Progress Report
The Board wish to announce the Company's further progress towards achieving the
objectives set out in its Admission Document:
1. Operational - The mill at Drylands turned for first time on August 1,
only one year after casting foundations, on schedule and within budget. In
initial tests, the plant is performing well under load. Full production at
Drylands is forecast for December 2002
2. Plant purchases - The Company has purchased 9 mills, spares and
mill house for #156,250. Strategic spares are included in the purchase
price. This demonstrates the Company's ability to purchase low cost good quality
used plant
12 August 2002
END
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCBKBKNDBKDCFD
Bullion Res (LSE:BLO)
Graphique Historique de l'Action
De Mai 2024 à Juin 2024
Bullion Res (LSE:BLO)
Graphique Historique de l'Action
De Juin 2023 à Juin 2024
Real-Time news about Bullion Res (London Stock Exchange): 0 recent articles
Plus d'articles sur Bullion Resources