Operational Update
- Self-mined Bitcoin: 126 Bitcoins, down
from the previous month due to temporary curtailments at our Bhutan
site related to higher seasonal electricity prices.
- Mining Rig Manufacturing and R&D:
- SEALMINER A1:
- Mass production of approximately 3.7 EH/s of mining rigs
remains on track with 0.4 EH/s powered on, 0.5 EH/s delivered for
installation, 0.4 EH/s in-transit to datacenters and 2.4 EH/s in
production. The manufacture of SEALMINER A1 is now expected to be
completed at end of February or early March 2025.
- SEALMINER A2:
- Production of approximately 35 EH/s of mining rigs through
October 2025, delayed by approximately one month due to 6.4
magnitude earthquake that struck Taiwan on January 21, 2025.
- First trial batch of air cooled rigs have been delivered to our
mining datacenters for testing and are running stably.
- ~29,000 units (~7 EH/s out of the 35 EH/s) of SEALMINER A2s
allocated for external sales are expected to begin shipment in
March through Q2 2025.
- SEALMINER A3:
- SEAL03 initial tape-out sample wafers with an expected chip
efficiency of approximately 10 J/TH are expected in Q1 2025.
- SEALMINER A4:
- SEAL04 R&D remains on track to achieve an expected chip
efficiency of approximately 5 J/TH with anticipated initial
tape-out in Q3 2025.
- The Bureau of Industry and Security (“BIS”) of the U.S.
Department of Commerce published a rule entitled “Implementation of
Additional Due Diligence Measures for Advanced Computing Integrated
Circuits”, in January 2025 (the “BIS Rules”). Based on preliminary
review, the Company does not expect that the application of the BIS
Rules will have any impact on the delivery of SEAL chips, as the
outsourced semiconductor assembly and test (“OSAT”) companies for
SEAL chips are Approved “OSAT” companies under BIS
regulations.
- HPC/AI:
- Discussions are ongoing with multiple development partners and
potential end users for select large scale sites in U.S. for
HPC/AI.
- Bitdeer AI Cloud, powered by NVIDIA DGX SuperPOD with H100, saw
its average utilization rate drop to ~60% in January 2025 due to an
initial shift toward R&D in model inference and AI Agents. In
the short term, some DGX H100 systems will be allocated to
deploying open-source models like DeepSeek, Llama, and Qwen,
enhancing API support for AI Agents, optimizing platform services,
and advancing related R&D.
- Hosting:
- Client-hosted machines increased by 2,000 units and overall
hashrate increased by 0.5 EH/s as customers are replacing older
mining rigs with high efficiency ones.
- Infrastructure:
- Tydal, Norway, 40 MW phase 1 expansion has completed
installation of transformers, with delivery and installation of
electrical equipment currently in progress. The energization
application has entered into the fast track for final regulatory
approval.
- Rockdale, Texas, USA, 100 MW hydro-cooling conversion is on
track for phased completion during Q1 2025.
- Clarington Phase 2, Ohio, USA, 304 MW is still pending approval
and in negotiation with the landlord.
- Jigmeling, Bhutan, 500 MW construction is on track with the
primary substation expected to be completed by Q1 2025.
- Fox Creek, Alberta, 101 MW gas-fired power plant and 99 MW
datacenter of capacity for Bitcoin mining planned for energization
in Q4 2026.
- Financing:
- Successfully executed a $17M supply chain financing facility
with a 10.2% interest rate with a Singapore financial institution
and completed the drawdown of facility in January 2025.
Management Commentary
“Our strategic acquisition of the 101 MW site near Fox Creek,
Alberta and gas-fired power plant project marks a significant step
in our strategy to become a fully-vertically integrated Bitcoin
miner,” stated Matt Kong, Chief Business Officer of Bitdeer. “By
combining our own power generation, SEALMINER mining machines and
opportunistic grid participation, we believe this site will set a
new benchmark for industry unit economics.”
