ASX
RELEASE
28 January 2025
Activities report for the December quarter
2024
Aura Energy Limited (ASX:AEE, AIM:AURA) (Aura or
the Company) is pleased to provide its quarterly activities report
for the period ended 31 December 2024 to accompany the Company's
Appendix 5B.
Aura has continued to make significant progress
on the development of the Company's flagship Tiris Uranium Project
(Tiris) in Mauritania, West Africa, as its progresses towards a
Final Investment Decision (FID) in early 2025 while advancing the
licensing of the Häggån Polymetallic Project (Häggån) in
Sweden.
Important milestones achieved during the quarter
include:
1. The Tiris
Uranium Project's Ore Reserve estimate increased by 49% to 33.6Mlb
of U3O8[1]
§ The updated Ore
Reserve estimate has been completed based on the June 2024 Mineral
Resource[2], as well as pit optimisation and
mine schedules that were reported as part of
the September 2024 Production Target update[3]
§ High Mineral Resource to Ore Reserve
conversion driven by low cost, shallow,
free-digging mineralisation that is upgraded 600% to 800%
through a simple wet screening beneficiation process prior to
further processing
§ Ongoing Ore Reserve growth
anticipated with future drilling and enhanced
Mineral Resource confidence. The 2024 drilling campaign achieved
Mineral Resources definition at an exceptionally low cost of
US$0.14/lb U3O8
2. Alternative
production targets provide growth opportunities for
Aura[4]
§ Aura undertook
an assessment of the opportunities for future capacity expansion at
Tiris utilising inputs from the September 2024 Production Target
Update3 by expanding the production capacity commencing
in the third year of operations from the initial development plan
production rate of ~2Mlbspa U3O8 per
year
§ The
~3Mlbspa
U3O8 production rate (6.25Mtpa mining
rate) case returned the highest NPV and
improved economics with results including:
§
NPV8 of
approximately US$544M (A$836M) an increase of 9% on the base
case3
§ IRR of ~45% post tax and payback in the
order of 2.5 years
§ High margin average annual post-tax cash
flows over the life of mine of ~US$86M, an increase of 37% and
average ~US$116M over the first five years of
operations
§ Additional development capital fundable
from cashflow
§ Importantly, the
analysis was restricted to only 27% of the total defined Tiris East
Inferred Mineral Resources. Further work aimed at increasing the
resource confidence and additional exploration success will have a
materially positive impact on this analysis
3.
Activities and milestones at Tiris
Numerous activities have commenced or have been
completed during the quarter supporting Aura's objective of
finalising a mine development decision by Q1
CY2025, including:
§ Project development funding process well
advanced with both debt and strategic equity
engagement well advanced including site visits and commencing due
diligence. Independent Technical Experts (ITE) RPM Global have also
completed site visits with due diligence reporting expected to be
completed during Q1 CY2025
§ Water drilling and
pump testing has defined very significant quantities of
water in the Taoudeni Basin and C22 borefield
with aquifer modelling underway
§ John Wood Group
plc (Wood), a highly
credentialled engineering contractor has commenced a basic engineering and early
works definition program in preparation for the
FID
§ Agreement with
Wood
also for the Engineering, Procurement and Construction
Management (EPCM) of the Tiris Uranium Project
development
§ Project development
team strengthened with the appointment of Mr Mohamed El Moctar Mohamed El Hacene
to the newly established role of Country Manager Mauritania. Mr.
Hacene is a highly qualified Mauritanian national with extensive
experience in mining and international affairs. Mr. Hacene previously served as Mauritania's
Minister of Petroleum and Mines from 2007 to 2008, during
which time uranium was first discovered at Tiris by Aura
4.
Swedish Government inquiry recommends lifting uranium mining
ban
In announcing the results of its inquiry into
uranium mining on 20 December 2024, the Government of Sweden has
taken an important step towards lifting the ban on uranium mining
which has been in place since 2018.
The Government inquiry has recommended that
uranium be regulated as a concession mineral within the Minerals
Act. This would allow deposits containing economic quantities of
uranium to be exploited like other natural resources in the
country.
This aligns Sweden's mining legislation with its
energy policy that calls for a substantial expansion of nuclear
power. Sweden already generates one third of the country's
electricity from nuclear power but currently relies completely on
imported raw material for nuclear fuel.
The next step in the legislative process is for
the results of the inquiry to be referred for wider consultation
(of which Aura has been included) before it is converted into a
legislative proposal and brought to Parliament for consideration in
early 2026.
