This news release constitutes a "designated
news release" for the purposes of the Company's prospectus
supplement dated August 12, 2024, to
its short form base shelf prospectus dated June 21, 2024.
RENO,
Nev., Feb. 18, 2025 /CNW/ - i-80 GOLD
CORP. (TSX: IAU) (NYSE: IAUX) ("i-80 Gold", or the
"Company") is pleased to announce the results of the
preliminary economic assessment (the "PEA") for the Archimedes
Underground Project ("Archimedes" or the "Project"), situated
within the Company's broader Ruby Hill Complex (the "Complex"). The
Complex is located along the southeastern end of the Battle
Mountain-Eureka Trend in northeastern Nevada, United States. The PEA confirms that
Archimedes has the potential to become a key component of the
Company's regional hub-and-spoke mining and processing
strategy.
"The release of the Archimedes PEA marks another step forward in
our plan to establish i-80 Gold's broader hub-and-spoke mining and
processing strategy in northeastern Nevada. Based on the PEA,
Archimedes is expected to contribute meaningfully to the overall
production and economics of the Company's hub-and-spoke strategy in
spite of higher transportation costs to our central autoclave
facility, and lower grades relative to the Company's two other
underground projects. The PEA's findings show that at a base case
gold price of $2,175/oz, Archimedes
Underground is at the lower end of valuation compared to other
underground gold projects in our portfolio, however it presents the
highest leverage to gold prices," stated Richard Young, Chief Executive Officer.
PEA Highlights
Mineral Estimates, Production and Mine Life
- High-grade underground gold mine with a life of mine ("LOM") of
approximately 10 years.
- Average annual gold production of approximately 100,000 ounces
of gold following ramp up.
- Estimated LOM cash costs(1) of $1,769 per ounce and all-in-sustaining
costs(1) of $1,893 per
ounce.
- Updated mineral resource estimate resulting in an indicated
gold mineral resource of 436,000 ounces at 7.6 grams per tonne
("g/t") and an inferred gold mineral resource of 988,000 ounces at
7.3 g/t.
- All drilling conducted within the Archimedes underground area
since the property's acquisition in 2021, is included in the PEA.
Additional infill drilling is expected to be completed from the
underground on the Ruby Deeps and the 426 zone in 2027 to be
included in a planned feasibility study in 2028.
- Several exploration targets to be followed up on in the coming
years to potentially extend the mine life beyond the current 10
years.
Project Economics
- Based on a $2,175/oz gold price,
the Project's undiscounted after-tax cash flows(2)(3)
total $212 million with an after-tax
net present value(2)(3) ("NPV") of $127 million, assuming a 5% discount rate,
generating a 23% internal rate of return ("IRR").
- Based on a spot gold price of $2,900/oz, the Project's undiscounted after-tax
cash flows(2)(3) total $902
million with an after-tax NPV(2)(3) of
$581 million, assuming a 5% discount
rate, generating a IRR of 75%.
- Mine construction capital is estimated at $49 million.
- LOM development and sustaining capital is estimated at
$106 million.
Mining and Processing
- Long hole open stoping with delayed backfill is the primary
planned mining method.
- Approximately 90% of the material mined is anticipated to be
processed at i-80 Gold's Lone Tree autoclave facility (see Figure
1) starting in 2028. The remainder is expected to be processed at a
third-party autoclave facility in 2026 and 2027, as well as the
property's heap leach facility.
- Overall average gold grade processed of 7.0 g/t with an average
gold recovery of 90% (autoclave) and an average expected heap leach
grade of 3.8 g/t gold with an average recovery of 87%.
All amounts are in United
States dollars, unless otherwise stated.
A summary of key valuation, cost, and operating metrics is
presented in Table 1 below. For more detailed metrics presented on
an annual basis, see Archimedes Underground Project Detailed Cash
Flow Model in the Appendix.