Mr. Kong continued, “In terms of our ASICs roadmap, mass
production of our SEALMINER A1s remain on schedule. SEALMINER A2s
were slightly impacted by the 6.4 magnitude earthquake in Taiwan on
January 21, 2025, and its mass production in H2 is expected to
delay about one month. However, the first trial batch of SEALMINER
A2 air cooled models have been delivered to our own datacenters for
testing and are running smoothly. Further, we expect the initial
tape-out sample wafers of our SEAL03 chip to be ready in March for
testing. SEAL03 is expected to be the most advanced and
energy-efficient Bitcoin mining chip on the market and represents a
significant achievement for Bitdeer and the industry.”
Production and Operations Summary
Metrics |
Jan 2025 |
Dec 2024 |
Nov 2024 |
Total hash rate under
management1(EH/s) |
22.4 |
21.6 |
20.7 |
- Proprietary hash rate |
9.2 |
8.9 |
8.8 |
• Self-mining |
8.7 |
8.5 |
8.2 |
• Cloud Hash Rate |
0.0 |
0.0 |
0.2 |
• Delivered but not hashing |
0.5 |
0.4 |
0.4 |
- Hosting |
13.2 |
12.7 |
11.9 |
Mining machines under management |
179,000 |
175,000 |
178,000 |
- Self-owned2 |
87,000 |
85,000 |
86,000 |
- Hosted |
92,000 |
90,000 |
92,000 |
Bitcoins mined (self-mining only) |
126 |
145 |
150 |
Bitcoin held3 |
724 |
594 |
443 |
1 Total hash rate under management as of
January 31, 2025 across the Company’s three primary business lines:
Self-mining, Cloud Hash Rate, and Hosting.
- Self-mining refers to cryptocurrency mining
for the Company’s own account, which allows it to directly capture
the high appreciation potential of cryptocurrency.
- Cloud Hash Rate offers hash rate subscription
plans and shares mining income with customers under certain
arrangements. The Cloud Hash Rate stated above reflects the
contracted hash rate with customers at month-end.
- Hosting encompasses a one-stop mining machine
hosting solution including deployment, maintenance, and management
services for efficient cryptocurrency mining.
2 Self-owned mining machines are for the
Company’s self-mining business and Cloud Hash Rate business.3
Bitcoins held do not include the Bitcoins from
deposits of the customers.
Infrastructure Construction Update
Rockdale, Texas – 100 MW Hydro-cooling
conversion to be energized in phases in Q1 2025:
- Cooling system will be delivered and installed in phases in Q1
2025.
- Planning for phased energization by March 2025.
Tydal, Norway – 175 MW site expansion
anticipated to be fully energized by mid-2025:
- Installation of the transformers has been completed, with the
delivery and installation of electrical equipment currently in
progress. Additionally, the procurement and delivery of containers
and hydro-cooling systems are underway, and drainage systems
construction is ongoing.
- Tydal, Norway Phase 1 40 MW expansion pending regulatory
approval. Energization of the full 175 MW site is expected to occur
no later than mid-2025, subject to regulatory approval.
Massillon, Ohio – 221 MW site construction has
begun ahead of schedule:
- Substation construction is underway and is expected to be
completed in Q3 2025.
- Building design is completed and construction has begun earlier
than expected, estimated to be completed in phases between Q3 and
Q4 2025.
- Estimated energization timeline remains on track for
mid-to-late 2025.
Clarington Phase 2, Ohio – 304 MW is still
pending approval and in negotiation with the landlord.
Jigmeling, Bhutan – 500 MW site is progressing
well, with the following key milestones achieved:
- Construction of transformer and container foundations in
progress and will be completed in phases, with the last phase
expected by the end of February 2025.
- 132kv/140MW and 220kv/360MW substation designs are completed
with construction anticipated to be finished by the end of Q1
2025.
- Orders for the procurement of transformers and electrical
equipment have been placed, with delivery and installation work to
be completed in phases over Q1 and Q2 2025.
- Procurement and delivery of containers and hydro-cooling
systems are in progress, with completion expected in phases by the
end of Q1 2025.
Fox Creek, Alberta – 101 MW site acquired in
Alberta sits on 19 acres is fully licensed and permitted:
- Acquisition includes all permits and licenses to construct an
on-site natural gas power plant, as well as approval for a 99 MW
grid interconnection with Alberta Electric System Operator
(“AESO”).