The assessment of the processing concession for
Aura's Häggån K1 by the Swedish Mining Inspectorate has
commenced.
5.
Balance sheet
On 17 December 2024, Aura announced a A$9
million (gross) private placement to professional and sophisticated
investors, including the introduction of a significant new
shareholder, Sachem Cove Partners LLC (Sachem Cove), a leading
international uranium investment group, who committed A$6.5 million
to the placement and now holds approximately 5.1% of Aura Energy's
issued share capital.
Net funds will be used to advance development of
the low-cost, high-value Tiris Uranium Project including funding of
an early works program.
As of 31 December 2024, the Company had cash of
A$20.6 million.
Aura Energy Managing Director and Chief Executive Officer,
Andrew Grove said:
"The significant upgrade to Tiris' Ore
Reserves, increased by 49% to 33.6Mlb of
U3O8, on the back of the revised Production
Target and the option analysis clearly demonstrates the significant
value, robust and scalable opportunity at Tiris.
2025 will be a pivotal year for Aura and Tiris.
The work completed during the quarter and throughout 2024 included
significantly increasing the scale, size and value at Tiris,
derisking the Project including water supply, establishing the team
to execute on the development and advancing the development funding
provides a solid platform for the commencement of development at
Tiris during 2025.
We appreciate the continued support from our
existing shareholders and welcome Sachem Cove as a significant new
shareholder in the recent A$9 million raise that further supports
the continued advancement of Tiris and gives us the capacity to
commence early works, ensuring the development timeline of late
2026 early 2027 is maintained.
We look forward to keeping shareholders updated
as we progress through 2025."
Tiris uranium project,
Mauritania
The Tiris Uranium Project located in Mauritania
is a potential near-term, low-cost, long-life uranium mine
producing 2Mlbspa U3O8 over the currently
defined 25-year mine life[5]
with production expected to commence in
2026/27.
During the December quarter, important
activities continued to progress Tiris towards FID in early 2025
and, ultimately, the development of Mauritania's first uranium
mine, including:
§ Tiris Uranium
Project's Ore Reserves increased by 49% to 33.6Mlb of
U3O8[6]
§ Alternative
production target analysis demonstrated growth opportunities at
Tiris5
§ Water drilling
completed with significant water identified
§ Project funding
activities well advanced
§ Wood commenced basic
engineering and selected for EPCM contractor
§ Country manager
commenced in Mauritania
§ Numerous other
pre-development activities progressed
Tiris uranium project's Ore
Reserve estimate increased by 49% to 33.6Mlb of
U3O86
The Tiris Uranium Project Ore Reserve estimate
increased 49% to 62.8Mt at 243ppm U3O8,
containing an estimated 33.6Mlb U3O8
(previously 40.4Mt at 254ppm U3O8, containing
an estimated 22.6Mlb U3O8)6. The
updated Ore Reserve estimate was completed on the June 2024 Mineral
Resource Estimate (MRE), which included growth of Measured and
Indicated Mineral Resources of 35% to 91.3Mlb
U3O8[7]. The Ore
Reserve estimate update has been completed based on pit
optimisation and mine schedules reported as part of the September
2024 Production Target update5.
The key mining areas and process infrastructure
remain unchanged from those reported within the September 2024
Production Target Update. The upgrade has seen incremental growth
in the Ore Reserve estimate in the Lazare North, Lazare South, Sadi
and Hippolyte resource areas, mainly due to increased
classification of resources as Measured and Indicated in the June
2024 MRE update.
The updated Ore Reserve estimate, with
comparison to the previously reported Ore Reserve estimate has been
summarised in Table 1. The Ore
Reserves are estimated from their respective Mineral Resources
after consideration of the level of confidence in the Mineral
Resource and taking account of material and relevant modifying
factors. No Inferred Mineral Resources have been included in the
Ore Reserve.