Table 1: Summary of PEA Key Operating and Financial
Metrics
Project Economics
|
Unit
|
|
Gold Price
|
$/oz
|
$2,175
|
Silver Price
|
$/oz
|
$27.25
|
Pre-Tax
NPV(5%)(2)
|
$M
|
$126.8
|
After-Tax
NPV(5%)(2)(3)
|
$M
|
$126.8
|
After-Tax
IRR(3)
|
%
|
23 %
|
After-Tax Cash
Flow(3)
|
$M
|
$211.9
|
|
|
|
Production
Profile
|
|
|
Mine Life
|
years
|
10
|
Mineralized Material
Mined
|
000s
tonnes
|
4,566.9
|
Gold Grade of
Mineralized Material Mined
|
g/t Au
|
7.0
|
Silver Grade of
Mineralized Material Mined
|
g/t Ag
|
1.64
|
Waste Tonnes
Mined
|
000s
tonnes
|
1,353.8
|
Total Tonnes
Mined
|
000s
tonnes
|
5,920.7
|
Total Mineralized
Material Processed
|
000s
tonnes
|
4,566.9
|
Gold Grade
Processed
|
g/t Au
|
7.0
|
Silver Grade
Processed
|
g/t Ag
|
1.64
|
Average Gold
Recovery
|
%
|
90 %
|
Average Silver
Recovery
|
%
|
10 %
|
Total Gold
Recovered
|
000s oz
|
927.9
|
Total Silver
Recovered
|
000s oz
|
24.3
|
Average Annual Gold
Production (LOM)
|
000s oz
|
84.4
|
Average Annual Gold
Production
(following production ramp up)
|
000s oz
|
101.9
|
|
Unit Operating
Costs
|
|
|
LOM Operating
Cost
|
|
|
Mineralized Material
Mined
|
$/t mined
|
$130.2
|
Mineralized Material
and Waste Mined
|
$/t mined
|
$126.7
|
Processed (autoclave
& heap leach)
|
$/t milled
|
$107.3
|
Transportation
|
$/t milled
|
$42.1
|
Dewatering
Electricity
|
$/t milled
|
$6.4
|
G&A
|
$/t milled
|
$17.3
|
LOM Total Cash
Costs(1) (net of by-product credit)
|
$/oz
|
$1,769
|
LOM All-in Sustaining
Costs(1) (net of by-product credit)
|
$/oz
|
$1,893
|
|
Total Capital
Costs
|
|
|
Construction
Capital
|
$M
|
$47.3
|
Definition &
Conversion Drilling
|
$M
|
$10.6
|
LOM Development &
Sustaining Capital
|
$M
|
$97.6
|
Closure
Costs
|
$M
|
$8.9
|
Total Capital &
Closure Costs
|
$M
|
$164.4
|
"The Archimedes PEA reinforces its value within i-80 Gold's
portfolio, with the potential to achieve the highest mining rate
among our underground operations. The geometry of the mineralized
body supports the use of bulk mining methods, driving lower unit
costs and enhancing project economics. Additionally, extensive
infrastructure is already in place, and the sequential permitting
approach allows us to expedite mining activities through mid-2027,
while finalizing approvals for the lower section," added
Matthew Gili, President and Chief
Operating Officer.
Mineral Resource Update
The PEA includes all drilling conducted on the Archimedes
underground since i-80 Gold's acquisition of the property. The
updated mineral resource estimate includes a total of 436,000
ounces of gold at 7.6 g/t Au in the indicated category and
988,000 ounces of gold at 7.3 g/t Au in the inferred category
(see Table 2). The majority of the resource estimate is currently
hosted in the Ruby Deeps deposit (see Figure 1). The mineral
resource estimate is based on stope optimization software. This
methodology is more accurate than previous estimation techniques
and has become the industry standard for underground deposits in
Nevada.
The updated resource estimate includes all drilling since 2021,
as well as stope optimization which results in additional
mineralized body constraints. Overall, the indicated resource
tonnes and gold ounces have increased by 49% and 116%,
respectively, as compared to the 2021 resource estimate resulting
in a total of 436,000 indicated gold ounces contained. The increase
in indicated ounces is offset by a decline in inferred tonnes and
ounces by 49% and 37%, respectively, resulting in a total of
988,000 inferred ounces contained. Gold grades have increased in
all categories of resource, improving by 46% in the indicated
category and 21% in the inferred category.
Once the underground drill platforms are constructed, a
significant infill drill program is planned for Ruby Deeps and the
426 zone in the coming years to follow up on earlier positive
results in a more cost-effective manner with the goal of extending
the mine life beyond the current 10 years. Ruby Deeps remains
open to the north and south, offering substantial exploration
potential.
An updated mineral resource estimate is expected to be completed
in 2028 for inclusion in a planned feasibility study. The updated
resource is expected to include 50,000 meters of drilling, of which
the majority is infill drilling to define reserves, targeting the
426 zone and the Ruby Deeps scheduled for 2027.
