TIDMAYM 
 
Anglesey Mining plc LSE:AYM 
 
15 August 2012 
 
Interim Management Statement 
 
LIM first quarter results and operational update 
 
Anglesey's major activity is its 26% share of Toronto-listed Labrador Iron 
Mines Holdings Limited (TSX:LIM) which holds twenty direct shipping iron ore 
deposits in western Labrador and north-eastern Quebec and is currently mining 
the first of these to be developed at the James Mine. 
 
Anglesey also has 100% of the Parys Mountain zinc-copper-lead deposit in North 
Wales, UK with a total historical resource in excess of 7 million tonnes at 
over 9% combined copper, lead and zinc. A 2,000 metre exploration programme has 
been completed and results are being compiled into an updated Scoping Study. 
 
Labrador 
 
During the first quarter ended June 30, 2012, LIM sold three shipments 
totalling 486,000 dry tonnes of iron ore and subsequently recognized revenue of 
$38.0 million FOB Port of Sept-Îles from these sales. 
 
For the quarter ended June 30, 2012, LIM reported a loss of $10.6 million, or 
$0.16 per share, compared to a loss of $4.7 million or $0.09 per share during 
the corresponding quarter of last year. The net loss reported included an 
amortization charge of $9.8 million, which was recorded concurrently with the 
commencement of full-scale mining operations. LIM has filed its first quarter 
results and its Management Discussion and Analysis on Sedar where they may be 
accessed in full. 
 
James Mine 
 
The James mine recommenced full-scale operations on April 2, 2012. During the 
quarter ended June 30, 2012, approximately 648,000 tonnes of ore at a grade of 
62.6% Fe were mined. Of the total production during the quarter, approximately 
483,000 tonnes were direct rail ore at an average grade of 62.6% Fe. By the end 
of the quarter, the mine was operating at a rate of 32,000 tonnes per day (ore 
and waste), in excess of its planned mining rate of 28,000 tonnes per day. 
 
The general mining sequence planned for the current year commenced with mining 
higher grade (60%+ Fe) DRO during the early months of the operating season 
while the processing plant was being re-commissioned. This will be followed by 
mining lower grade plant feed (50%+ Fe) in the summer and fall when the 
processing plant is operating at full capacity. In accordance with the mining 
sequence, mainly DRO material was mined at James during the quarter ended June 
30, 2012. 
 
Sinter product is planned to be railed and shipped throughout the summer and 
early fall, followed by railing and shipping lump material in late fall. From 
previous experience, lump ore is most resilient to freezing in railcars during 
the late months of the operating season due to its lower moisture content. 
 
Mass recovery of all products from the ore mined during the quarter ended June 
30, 2012 was approximately 88%. This very high mass recovery percentage is 
largely attributable to the mining of DRO during the quarter. 
 
Processing 
 
Dry Process Stream 
 
During the quarter LIM added a dry classifying system to process (crush and 
screen) lump and sinter fines products as LIM transitions its product mix to 
produce lump and sinter exclusively. This dry process stream, targeting 
high-grade (60%+ Fe) ore, has a design capacity of 1,000 tonnes per day with a 
mass recovery of close to 100%. Moving forward, the additional process 
equipment will supplement the mining sequence and enhance product yield, 
especially during the commissioning period of the wet processing plant. 
 
Silver Yards 
 
Start-up of the Silver Yards processing facility commenced in mid-May and the 
plant was commissioned in five weeks. From mid-May to June 30, 2012, 
approximately 127,000 tonnes of 55.6% Fe material was fed to the plant, 
yielding 52,000 tonnes of lump and sinter fines products. 
 
The Silver Yards processing plant operated at approximately 50% throughput 
capacity and achieved mass yield of 41% during the re-commissioning period. 
Subsequent to the end of the quarter, July throughput averaged 4,300 tonnes per 
day and mass yield increased to 58%. Further plant performance improvements are 
anticipated throughout the current quarter. 
 
The Phase 3 plant expansion is targeted for completion by the end of August. 
This expansion is intended to increase plant throughput to 12,000 tonnes per 
day and improve weight recovery to above 75%. 
 