Deposit
|
|
Proved Ore
Reserve
|
Probable Ore
Reserve
|
Total Ore
Reserve
|
Tonnes
(Mt)
|
U3O8
(ppm)
|
U3O8
(Mlb)
|
Tonnes
(Mt)
|
U3O8
(ppm)
|
U3O8
(Mlb)
|
Tonnes
(Mt)
|
U3O8
(ppm)
|
U3O8
(Mlb)
|
Lazare
North
|
Dec-24
|
3.6
|
297
|
2.4
|
8.3
|
262
|
4.8
|
12.0
|
273
|
7.2
|
|
Mar-23
|
0.9
|
298
|
0.6
|
8.0
|
251
|
4.4
|
8.9
|
256
|
5.0
|
|
Diff
|
2.7
|
-1
|
1.8
|
0.4
|
11
|
0.4
|
3.1
|
17
|
2.2
|
|
%
Diff
|
286%
|
0%
|
287%
|
5%
|
4%
|
9%
|
35%
|
7%
|
44%
|
Lazare
South
|
Dec-24
|
7.5
|
245
|
4.1
|
4.8
|
243
|
2.5
|
12.3
|
244
|
6.6
|
|
Mar-23
|
6.5
|
264
|
3.8
|
2.7
|
291
|
1.7
|
9.2
|
271
|
5.5
|
|
Diff
|
1.0
|
-19
|
0.3
|
2.1
|
-48
|
0.8
|
3.1
|
-27
|
1.1
|
|
%
Diff
|
15%
|
-7%
|
8%
|
80%
|
-16%
|
47%
|
34%
|
-10%
|
20%
|
Hippolyte
|
Dec-24
|
7.6
|
274
|
4.6
|
7.5
|
266
|
4.4
|
15.0
|
270
|
8.9
|
|
Mar-23
|
5.7
|
270
|
3.4
|
7.1
|
231
|
3.2
|
12.8
|
248
|
7.0
|
|
Diff
|
1.9
|
4
|
1.2
|
0.4
|
35
|
0.8
|
2.2
|
22
|
1.9
|
|
%
Diff
|
32%
|
1%
|
36%
|
5%
|
15%
|
22%
|
17%
|
9%
|
27%
|
Sadi
|
Dec-24
|
9.1
|
213
|
4.3
|
14.5
|
207
|
6.6
|
23.6
|
209
|
10.9
|
|
Mar-23
|
6.1
|
232
|
3.1
|
3.3
|
261
|
1.9
|
9.5
|
242
|
5.1
|
|
Diff
|
3.0
|
-19
|
1.2
|
11.1
|
-54
|
4.7
|
14.1
|
-33
|
5.9
|
|
%
Diff
|
49%
|
-8%
|
37%
|
336%
|
-21%
|
246%
|
149%
|
-14%
|
116%
|
Total
|
Dec-24
|
27.8
|
249
|
15.3
|
35.0
|
238
|
18.4
|
62.8
|
243
|
33.6
|
|
Mar-23
|
19.3
|
257
|
11.0
|
21.0
|
251
|
11.6
|
40.4
|
254
|
22.6
|
|
Diff
|
8.5
|
-8
|
4.34
|
14.0
|
-13
|
6.
8
|
22.5
|
-11
|
11.0
|
|
%
Diff
|
44%
|
-3%
|
40%
|
66%
|
-5%
|
58%
|
56%
|
-4%
|
49%
|
Table 1 - Updated Ore Reserve Estimate
showing key changes at deposits
Notes:
Ore Reserves are a subset of Mineral
Resources.
Ore Reserves conform with and use
the JORC Code 2012 definitions.
Ore Reserves are calculated using a
uranium price of US$80/lb.
Ore Reserves are calculated using a
cut-off grade of 100ppm U3O8.
Tonnages are reported including
mining dilution.
All figures are rounded to reflect
appropriate levels of confidence which may result in apparent
errors of summation.
Alternative production
targets provide growth opportunities for
Tiris[8]
Aura undertook an assessment of the
opportunities for future capacity expansion at the Tiris Uranium
Project in Mauritania utilising inputs from the September 2024
Production Target Update[9]
and the recently expanded 91.3Mlbs U3O8
Mineral Resource[10].
The Production Target Update9 presented an
increase in mine life from 17 to 25 years. The alternative
production targets (Production Targets) are based on an analysis of
opportunities to accelerate production from year three of operation
onwards, without any other material changes to the underlying
assumptions or levels of confidence.
Options have been analysed to expand the
production capacity commencing in the third year of operations from
the initial development plan of 4.1Mtpa mine rate to produce
~2Mlbspa U3O8 per year by accelerating the
mining rate and increasing production capacity. Production
scenarios have been assessed for mining rates of 6.25Mtpa,
producing ~3Mlbspa U3O8 and 8.2Mtpa,
producing ~4Mlbspa U3O8. The options
presented will not replace the Base Case presented in the September
2024 Production Target Update9, rather they demonstrate
optionality for the Tiris Uranium Project once in
operation.