Table 2: Archimedes Underground Mineral Resource Estimate as
of December 31, 2024
|
Indicated Mineral
Resources
|
|
|
Tonnes
|
Au
|
Ag
|
Au
|
Ag
|
|
|
(000)
|
(g/t)
|
(g/t)
|
(000
oz)
|
(000
oz)
|
|
426
|
899
|
6.9
|
0.8
|
199
|
22
|
|
Ruby Deeps
|
892
|
8.3
|
2.4
|
237
|
69
|
|
Total
Indicated
|
1,791
|
7.6
|
1.6
|
436
|
92
|
|
|
|
|
|
|
Inferred Mineral
Resources
|
|
|
Tonnes
|
Au
|
Ag
|
Au
|
Ag
|
|
|
(000)
|
(g/t)
|
(g/t)
|
(000
oz)
|
(000
oz)
|
|
426
|
1,038
|
6.6
|
1.2
|
219
|
40
|
|
Ruby Deeps
|
3,150
|
7.6
|
2.4
|
769
|
246
|
|
Total
Inferred
|
4,188
|
7.3
|
2.1
|
988
|
286
|
|
Notes to table
above:
|
I.
|
Mineral resources have
been estimated at a gold price of $2,175 per troy ounce;
|
II.
|
Mineral resources have
been estimated using pressure oxidation gold metallurgical
recoveries of 96.8% and 89.5% for the 426 and Ruby Deeps deposits
respectively;
|
III.
|
Pressure oxidation
cutoff grades are 5.06 and 5.48 Au g/t (0.148 and 0.160 opt) for
the 426 and Ruby Deeps deposits respectively;
|
IV.
|
The effective date of
the Mineral resource estimate is December 31, 2024;
|
V.
|
Mineral resources,
which are not mineral reserves, do not have demonstrated economic
viability. The estimate of mineral resources may be materially
affected by environmental, permitting, legal, title,
socio-political, marketing, or other relevant factors;
|
VI.
|
An inferred mineral
resource is that part of a mineral resource for which quantity and
grade or quality are estimated on the basis of limited geological
evidence and sampling. Geological evidence is sufficient to imply
but not verify geological and grade or quality continuity. An
inferred mineral resource has a lower level of confidence than that
applying to an indicated mineral resource and must not be converted
to a mineral Reserve. It is reasonably expected that the majority
of inferred mineral resources could be upgraded to indicated
mineral resources with continued exploration; and
|
VII.
|
The reference point for
mineral resources is in situ.
|
Economic Analysis
The Project's NPV and IRR in relation to fluctuations in the
long-term gold price are outlined in Table 3 and the Project's cost
sensitivities are illustrated in Figure 2 below. Capital costs have
been sensitized against mine facilities and drilling.
Table 3: Archimedes Project Gold Price Sensitivity After-tax
Analysis
|
Gold Price
($/oz)
|
|
|
$2,000
|
$2,175
|
$2,500
|
$2,750
|
$2,900
|
$3,000
|
NPV5%(2) ($M)
|
|
$17
|
$127
|
$331
|
$487
|
$581
|
$644
|
IRR (%)
|
|
8 %
|
23 %
|
48 %
|
65 %
|
75 %
|
81 %
|
Project Overview
Archimedes is located along the southeastern end of the
Battle Mountain/Eureka gold trend. The Project is a component
of the broader Ruby Hill Complex and an extension of the
historically mined open pit, which was a major past-producing
asset. During the 1990s, an ore body was discovered, which became
the Archimedes Pit. Later discoveries included the Ruby Deeps
sulfide deposit with the most recent discovery of the polymetallic
Hilltop zone.
The Complex also includes the Mineral Point deposit, an open pit
heap leach project, as well as several base metal deposits. Mineral
Point is a large oxide gold and silver deposit with the potential
to become the Company's largest gold producing asset. An updated
PEA for the Mineral Point open pit project is expected to be
completed in the first quarter of 2025. Processing infrastructure
at the Complex includes a primary and secondary crushing plant,
grinding mill, leach pad, and carbon-in-column circuit, which are
designed to process oxide material. The Archimedes deposit is
composed of single refractory sulfide material, which is not
amenable to the facilities at the Complex, and therefore, will be
trucked to the Company's Lone Tree property.
Geology and Mineralization
The Archimedes underground deposit is comprised of the Ruby
Deeps and 426 zone, which are located immediately northwest and
below the historic Archimedes Pit (see Figure 1). Both the 426 zone
and Ruby Deeps consist of Carlin-Type mineralization, characterized
by fine-grained pyrite with gold bearing arsenic-rich rims. In the
426 zone, mineralization is primarily located in the lower
laminated portion of the Ordovician Goodwin limestone along the
northeast striking 426 fault zone. The 426 zone is generally
flat-lying and consists of a mixture of oxide and sulfide material.
At Ruby Deeps, mineralization is found in the Cambrian Windfall
limestone, Dunderberg shale, and a Cretaceous granodiorite sill, in
the hanging-wall of the north striking Holly fault. The mineralized
zone in Ruby Deeps is generally flat-lying and consists entirely of
sulfide material.