Rail and Port 
 
During the quarter, approximately 532,000 tonnes of iron ore was railed to the 
Port of Sept-Îles. 
 
Rail operations continued to ramp up in July, with an additional 240,000 wet 
tonnes railed to the Port. LIM has lengthened two of its train sets, increasing 
their capacity by over 30%. In addition, a fifth train set is scheduled for 
delivery later this year and is expected to increase sales volumes for the 
balance of the 2012 season. 
 
In June 2012, LIM completed a life-of-mine agreement with the Tshiuetin Rail 
Transportation Inc. ("TSH") railway, replacing its previous annual agreement. 
 
Subsequent to the end of the quarter, LIM announced two important developments 
that will enhance and provide optionality for long-term rail and port access of 
LIM's iron ore. The first was participation in the development of the new 
multi-user dock at the Port of Sept-Îles, which will be dedicated exclusively 
to iron ore shipments. Under the terms of the agreement with the Port 
Authority, LIM has reserved an annual capacity of 5 million tonnes of iron ore 
with a right to secure additional residual capacity. Construction of the new 
dock is expected to be completed by March 31, 2014. 
 
LIM also announced its collaboration in working with CN on a feasibility study 
to develop a new, continuous multi-user rail line and a new terminal handling 
facility located at the Port of Sept-Îles, which would complement the planned 
development of the new multi-user dock previously mentioned. 
 
Sales 
 
During the quarter ended June 30, 2012, LIM sold three capesize shipments 
totalling 486,000 dry tonnes of direct rail ore with a grade of 63.2%Fe at a 
weighted average price of approximately US$122 per tonne on a CFR China basis. 
Direct rail ore is a mixed-size fraction product that requires additional 
crushing and screening by the customer and, as such, is sold at a discount to 
the benchmark price. Subsequent to the end of the first quarter, one additional 
capesize shipment of direct rail ore was sold in July and another capesize 
shipment of direct rail ore is currently stockpiled at the Port. After this 
stockpile is sold, all remaining sales during the year are planned to be lump 
and sinter fines products. 
 
Production and Operating Costs 
 
LIM is on track to meet its 2012 saleable production target of 2 million tonnes 
of iron ore. During the quarter ended June 30, 2012, operating costs of product 
sold, unloaded at the port, were approximately $72 per tonne. Included in this 
amount were approximately $7.50 per tonne sold in non-recurring charges related 
to contractor mobilization, railway take-or-pay fees in April, and certain 
one-off charges related to port facility set-up in 2011 at the Pointe aux 
Basques wharf, which is no longer being pursued. In addition, fixed costs per 
tonne were higher than planned due to revenue recognition on three sales rather 
than the four anticipated for the quarter. Excluding these non-recurring 
charges, operating costs were approximately $64.50 per tonne of product sold. 
Cash operating costs per tonne of product sold in June and July were lower and 
within LIM's 2012 guidance of $60 to $65 per tonne, unloaded at the port. 
 
LIM's operating results for the quarter ended June 30, 2012, is outlined in the 
table below. 
 
Production for the Quarter Ended June 30, 2012 
 
(all tonnes are dry metric tonnes)          Tonnes Grade (% Fe) 
 
Total Ore Mined                            668,193        62.6 
 
Direct Rail Ore portion                    483,444        62.6 
 
Waste Mined                              1,369,398           - 
 
Ore Processed                              127,463        55.6 
 
Lump Ore Produced                           17,728        60.2 
 
Sinter Fines Produced                       34,711        65.6 
 
Total Product Railed                       532,329        62.6 
 
Tonnes Product Sold                        486,506        63.2 
 
Port Product Inventory                     223,492        63.0 
 
Site Product Inventory                      65,372        64.0 
 
Run-of-Mine Ore inventory                  273,503        58.8 
 
Houston Development 
 
During the quarter ended June 30, 2012 and subsequent thereto, LIM has been 
preparing and submitting applications for permits and regulatory approvals 
required for the construction of mine infrastructure and related facilities to 
enable the development and construction at the Houston deposits in the 
remainder of 2012 and the first half of 2013. Development work to date includes 
completion of forestry work clearing the planned Houston access road route and 
commencement of forestry work clearing the planned Houston rail siding route. 
Engineering consultants have been chosen to design the Houston access road, 
bridge and rail siding, and their design work has commenced. 
 