Key
points:
§ The ~3Mlbspa U3O8
production rate (6.25Mtpa mining rate) case
(Option 1) returned the highest NPV and improved economics with
results including:
§
NPV8% of
approximately US$544M (A$836M) an increase of 9% on the base
case9
§ IRR of ~45% post tax and payback in the
order of 2.5 years
§ High margin average annual post-tax cash
flows over the life of mine of ~US$86M, an increase of 37% and
average ~US$116M over the first five years of
operations
§ Additional development capital fundable
from cashflow
§ Analysis used only
27% (21Mt) of the total defined Tiris East Inferred Mineral
Resources (79Mt at 210ppm U3O8 for 36.7Mlbs
U3O8)[11], increasing the confidence that any future
increases in Inferred Mineral Resources and exploration success
will have a materially positive impact on this analysis
Information on the future capacity expansion
options is summarised in Table 2 below.
|
Units
|
4.1Mtpa mining (~2Mlbspa
U3O8)
Sept 24[12]
|
Option 1
6.25Mtpa mining
(~3Mlbspa
U3O8)
|
Option 2
8.2Mtpa mining
(~4Mlbspa U3O8)
|
Uranium Price
|
US$/lb
U3O8
|
$80
|
$80
|
$80
|
Valuations and
Returns
|
Post-tax NPV8
|
US$M
|
499
|
544
|
521
|
Post-tax IRR
|
%
|
39%
|
45%
|
41%
|
Payback period
|
Years
|
2.25
|
2.5
|
3.25
|
Cashflow
Summary
|
Initial Life of Mine
|
Years
|
25
|
18
|
16
|
LOM
Production
|
Mlbspa
U3O8
|
43.5
|
37.9
|
37.9
|
Annual Production
|
Mlbspa
U3O8
|
1.8
|
2.3
|
2.9
|
Gross Revenue (LOM)
|
US$M
|
3,467
|
2,898
|
2,898
|
Free Cashflow pre-tax (LOM)
|
US$M
|
1,922
|
1,817
|
1,813
|
Free Cashflow post tax (LOM)
|
US$M
|
1,509
|
1,457
|
1,484
|
Unit Operating
Costs
|
All
in Cost
|
US$/lb
U3O8
|
41.0
|
40.2
|
43.7
|
All-in Sustaining Costs
|
US$/lb
U3O8
|
35.7
|
31.8
|
31.9
|
C1
Cash Cost
|
US$/lb
U3O8
|
31.4
|
27.7
|
27.9
|
Operating Margin
|
US$/lb
U3O8
|
44.3
|
48.8
|
48.1
|
Operating Margin
|
%
|
55%
|
60%
|
60%
|
Capital
Cost
|
Development Capital
|
US$M
|
230
|
317
|
445
|
Table 2 - Summary of the future capacity
expansion options results with comparison of the September 2024
Production Target update
The assessment of the capacity expansion
opportunities identifies revenue can be moved forward by
accelerating the mining schedule with the following observations
for the cases analysed:
§ The open pit mining is a simple, low-risk,
shallow, flexible, free digging operation without the need
for crushing and grinding
§ Initial development
plan provides for a high margin long life business. Future
expansion plans can further enhance the Project value and can be
potentially funded from cash flows
§ Operating costs, AISC,
decrease in the expansion cases analysed and are largely due to
spreading the fixed costs over a larger annual production
base
§ The analysis only used
approximately 27% of Inferred Mineral Resources currently defined
in the Tiris Uranium Project area amounting in aggregate to 21Mt of
the total 79Mt at 210ppm U3O8 for 36.7Mlbs
U3O811. Drilling to increase the
confidence of the Inferred Resources is anticipated to have a
materially positive impact on this economic analysis
§ The significant
exploration potential at Tiris also presents an opportunity to add
significant additional value to the future operations and support a
future expansion of the operations
§ The construction and
operation of the Tiris Uranium Project is anticipated to deliver
significant and ongoing benefits to Aura shareholders and the
people of Mauritania
Water drilling update
Hydrogeological drilling and long-term pump
testing of the Taoudeni Basin (~100km south of the Tiris uranium
project) and the C22 borefield (~30km from the Tiris uranium
project), has been completed.
The program included 26 holes for 2,755 metres
in the Taoudeni Basin, an additional 17 holes for 1,763 metres at
the C22 borefield and six holes for 700m confirming groundwater
conditions at the Project site. Results have been highly successful
with summary results and initial observations from Knight Piésold
detailed below.
Taoudeni
Basin: Water reported in 61% of holes with
significant water flows (up to 55m3 per hour in air lift
testing). The water column averaged 14m thick with a flow rate of
20m3 per hour. The exploration drill and test programme
undertaken at the Taoudeni Basin region yielded good to very good
quality water, with several high yielding targets intersected.