Mining and Processing
The PEA demonstrates an initial 10-year mine life with average
annual gold production of approximately 100,000 ounces of gold
following ramp up. The PEA represents a preliminary point-in-time
estimate of the mine plan.
Underground access will be through twin portals located in the
north wall of the Archimedes Pit adjacent to the pit haulage ramp.
The main decline will provide personnel and equipment access to all
areas of the mine and will be wide enough to accommodate 30-ton
haul trucks.
Long hole open stoping ("LHOS") with delayed backfill is the
primary mining method planned for Ruby Hill. Drift and fill mining
can be implemented when the mineralization geometry does not have
sufficient vertical extent to allow LHOS, sill mining, or where
ground conditions will not maintain vertical stope walls. Underhand
drift and fill mining is preferred since the backfill quality will
be better than the rock quality.
While a small component of the upper levels of the 426 zone
contains oxide mineralization, metallurgical testing has
demonstrated that both the 426 and Ruby
Deep zones of the Archimedes Underground are generally
single refractory and require an oxidation process to increase gold
extraction using whole cyanidation of mineralized material.
Additionally, testing has demonstrated that the gold recovery for
both deposits is materially higher when an autoclave is operated in
the acidic environment.
The PEA incorporates toll-milling arrangements with associated
over-the-road trucking costs for the years 2026 and 2027. Starting
in 2028, the processing costs and recoveries associated with
hauling to and processing at the Lone Tree autoclave in the acidic
environment have been incorporated into the PEA. Processing
materials in the acidic environment increases per tonne processing
costs by approximately $35; however,
the additional cost is offset by higher recovery rates. The oxide
mineralization from the 426 zone will be processed via heap leach
at the existing Complex leach pad, with the associated recoveries
applied. A LOM processing schedule is illustrated in Figure 4.
Capital Cost Summary
Mine construction capital is estimated to be $49 million.
Archimedes benefits from the extensive facilities and
infrastructure that remains from the Archimedes Pit. The majority
of the capital budget, including mine construction and sustaining,
is associated with mine development. Construction of the
underground portals and associated near portal facilities is
budgeted at $8.6 million. These
activities are currently underway in preparation for commencement
of underground development early in the second quarter of 2025.
Archimedes is expected to generate an estimated $212 million in after-tax cash flow over the
current 10-year mine life (see Figure 5).
Table 4: Capital Cost Estimates
|
Mine
Construction
|
Sustaining
|
($M)
|
($M)
|
Environmental,
Permitting and Technical
|
$2.5
|
$3.5
|
Dewatering
|
$0
|
$4.0
|
Mine
Development
|
$28.8
|
$71.2
|
Mine Facilities &
Overhead
|
$8.6
|
$4.1
|
Resource Conversion
Drilling
|
$2.1
|
$8.5
|
Contingency
(15% Drilling and Development; 25% Facilities)
|
$7.4
|
$14.8
|
Total Capital
Cost
|
$49.4
|
$106.1
|
Operating Cost Summary
The PEA estimates cash costs(1) of $1,769 per ounce of gold and all-in sustaining
costs(1) of $1,893 per
ounce of gold for the LOM (see Table 5). Cash and all-in-sustaining
costs include a non-cash capital toll milling charge through the
Company's Lone Tree autoclave of $21
per tonne or approximately $100 per
ounce of gold. Figure 6 illustrates these operating costs over
Archimedes' estimated production profile.
Table 5: Total and Unit Operating Costs
|
Total
Costs
|
Unit
Cost
|
Cost per
Ounce
|
($M)
|
($/t
milled)
|
($/oz
Au)
|
Mining
|
$750.0
|
$164.2
|
$808
|
Transportation &
Processing
|
$682.2
|
$149.4
|
$735
|
G&A, Royalties
& Net Proceeds Tax
|
$210.4
|
$46.1
|
$227
|
By-Product
Credits
|
($0.7)
|
($0.1)
|
($1)
|
Total Operating
Cost/Cash Costs(1)
|
$1,642.0
|
$359.5
|
$1,769
|
Closure &
Reclamation
|
$8.9
|
$1.9
|
$10
|
Sustaining
Capital
|
$106.1
|
$23.2
|
$114
|
All-in Sustaining
Costs(1)
|
$1,757.0
|
$384.7
|
$1,893
|
Table 6: Development Cost Per Foot (Excluding 15%
Contingency)
|
Total
Development
|
Cost
|
(feet)
|
($/foot)
|
Primary Capital
Drifting
|
25,640
|
$2,000
|
Secondary Capital
Drifting
|
21,245
|
$2,000
|
Capital
Raising
|
1,548
|
$4,000
|
Total/Weighted
Average
|
48,434
|
$2,064
|
Permitting
The phased permitting process at Archimedes is well underway,
allowing for simultaneous mining while permitting for the next
phase progresses. The initial phase covers mining activities above
the 5100-foot elevation, a threshold consistent with previously
approved permits for open pit mining at Ruby Hill. The first phase
of permitting is nearing completion and once finalized, will allow
for mining through June 2027.