LIM remains committed to executing on its development plans for the Houston 
deposits. To the end of June 30, 2012, approximately $1 million had been 
expended on the Houston project. LIM is currently reviewing its capital 
expenditure programmes for the balance of 2012. 
 
2012 Exploration Programme 
 
Fieldwork for the 2012 exploration programme began in June with the 
mobilization of LIM's contract drillers targeting improved delineation of the 
Houston 1 and 3 resources. 
 
In addition, LIM completed its first diamond drill hole on the Houston 3 
deposit at a depth of 140 m. This part of the drilling programme is aimed at 
proving up the potential use of diamond drilling to recover core needed to 
better understand the geological, geotechnical and various metallurgical 
parameters of the Houston, James and Malcolm deposits. 
 
The overall 2012 exploration programme plans for the completion of 
approximately 10,800 m of drilling, of which 8,000 metres could be achieved by 
diamond drilling. By the end of July, two drill rigs were mobilized and 
drilling activities ramped up significantly for a total of about 2,000 m of RC 
and diamond drilling completed. Two additional drill rigs are expected to be 
added by the end of August, which will further advance these drill programmes. 
 
Ground geophysical surveys were also carried out during the quarter to 
determine drill target locations on recently identified taconite iron 
mineralization - the Gagnon and Elizabeth taconites. The Schefferville/Menihek 
area has a number of taconite deposits being explored by other companies and 
these deposits, which usually average about 30% Fe, can often show very 
significant tonnages. Ground geophysical surveys were also carried out on the 
Houston, James and Howse deposits and were completed in July. 
 
A bulk sampling programme of some historic stockpiles will be initiated this 
month with a view to providing supplemental plant feed to the Silver Yards 
processing plant. Metallurgical test work aimed at evaluating historical 
manganese resources will also be carried out with a view to ascertaining 
compatibility with the Silver Yards processing plant flow sheet. 
 
LIM recently completed a ground gravity survey on the James deposits. This 
survey identified a positive anomaly extending approximately 400 m southeast of 
the James South orebody, containing similar characteristics to that of the 
James deposits. This anomaly will be drill tested later this year. 
 
Iron ore Price Outlook 
 
Iron ore spot prices continued to soften throughout the second quarter of the 
calendar year, with port inventories in China remaining high, while Chinese 
steelmakers experienced a squeezing of operating margins. Recently, Chinese 
traders were apparently liquidating inventories. By early August, spot prices 
have continued to decline and have reached US$111 on a CFR China basis. 
 
Market commentators are speculating that a bottom could be reached this 
quarter, as the current spot price is below the assumed marginal cost of 
Chinese production. LIM believes this is likely and anticipates that prices 
will recover to the US$130 to US$140 range on a CFR China basis later in the 
year. 
 
Financial Review 
 
During the fiscal first quarter ended June 30, 2012, LIM sold three shipments 
totalling 486,000 dry tonnes of iron ore and subsequently recognized revenue of 
$38.0 million (FOB Port of Sept-Îles) from the sale of these shipments. 
 
Operating costs, including mining, processing, transportation and site 
expenses, were $35.1 million or $72 per tonne of iron ore sold during the 
quarter. Operating costs for the quarter included non-recurring charges related 
to contractor mobilization, railway take-or-pay fees in April, and certain 
charges from 2011 related to port facility set-up. Operating costs per tonne 
sold in June and July have been lower and are within LIM's 2012 guidance of $60 
to $65 per tonne, unloaded at the Port. 
 
For the quarter ended June 30, 2012, LIM reported a loss of $10.6 million, or 
$0.16 per share, compared to a loss of $4.7 million or $0.09 per share during 
the corresponding quarter of last year. The net loss reported included an 
amortization charge of $9.8 million, which was recorded concurrently with the 
commencement of full-scale mining operations. This amortization represents a 
period charge, primarily on a units-of-production basis, of the cost of the 
James mine (including capitalized stripping and dewatering), Silver Yards 
processing plant, transportation equipment and infrastructure, and site 
administration properties associated with the operational activities of the 
James mine. There was no such comparable amortization charged in the same 
quarter of the previous year, as LIM's mining operations were still in a 
start-up phase during that period. 
 