Additionally, the bores installed in this area are spaced far
apart, therefore increasing long-term potential use, and scope for
expanding this target region as a borefield.
There is significant scope for additional
exploration and expansion of the groundwater resource in this
region, particularly around high yielding zones as well as along
regional scale fault zones for long term use, with the targeted
aquifer systems extending significantly to the northeast and
southwest of the exploration programme area. Due to this scale
(including the same lithologies and most likely, hydrogeological
conditions), there is potential for several additional borefields
in the Taoudeni Basin with similar prospectivity to that of the
2024 program.
The potential for establishing future Project
scale borefields in the Taoudeni, around the high yielding zones as
well as along large fault zoned for long term use, is
significant.
C22
borefield: Drilling was completed in 2021 to
define an initial water resource[13].
Drilling in this program to extend the aquifer returned 41% of
holes that were productive, with water flows up to 40m3
per hour in air lift testing. The existing groundwater resource at
the C22 borefield area has been expanded, the initial results of
which show significant potential for success. There exists a large
scope for further exploration at prospective targets in the area
with similar hydrogeological characteristics such as intersecting
large scale geological structures and areas of deeper weathering,
both of which have been shown in the 2024 investigation to be
highly prospective for groundwater supply.
Knight Piésold, internationally recognised
hydrological consultants, have been supporting the program and will
undertake aquifer modelling early in Q1 CY2025.
Water drilling has been very successful at both
locations with air lift testing defining a cumulative
344m3/hr of water flow rates. The Project's water demand
has been estimated at between 120m3/hr to
160m3/hr.
In addition, six holes were drilled under the
proposed plant site intersecting no water. With no water table in
the plant area this significantly limits the possibility of
potential contamination from the processing activities.
Tiris Project funding update
In June 2024, Aura appointed Orimco to arrange debt
funding for Tiris. Orimco has vast experience supporting projects
throughout Africa and at the same time, Macquarie Capital was
appointed in Australia to identify and engage with strategic
investors for a potential equity investment in Tiris and/or
Aura.
We have received confidential, non-binding proposals
from a number of investors and debt providers and other parties
continue to contact us expressing willingness to co-invest.
Both funding processes are ongoing, with
advisors actively advancing discussions with multiple parties
interested in debt financing and strategic investment
opportunities.
At this time, discussions in respect of the proposals
have not sufficiently progressed to be announced to the market and
there is no binding agreement in place with respect to any funding
arrangement. Aura confirms that no assurance can be given that the
ongoing confidential discussions will result in any binding
agreement between the parties, and Aura will continue to maintain
its policy of keeping the market fully informed with its continuous
disclosure obligations.
The Independent Technical Engineers, RPM Global, are
well advanced in their due diligence analysis on all aspects of the
project on behalf of the lenders and investors which included
undertaking site visits to Tiris in late October 2024. Additional
site visits have been scheduled for January and February 2025.
Other Tiris activities
Key Project development activities during the
quarter included:
§ Wood, a highly
credentialled engineering contractor has commenced a basic
engineering and early works definition program
§ Agreement with Wood also
for the subsequent Engineering, Procurement and Construction
Management (EPCM) of the Tiris Uranium Project
development
§ ECG Engineering has been
appointed and commenced work on defining the optimal power
generation solution for Tiris
§ Team strengthened with
the appointment of Mr Mohamed El Moctar Mohamed El
Hacene to the newly established role of Country Manager Mauritania.
Mr. Hacene is a highly qualified Mauritanian national with
extensive experience in mining and international affairs. Mr.
Hacene previously served as Mauritania's Minister of Petroleum and
Mines from 2007 to 2008, during which time uranium was first
discovered at Tiris by Aura
§ Continued strong engagement
with Mauritanian government
§ Continued engagement
with multiple nuclear utilities with respect to securing offtake
contracts for the future Tiris uranium production
Häggån Project update
The Häggån Polymetallic Project, located in the
municipality of Berg in the county of Jämtland, hosts a globally
significant two billion tonne polymetallic Mineral
Resource[14] which also
includes an Inferred uranium Mineral Resources of 800Mlbs of
U3O8, 2.35 billion tonnes at a grade of
155ppm U3O8 (reported at a cut-off grade of
100ppm U3O8)[15]. The primary metals
and minerals are vanadium, sulphate of potash and uranium, with
nickel, molybdenum and zinc also present.