The second phase of permitting covers mining below the 5100-foot
elevation and is set to begin immediately upon receipt of the first
phase of permits. This phase is scheduled for completion by the end
of the second quarter 2027, with the objective of ensuring
uninterrupted mining at the Project.
National Environmental Policy Act ("NEPA") associated permitting
activities continue to progress. Amended Plan of Operations and
Environmental Assessment documents have been provided to the Bureau
of Land Management ("BLM") with the next step being completion of
the Decision Record (DR). Nevada
Division of Environmental Protection ("NDEP") permitting
activities are also progressing, focusing on the site's Water
Pollution Control Permits. Both the NEPA and NDEP permits are
expected at the end of the first quarter of 2025.
Next Steps to Feasibility Study
A feasibility study in accordance with National Instrument
43-101 - Standards of Disclosure for Mineral Projects ("NI
43-101") and Subpart 1300 of Regulation S-K ("S-K 1300")
with an updated mineral resource estimate is expected to be
completed in 2028. The updated resource is expected to include
50,000 meters of drilling targeting the 426 zone and the Ruby
Deeps. Below is a summary of additional work to be conducted.
Resource Delineation and Exploration
- Begin resource conversion drilling as decline advances and
drill platforms become available. Incorporate this data into an
updated resource model.
Permitting
- Complete the NEPA and NDEP permitting amendments for mining
below the 5100 foot elevation.
Metallurgical Testing
Additional metallurgical testing is required from the initial
Ruby Hill production areas to confirm metallurgical recoveries with
Lone Tree autoclave process conditions. Sample selection will be
based on available mine production plans to reflect typical stope
dimensions and expected dilution. Testing will include:
- Comminution testing to confirm throughput through the Lone Tree
mill.
- Additional pressure oxidation tests using both alkaline and
acidic pressure oxidation conditions for the Lone Tree
autoclave.
- Carbon-in-leach tests on
pressure oxidation productions.
Technical Disclosure and Qualified Persons
The PEA was prepared in accordance with NI 43-101. The full PEA
will be filed within 45 days under the Company's issuer profile on
SEDAR+ at www.sedarplus.ca and on i-80 Gold's profile. An Initial
Assessment for the Archimedes Underground Project ("S-K 1300
Report") was also prepared in accordance with S-K 1300 and Item 601
of the Regulation S-K and the S-K 1300 Report will be filed on
EDGAR at www.sec.gov. Both reports will be available on the
Company's website at www.i80gold.com. The mineral estimates and
project economics are the same under the PEA and the S-K 1300
Report.
The technical information contained in this press release has
been prepared under the supervision of, and has been reviewed and
approved by Dagny Odell, P.E., (SME No. 2402150) Practical Mining
LLC, and Tyler Hill CPG., Vice President Geology for the Company,
who are all qualified persons within the meaning of NI 43-101 and
S-K 1300.
For a description of the data verification, assay procedures and
the quality assurance program and quality control measures applied
by the Company, please see the Company's Annual Information Form
dated March 12, 2024 filed under the
Company's profile on SEDAR+ at www.sedarplus.ca and filed with the
Company's Form 40-F under the Company's profile on EDGAR at
www.sec.gov. Further information about the PEA referenced in this
news release, including information in respect of data
verification, key assumptions, parameters, risks and other factors,
will be contained in the PEA.
The PEA is preliminary in nature and includes an economic
analysis that is based, in part, on inferred mineral resources.
Inferred mineral resources that are considered too speculative
geologically to have for the application of economic considerations
applied to them that would enable them to be categorized as mineral
reserves, and there is no certainty that the results of the PEA
will be realized. Mineral resources do not have demonstrated
economic viability and are not mineral reserves.
Endnotes
- This is a non-IFRS/non-GAAP measure. Please see both
sections titled "Non-IFRS Performance Measures/Non-GAAP Financial
Performance Measures" below.
- Cash flow and NPV are calculated as of the start of
construction, which is anticipated to commence in early in the
second quarter 2025, subject to obtaining the necessary permits by
March 31, 2025, as anticipated.