During the quarter LIM invested approximately $2.7 million in its mineral 
property interests. This investment was mainly exploration and development and 
operating expenditures on deposits other than the James deposit. The equivalent 
investment in the same quarter of the previous year was $4.1 million. 
 
Also during the quarter LIM invested approximately $19.0 million in property, 
plant and equipment, which consisted mainly of investments in procurement and 
construction activities for the Phase 3 expansion of Silver Yards, grid 
connection infrastructure, railcar modifications and expansion of the mine 
accommodation camp. 
 
As at June 30, 2012, LIM had current assets of $89.0 million, including 
inventories with a carrying value of $16.5 million and accounts receivable and 
prepaid expenses of $49.1 million. At June 30, 2012, LIM had a total of $22.0 
million in unrestricted cash and cash equivalents and an additional $7.6 
million in restricted cash. 
 
LIM had working capital of $42.8 million as at June 30, 2012. LIM has no debt. 
 
Management regularly monitors conditions in the iron ore market and in 
particular, price trends for iron ore. Proposed capital expenditures are 
therefore reviewed on a regular basis in comparison to budgeted and projected 
operational cash flow in order to prudently manage cash balances. 
 
Parys Mountain 
 
In 2012 a 12 hole 2,000 metre diamond drilling exploration programme at three 
separate sites at Parys Mountain has been completed. These holes were in the 
upper portion of the Engine Zone adjacent to the White Rock Zone, in the Great 
Open cast area, and at the Pearl Engine House area. All the stages of this 
programme are considered to have been successful. The Pearl area drilling is 
particularly encouraging as it opens up an area that is more than one kilometre 
away from the Morris Shaft and in conjunction with previous results from the 
Garth Daniel area which lie midway between the Pearl Engine House and Morris 
Shaft locations demonstrates that mineralisation at potentially economic grades 
and widths persists across the entire property. This can only generate further 
optimism and interest in the overall potential for Parys Mountain. 
 
Micon International has been retained to update the resource estimates for all 
of Parys Mountain to bring them a compliant basis work based on JORC and has 
further been retained to conduct a scoping study for a small scale stand-alone 
mining operation. This study will incorporate both the entire White Rock zone 
and the now compliant Engine Zone, and will update Micon's 2007 study which was 
based solely on the shallow portion of the White Rock resources close to the 
Morris Shaft. 
 
In July 2012 an agreement was reached with Intermine Limited whereby the net 
profits royalty formerly due to Intermine has been bought out and all amounts 
due have been discharged. At 15 August 2012 there is available cash of 
approximately GBP1.8 million. 
 
About Anglesey Mining plc 
 
Anglesey holds 26% of Toronto-listed Labrador Iron Mines Holdings Limited which 
is producing iron ore from its James deposit, one of LIM's twenty direct 
shipping iron ore deposits in western Labrador and north-eastern Quebec. 
 
Anglesey is also carrying out development and exploration work at its 100% 
owned Parys Mountain zinc-copper-lead deposit in North Wales, UK where there is 
estimated to be a total historical resource in excess of 7 million tonnes at 
over 9% combined copper, lead and zinc. 
 
For further information, please contact: 
 
Bill Hooley, Chief Executive +44 (0)1492 541981; 
 
Ian Cuthbertson, Finance Director +44 (0)1248 361333; 
 
Samantha Harrison / Klara Kaczmarek: RFC Ambrian +44 (0)2076 344700; 
 
Emily Fenton / Jos Simson: Tavistock Communications +44 (0)20 7920 3155 
 
 
 
END 
 

Anglesey Mining (LSE:AYM)
Graphique Historique de l'Action
De Juin 2024 à Juil 2024 Plus de graphiques de la Bourse Anglesey Mining
Anglesey Mining (LSE:AYM)
Graphique Historique de l'Action
De Juil 2023 à Juil 2024 Plus de graphiques de la Bourse Anglesey Mining