The 2023 Häggån Scoping
Study[16] results reported
that the inclusion of uranium by-product credits in
project economic estimates contributed approximately
13% of overall project revenues and increased the Project
NPV8 by 37% at a uranium price of US$65/lb
U3O8, from the Project NPV8 range
excluding uranium by-product credits, of between US$456 million to
US$1,307 million.
There is a low level
of geological confidence associated with the Inferred uranium
Mineral Resources and
there is no certainty that further exploration work will result in
the determination of Indicated Mineral Resources or that the
production target itself will be realised.
On the 20 December 2024 the Swedish government
announced the results of its inquiry into uranium mining. The
Government inquiry into uranium mining has recommended that the
current uranium mining ban be lifted and that uranium be regulated
as a concession mineral within the Minerals Act. This would allow
deposits containing economic quantities of uranium to be exploited
like other natural resources in the country.
This aligns Sweden's mining legislation with its
energy policy that calls for a substantial expansion of nuclear
power. Sweden already generates one third of the country's
electricity from nuclear power but currently relies completely on
imported raw material for nuclear fuel.
Extracting uranium from its substantial
endowment of geology which hosts uranium as a by-product would
greatly increase Sweden's energy security. The Häggån deposit alone
could fuel Sweden's existing nuclear reactor fleet for over three
centuries. It would also bring investment, create jobs and generate
exports for the economy.
All parties in the governing coalition have
expressed their support to overturn the current uranium mining ban.
The next step in the legislative process is for the results of the
inquiry to be referred for wider consultation before it is
converted into a legislative proposal and brought to Parliament for
consideration. The governing coalition holds a majority of the
seats in Parliament.
Following the inquiry and the referral process,
the Government can proceed with a legislative proposal to
Parliament to enact the proposed changes. The proposed date for
legislative changes to come into effect by 1 January
2026.
Aura is included in the list of consultation
parties for the uranium inquiry.
The Swedish Mining Inspectorate have commenced
evaluation of the processing concession ('Exploitation Permit
Application') for Häggån K no 1 submitted in August
2024[17].
Corporate activities:
Private placement
On 17 December 2024, the Company announced a
placement to professional and sophisticated investors to raise
approximately A$9 million before costs through the issue of
64,285,714 fully paid ordinary shares at A$0.14 per share. The
placement was completed on the 24 December 2024.
Sachem Cove Partners LLC (Sachem Cove), a
leading international uranium investment group, committed A$6.5
million to the placement and now holds approximately 5.1% of Aura
Energy's issued stock.
The placement was also well supported by
existing shareholders and attracted several new high-quality
investors.
Net funds will be used to advance development of
the low-cost, high-value Tiris Uranium Project, including an early
works program beyond the FID.
Cash
and cash forecast
The Company's cash position as of 31 December
2024 was A$20.6 million. The Company's major cashflow movements for
the quarter included:
§ Investments in the
Company's exploration and evaluation assets of A$2.6
million
§ Proceeds from
placement A$8.4 million
§ Administration and
corporate costs of A$0.9 million
§ Staff costs of A$0.4
million
The forecasted net operating cashflow and
investment in the Company's exploration and evaluation assets for
the coming quarter is A$3.8 million. With a closing cash balance of
A$20.6 million, the company has enough cash for 5.4
quarters.
March 2025 quarter planned activities
At Tiris, the next steps in progressing towards
the construction and development of the Project during the March
quarter include:
§ Project development
funding
§ Offtake contract
negotiations
§ Complete reservoir
modelling to confirm water infrastructure sufficient to support
future operations
§ Finalise EPMC
contract with Wood to develop Tiris
§ Continue basic
engineering, project execution and early works development
planning
§ Commence early works
programs
§ Geometallurgy,
engineering and design work to support development
activities
§ Baseline
environmental and radiation monitoring
§ Implementation of ESG
framework
At Häggån the planned activities
include:
§ Work to support the
exploitation permit application
§ Aura's submission to
the uranium mining inquiry
December 2024 quarter ASX announcements
This Quarterly Activities Report contains
information extracted from ASX market announcements reported in
accordance with the 2012 edition of the "Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore
Reserves" (2012 JORC Code). Further details (including 2012 JORC
Code reporting tables where applicable) of 2012 JORC Code related
disclosures referred to in this Quarterly Activities Report can be
found in the relevant announcements lodged on the ASX and in the
section titled "ASX JORC Related Disclosures" set out in this
report. Following is a list of all market sensitive announcements
lodged by the Company during the December Quarter:
§ Appointment of
Country Manager -
Mauritania
11 November 2024
§ Results of Meeting
and Chair's Address to
Shareholders
27 November 2024
§ Tiris Uranium Project
Alternative Production
Targets
13 December 2024
§Substantial increase
in Tiris Uranium Project Ore Reserves
16 December 2024
§ A$9 million placement
to accelerate Tiris Uranium Project
17 December 2024
§ Amendment - Tiris Ore
Reserve Update
20 December 2024
§ Swedish government
recommendation - lifting uranium ban 23
December 2024
These announcements are available for viewing on
the Company's website auraenergy.com.au. Aura confirms that it is
not aware of any new information or data that materially affects
the information, or key assumptions, included in any of these
original ASX announcements.