- After tax metrics assume the Company consumes existing net
operating losses sufficient to offset all tax liabilities.
About i-80 Gold Corp.
i-80 Gold Corp. is a Nevada-focused mining company with
the fourth largest gold mineral resources in the state of Nevada.
The recapitalization plan underway is designed to unlock the value
of the Company's high-grade gold deposits to create a Nevada
mid-tier gold producer. i-80 Gold's common shares are listed on the
TSX and the NYSE American under the trading symbol IAU:TSX and
IAUX:NYSE. Further information about i-80 Gold's portfolio of
assets and long-term growth strategy is available at
www.i80gold.com or by email at info@i80gold.com.
Forward-Looking Information
Certain statements in this release constitute "forward-looking
statements" or "forward-looking information" within the meaning of
applicable securities laws, including but not limited to,
statements regarding the updated results of the PEA on the Project,
such as future estimates of internal rates of return, net present
value, future production, estimates of cash cost, proposed mining
plans and methods, mine life estimates, cash flow forecasts, metal
recoveries, estimates of capital and operating costs, timing for
permitting and environmental assessments, timing, completion and
results of feasibility studies, and the size and timing of phased
development of the Project. Furthermore, forward-looking statements
are necessarily based upon a number of estimates and assumptions
that, while considered reasonable by the Company as of the date of
such statements, are inherently subject to significant business,
economic and competitive uncertainties and contingencies. With
respect to this specific forward-looking information concerning the
development of the Project, the Company has based its assumptions
and analysis on certain factors that are inherently uncertain.
Uncertainties include: (i) the adequacy of infrastructure; (ii)
geological characteristics; (iii) metallurgical characteristics of
the mineralization; (iv) the ability to develop adequate
processing capacity; (v) the price of gold, silver and other
commodities; (vi) the availability of equipment and facilities
necessary to complete development; (vii) the cost of consumables
and mining and processing equipment; (viii) unforeseen
technological and engineering problems; (ix) natural disasters
and/or accidents; * currency fluctuations; (xi) changes in
regulations; (xii) the compliance by and/or key suppliers with
terms of agreements; (xiii) the availability and productivity of
skilled labour; (xiv) the regulation of the mining industry by
various governmental agencies, including permitting and
environmental assessments; (xv) the ability to raise sufficient
capital to develop such projects; (xiv) changes in project scope or
design; and (xv) political factors.
Such statements can be identified by the use of words such as
"may", "would", "could", "will", "intend", "expect", "believe",
"plan", "anticipate", "estimate", "scheduled", "forecast",
"predict" and other similar terminology, or state that certain
actions, events or results "may", "could", "would", "might" or
"will" be taken, occur or be achieved. These statements reflect the
Company's current expectations regarding future events, performance
and results and speak only as of the date of this release and are
expressly qualified in their entirety by this cautionary statement.
Subject to applicable securities laws, the Company does not assume
any obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after
the date of this release.
This release also contains references to estimates of mineral
resources. The estimation of mineral resources is inherently
uncertain and involves subjective judgments about many relevant
factors. Mineral resources that are not mineral reserves do not
have demonstrated economic viability. The accuracy of any such
estimates is a function of the quantity and quality of available
data, and of the assumptions made and judgments used in engineering
and geological interpretation (including estimated future
production from the Project, the anticipated tonnages and grades
that will be mined and the estimated level of recovery that will be
realized), which may prove to be unreliable and depend, to a
certain extent, upon the analysis of drilling results and
statistical inferences that may ultimately prove to be inaccurate.
Mineral resource estimates may have to be re-estimated based on:
(i) fluctuations in commodities prices; (ii) results of drilling,
(iii) metallurgical testing and other studies; (iv) proposed mining
operations, including dilution; (v) the evaluation of mine plans
subsequent to the date of any estimates; and (vi) the possible
failure to receive required permits, approvals and licenses or
changes to existing mining licenses.
