CA                   on Nov. 29 through Dec 1. Could 
                              be associated with FCCU restart. 
 
                              4 weeks of maintenance at FCCU     Early 
                              beginning late Oct. seen ending    Dec 
                              in December, sources said on Nov. 
                              18. 
 
 
Tesoro  West Coast     N/A    Q4 2011 maintenance at West 
                              Coast refineries delayed until 
                              2012. Further details not pro 
                              vided. 
 
Valero   Wilmington,   78.0   Four weeks of maintenance for      Feb. 2012 
         CA                   crude and coker units starting 
                              in January 2012, Co. said on 
                              Nov. 1, 2011. 
 
CVR Energy (NYSE:CVI)
Graphique Historique de l'Action
De Juin 2024 à Juil 2024 Plus de graphiques de la Bourse CVR Energy
CVR Energy (NYSE:CVI)
Graphique Historique de l'Action
De Juil 2023 à Juil 2024 Plus de graphiques de la Bourse CVR Energy