Tenement Summary
The Company holds the following interest in
mining tenements, farm-in and farm-out agreements at the end of the
quarter:
Tenement No.
|
Name
|
Grant Date
|
Expiry
|
Km2
|
Holder
|
Equity
|
|
|
|
|
|
|
|
Mauritania
|
2491C4
|
Ain Sder
|
8/02/2019
|
7/02/2049
|
207
|
Tiris Ressources SA
|
85%
|
2492C4
|
Oued El Foule
|
8/02/2019
|
7/02/2049
|
190
|
Tiris Ressources SA
|
85%
|
2490C4
(formerly 561)
|
Oum Ferkik
|
19/05/2017
|
Pending
approval of application for Exploitation License
|
60
|
Aura Energy Limited
|
100%
|
2365B4
|
Oued El Foule Sud
|
04/12/2023
|
03/08/2026
|
166
|
Aura Energy Limited
|
100%
|
2457B2
|
Hadeibet Belaa
|
08/12/2023
|
07/08/2026
|
41
|
Tiris International Mining
Co.
|
100%
|
2458B2
|
Touerig Taet
|
08/12/2023
|
07/8/2026
|
134
|
Tiris International Mining
Co.
|
100%
|
Sweden
|
2007-243
|
Häggån nr 1
|
28/08/2007
|
Pending
determination of exploitation permit application
|
18
|
Vanadis Battery Metals AB
|
100%
|
2016:9
|
Möckelåsen nr 1
|
21/01/2016
|
21/01/202
|
18
|
Vanadis Battery Metals AB
|
100%
|
2016:7
|
Skallböle nr 1
|
20/01/2016
|
20/01/2028
|
8
|
Vanadis Battery Metals AB
|
100%
|
Table 4 - Tenement
summary
Farm-in agreement with Nomads Mining Company
sarl, Mauritania, Aura, through subsidiary Archean Greenstone Gold
has earned a 70% interest in Nomads 100%-owned exploration permit
in Mauritania (refer to ASX announcement 11 June 2019).
ENDS
The Board of Aura Energy Ltd has approved this
announcement.
This Announcement contains inside information
for the purposes of the UK version of the market abuse regulation
(EU No. 596/2014) as it forms part of United Kingdom domestic law
by virtue of the European Union (Withdrawal) Act 2018 (UK
MAR).
For
further information, please contact:
Andrew
Grove
Managing Director and CEO
Aura Energy Limited
agrove@auraee.com
+61 414 011 383
|
SP Angel
Corporate Finance LLP
AIM Nominated Adviser
David Hignell
Adam Cowl
Devik Mehta
+44 203 470 0470
|
Tamesis
Partners LLP
AIM Broker
Charlie Bendon
Richard Greenfield
+44 203 882 2868
|
|
About Aura Energy (ASX: AEE, AIM:
AURA)
Aura Energy is an Australian-based mineral
company with major uranium and polymetallic projects in Africa and
Europe.
The Company is focused on developing a uranium
mine at the Tiris Uranium Project, a major greenfield uranium
discovery in Mauritania. The 2024 FEED Study[18] and Production Target
Update[19]
demonstrates Tiris to be a near-term low-cost uranium mine
producing 2Mlbspa U3O8 over a 25-year mine
life with excellent economics and optionality to expand and to
accommodate future exploration success.
Aura plans to transition from a uranium
explorer to a uranium producer to capitalise on the rapidly growing
demand for nuclear power as the world shifts towards a decarbonised
energy sector.
Beyond the Tiris Project, Aura owns 100% of the
Häggån Project in Sweden. Häggån contains a global-scale 2.0Bt
vanadium, sulphate of potash (SOP)[20] and uranium[21] resource. Utilising only 3% of the
resource, a 2023 Scoping Study[22] outlined a 17-year mine life based on
a 3.6Mtpa production rate.