Forward-looking statements and information involve significant
known and unknown risks and uncertainties, should not be read as
guarantees of future performance or results and will not
necessarily be accurate indicators of whether or not such results
will be achieved. A number of factors could cause actual results to
differ materially from the results expressed or implied by such
forward-looking statements or information, including, but not
limited to: the Company's ability to finance the development of its
mineral properties; assumptions and discount rates being
appropriately applied to the PEA and S-K 1300 Report, uncertainty
as to whether there will ever be production at the Company's
mineral exploration and development properties; risks related to
the Company's ability to commence production at the Project and
generate material revenues or obtain adequate financing for its
planned exploration and development activities; uncertainties
relating to the assumptions underlying resource and reserve
estimates; mining and development risks, including risks related to
infrastructure, accidents, equipment breakdowns, labour disputes,
bad weather, non-compliance with environmental and permit
requirements or other unanticipated difficulties with or
interruptions in development, construction or production; the
geology, grade and continuity of the Company's mineral deposits;
the uncertainties involving success of exploration, development and
mining activities; permitting timelines; government regulation of
mining operations; environmental risks; unanticipated reclamation
expenses; prices for energy inputs, labour, materials, supplies and
services; uncertainties involved in the interpretation of drilling
results and geological tests and the estimation of reserves and
resources; unexpected cost increases in estimated capital and
operating costs; the need to obtain permits and government
approvals; material adverse changes, unexpected changes in laws,
rules or regulations, or their enforcement by applicable
authorities; the failure of parties to contracts with the company
to perform as agreed; social or labour unrest; changes in commodity
prices; and the failure of exploration programs or studies to
deliver anticipated results or results that would justify and
support continued exploration, studies, development or
operations. For a more detailed discussion of such risks and
other factors that could cause actual results to differ materially
from those expressed or implied by such forward-looking statements,
refer to i-80 Gold's filings with Canadian securities regulators,
including the most recent Annual Information Form, available on
SEDAR+ at www.sedarplus.ca.
Non-IFRS/Non-GAAP Financial Performance Measures
The Company has included certain terms or performance measures
in this news release that commonly used in the gold mining industry
that are not defined under International Financial Reporting
Standards ("IFRS") or United States Generally Accepted Accounting
Principles ("US GAAP"). This includes: all-in sustaining costs per
ounce and cash cost per ounce. Non-IFRS/Non-GAAP financial
performance measures do not have any standardized meaning
prescribed under IFRS or US GAAP, and therefore, they may not be
comparable to similar measures employed by other companies. The
data presented is intended to provide additional information and
should not be considered in isolation or as a substitute for
measures prepared in accordance with IFRS US GAAP and should be
read in conjunction with the Company's financial statements.
Because the Company has provided these measures on a
forward-looking basis, it is unable to present a quantitative
reconciliation to the most directly comparable financial measure
calculated and presented in accordance with IFRS or US GAAP without
unreasonable efforts. This is due to the inherent difficulty of
forecasting the timing or amount of various reconciling items that
would impact the most directly comparable forward-looking IFRS or
US GAAP measure that have not yet occurred, are outside of the
Company's control and/or cannot be reasonably predicted.
Definitions
"All-in sustaining costs" is a non-IFRS or US GAAP financial
measure calculated based on guidance published by the World Gold
Council ("WGC"). The WGC is a market development organization for
the gold industry and is an association whose membership comprises
leading gold mining companies. Although the WGC is not a mining
industry regulatory organization, it worked closely with its member
companies to develop these metrics. Adoption of the all-in
sustaining cost metric is voluntary and not necessarily standard,
and therefore, this measure presented by the Company may not be
comparable to similar measures presented by other issuers. The
Company believes that the all-in sustaining cost measure
complements existing measures and ratios reported by the Company.
All-in sustaining cost includes both operating and capital costs
required to sustain gold production on an ongoing basis. Sustaining
operating costs represent expenditures expected to be incurred at
the Project that are considered necessary to maintain production.
Sustaining capital represents expected capital expenditures
comprising mine development costs, including capitalized waste, and
ongoing replacement of mine equipment and other capital facilities,
and does not include expected capital expenditures for major growth
projects or enhancement capital for significant infrastructure
improvements.
"Cash cost per gold ounce" is a common financial performance
measure in the gold mining industry but has no standard meaning
under IFRS or US GAAP. The Company believes that, in addition to
conventional measures prepared in accordance with IFRS or US GAAP,
certain investors use this information to evaluate the Company's
performance and ability to generate cash flow. Cash cost figures
are calculated in accordance with a standard developed by The Gold
Institute. The Gold Institute ceased operations in 2002, but the
standard is considered the accepted standard of reporting cash cost
of production in North America. Adoption of the standard is
voluntary, and the cost measures presented may not be comparable to
other similarly titled measures of other companies.