- Bitdeer will develop and construct the power plant in
partnership with a leading Engineering, Procurement and
Construction (“EPC”) company and is expected to be energized by Q4
2026.
Site / Location |
Capacity (MW) |
Status |
Timing4 |
Electrical capacity |
|
|
|
- Rockdale, Texas |
563 |
Online |
Completed |
- Knoxville, Tennessee |
86 |
Online |
Completed |
- Wenatchee, Washington |
13 |
Online |
Completed |
- Molde, Norway |
84 |
Online |
Completed |
- Tydal, Norway |
50 |
Online |
Completed |
- Gedu, Bhutan |
100 |
Online |
Completed |
Total electrical capacity |
8955 |
|
|
Pipeline capacity |
|
|
|
- Tydal, Norway Phase 1 |
40 |
In progress |
Pending Regulatory Approval |
- Tydal, Norway Phase 2 |
135 |
In progress |
Mid 2025 |
- Massillon, Ohio |
221 |
In progress |
Mid-to-late 2025 |
- Clarington, Ohio Phase 1 |
266 |
In progress |
Q3 2025 |
- Clarington, Ohio Phase 2 |
304 |
Pending approval |
Estimate 2026 |
- Jigmeling, Bhutan |
500 |
In progress |
Mid-to-late 2025 |
- Rockdale, Texas |
179 |
In planning |
Estimate 2026 |
- Alberta, Canada |
99 |
In planning |
Q4 2026 |
Total pipeline capacity |
1,744 |
|
|
Total global electrical capacity |
2,639 |
|
|
4 Indicative timing. All timing references are to calendar
quarters and years.5 Figures may not add up due to rounding.
Upcoming Conferences and Events
- March 11 – 12, 2025: Cantor Global Technology
Conference in New York City
- March 16 – 18, 2025: 37th Annual ROTH Growth
Conference in Dana Point, California
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company
for blockchain and high-performance computing. Bitdeer is committed
to providing comprehensive computing solutions for its customers.
The Company handles complex processes involved in computing such as
equipment procurement, transport logistics, datacenter design and
construction, equipment management, and daily operations. The
Company also offers advanced cloud capabilities to customers with
high demand for artificial intelligence. Headquartered in
Singapore, Bitdeer has deployed datacenters in the United States,
Norway, and Bhutan. To learn more,
visit https://ir.bitdeer.com/ or follow Bitdeer on X @
BitdeerOfficial and LinkedIn @ Bitdeer Group.
Investors and others should note that Bitdeer
may announce material information using its website and/or on its
accounts on social media platforms, including X, formerly known as
Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages
investors and others to review the information it posts on the
social media and other communication channels listed on its
website.
Forward-Looking Statements
Statements in this press release about future expectations,
plans, and prospects, as well as any other statements regarding
matters that are not historical facts, may constitute
“forward-looking statements” within the meaning of The Private
Securities Litigation Reform Act of 1995. The words “anticipate,”
“look forward to,” “believe,” “continue,” “could,” “estimate,”
“expect,” “intend,” “may,” “plan,” “potential,” “predict,”
“project,” “should,” “target,” “will,” “would” and similar
expressions are intended to identify forward-looking statements,
although not all forward-looking statements contain these
identifying words. Actual results may differ materially from those
indicated by such forward-looking statements as a result of various
important factors, including factors discussed in the section
entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as
well as discussions of potential risks, uncertainties, and other
important factors in Bitdeer’s subsequent filings with
the U.S. Securities and Exchange Commission. Any
forward-looking statements contained in this press release speak
only as of the date hereof. Bitdeer specifically disclaims any
obligation to update any forward-looking statement, whether due to
new information, future events, or otherwise. Readers should not
rely upon the information on this page as current or accurate after
its publication date.
For investor and media inquiries, please
contact:
Investor RelationsOrange GroupYujia
ZhaibitdeerIR@orangegroupadvisors.com
Public RelationsBlocksBridge ConsultingNishant
Sharmabitdeer@blocksbridge.com
Bitdeer Technologies (NASDAQ:BTDR)
Graphique Historique de l'Action
De Jan 2025 à Fév 2025
Bitdeer Technologies (NASDAQ:BTDR)
Graphique Historique de l'Action
De Fév 2024 à Fév 2025