Disclaimer Regarding Forward-Looking
Statements
This ASX announcement (Announcement) contains
various forward-looking statements. All statements other than
statements of historical fact are forward-looking statements.
Forward-looking statements are inherently subject to uncertainties
in that they may be affected by a variety of known and unknown
risks, variables and factors which could cause actual values or
results, performance or achievements to differ materially
from the expectations described in such forward-looking
statements. The Company does not give any assurance or
guarantee that the anticipated results, performance or
achievements expressed or implied in those forward-looking
statements will be achieved.
The Company has concluded that it has a
reasonable basis for providing the forward-looking statements and
production targets included in this announcement and that material
assumptions remain unchanged. The detailed reasons for this
conclusion are outlined throughout this announcement, and in the
ASX and AIM announcements:
1. 29 March 2023 - Tiris Uranium
Project Enhanced Definitive Feasibility Study
2. 28 Feb 2024 - Aura's Tiris FEED
Study returns Excellent Economics
3. 11 Sep 2024 - Updated Production
Target Improves Economics at Tiris
4. 13 Dec 2024 - Tiris Uranium Project
Alternative Production Targets
5. 5 Sept 2023 - Scoping Study
Confirms Scale and Optionality of Häggån
The Company confirms that it is not aware of
any new information materially affecting the information included
in the ASX and AIM announcements:
1. 12 June 2024 - Aura
increases Tiris Mineral Resources by 55% to
91.3Mlbs U3O8
2. 20 Dec 2024
- Amendment - Tiris Ore Reserve
Update
3. 16 Dec 2024
- Substantial increase in Tiris Uranium Project Ore
Reserves
4. 22 Aug 2012 - Outstanding Häggån
Uranium Resource expands to 800 million pounds
5. 10 Oct 2019 - Häggån Battery Metal
Project Resource Upgrade Estimate
All material assumptions and technical
parameters underpinning the Tiris and Häggån Project Mineral
Resources Estimates continue to apply. The Company confirms that
the form and context in which the Competent Person's findings are
presented have not been materially modified from the original
market announcements.
ASX and JORC Related
Disclosures
Mineral
Resources
The information on Mineral Resources for the
Tiris Uranium Project in this report is extracted from the ASX
release on 12 June 2024 titled "Aura increases Tiris Mineral
Resources by 55% to 91.3Mlbs".
The information on Mineral Resources
for the Häggån Project in this report is extracted from the ASX
releases on 10 October 2019 titled "Häggån Battery Metal Project
Resource Upgrade Estimate Successfully Completed" and 22 August
2012 titled "Outstanding Häggån Uranium
Resource expands to 800 million pounds".
These reports can be viewed at https://auraenergy.com.au/investor-centre/asx-announcements.
The company confirms that it is not aware of any
new information or data that materially affects the information
included in the original market announcement and, in the case of
estimates of Mineral Resources that all material assumptions and
technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially
changed. The company confirms that the form and context in which
the Competent Person's findings are presented have not been
materially modified from the original market
announcement.
Ore
Reserves
The information on Ore Reserves for the Tiris
Uranium Project in this report is extracted from the ASX release on
20 December 2024 titled "Amendment - Substantial increase in
Tiris Uranium Project Ore Reserves".
The company confirms that it is not aware of any
new information or data that materially affects the information
included in the original market announcement and, in the case of
estimates of Ore Reserves, that all material assumptions and
technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially
changed. The company confirms that the form and context in which
the Competent Person's findings are presented have not been
materially modified from the original market
announcement.
Production
Targets
The information on Production Targets for the Tiris Uranium
Project in this report is extracted from the ASX releases on 11
September 2024 titled "Updated Production Target Improves Economics
at Tiris" and 12 December 2024 titled "Tiris Uranium Project Alternative Production
Targets". These
reports can be viewed at https://auraenergy.com.au/investor-centre/asx-announcements.
The company confirms that it is not aware of
any new information or data that materially affects the information
included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in
the relevant market announcement continue to apply and have not
materially changed.
Scoping
Study
The information on
Häggån Scoping Study in this report is extracted
from the ASX release on 5 September 2023 titled "Scoping Study
Confirms Scale and Optionality of Häggån". This report can be
viewed at https://auraenergy.com.au/investor-centre/asx-announcements.
The company confirms that it is not aware of
any new information or data that materially affects the information
included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in
the relevant market announcement continue to apply and have not
materially changed.