For a more detailed breakdown on how these measures were
calculated, please see the table below:
|
Total
Costs
|
Unit
Cost
|
Cost per
Ounce
|
($M)
|
($/t
milled)
|
($/oz
Au)
|
Mining
|
$750.0
|
$164.2
|
$808
|
Transportation &
Processing
|
$682.2
|
$149.4
|
$735
|
G&A, Royalties
& Net Proceeds Tax
|
$210.4
|
$46.1
|
$227
|
By-Product
Credits
|
($0.7)
|
($0.1)
|
($1)
|
Total Operating
Cost/Cash Cost(1)
|
$1,642.0
|
$359.5
|
$1,769
|
Closure &
Reclamation
|
$8.9
|
$1.9
|
$10
|
Sustaining
Capital
|
$106.1
|
$23.2
|
$114
|
All-in Sustaining
Costs(1)
|
$1,757.0
|
$384.7
|
$1,893
|
APPENDIX
Archimedes Underground Project Detailed Cash Flow
Model
All amounts are in United
States dollars, unless otherwise stated.
Archimedes
Underground
|
UNITS
|
TOTAL
LOM
|
2025
|
2026
|
2027
|
2028
|
2029
|
2030
|
2031
|
2032
|
2033
|
2034
|
2035
|
2036
|
2037
|
2038
|
2039
|
2040
+1
|
|
MINING
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mine Life
|
Years
|
~10
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mineralized Material
Mined
(incl. marginal)
|
k tonnes
|
4,567
|
-
|
41.8
|
258.6
|
473.1
|
572.9
|
533.5
|
558.8
|
561.4
|
573.1
|
569.4
|
400.0
|
24.2
|
-
|
-
|
-
|
-
|
|
Waste Moved
|
k tonnes
|
1,354
|
-
|
11.6
|
96.4
|
160.6
|
193.9
|
265.0
|
123.6
|
255.0
|
84.6
|
106.0
|
54.1
|
2.9
|
-
|
-
|
-
|
-
|
|
Total Moved
|
k tonnes
|
5,921
|
-
|
53.4
|
355.0
|
633.7
|
766.8
|
798.5
|
682.4
|
816.4
|
657.7
|
675.4
|
454.2
|
27.1
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Daily Mining
Rate
|
tpd
|
782
|
-
|
114.5
|
708.6
|
1,296.1
|
1,569.7
|
1,461.6
|
1,531.0
|
1,538.1
|
1,570.0
|
1,560.0
|
1,096.0
|
66.4
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Backfill
Placed
|
k tonnes
|
3,488
|
-
|
32.0
|
148.9
|
380.2
|
460.1
|
479.1
|
409.4
|
489.9
|
394.6
|
405.3
|
272.5
|
16.3
|
-
|
-
|
-
|
-
|
|
Capitalized
Mining
|
k tonnes
|
867
|
47.5
|
194.2
|
100.5
|
223.9
|
201.1
|
21.6
|
31.6
|
24.5
|
21.9
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROCESSING
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Material for
Processing
|
k tonnes
|
4,567
|
|
42
|
259
|
473
|
573
|
533
|
559
|
561
|
573
|
569
|
400
|
24
|
-
|
-
|
-
|
-
|
|
Gold Average
Grade
|
g/t Au
|
7.0
|
|
6.60
|
6.70
|
6.79
|
6.92
|
7.22
|
6.89
|
6.75
|
7.35
|
7.48
|
6.90
|
7.01
|
-
|
-
|
-
|
-
|
|
Contained
Gold
|
'000 oz Au
|
1,031
|
|
8.9
|
55.7
|
103.3
|
127.4
|
123.9
|
123.8
|
121.8
|
135.3
|
137.0
|
88.7
|
5.5
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Heap Leach
Processing
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Tonnes
Processed
|
k tonnes
|
171
|
|
15
|
56
|
75
|
25
|
1
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Gold Grade
|
g/t Au
|
3.82
|
|
4.02
|
3.63
|
3.76
|
4.35
|
2.30
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Silver
Grade
|
g/t Ag
|
0.52
|
|
0.45
|
0.47
|
0.55
|
0.59
|
1.79
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Contained
Gold
|
'000 oz Au
|
21.0
|
|
2.0
|
6.5
|
9.0
|
3.5
|
0.0
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Contained
Silver
|
'000 oz Ag
|
2.9
|
|
0.2
|
0.8
|
1.3
|
0.5
|
0.0
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Gold Average
Recovery
|
%
|
87 %
|
|
87 %
|
87 %
|
87 %
|
87 %
|
87 %
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Silver Average
Recovery
|
%
|
15 %
|
|
15 %
|
15 %
|
15 %
|
15 %
|
15 %
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Recovered
Gold
|
'000 oz Au
|
18
|
|
1.7
|
5.7
|
7.9
|
3.0
|
0.0
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Recovered
Silver
|
'000 oz Ag
|
0.4
|
|
0.0
|
0.1
|
0.2
|
0.1
|
0.0
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Autoclave
Processing
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Tonnes
Processed
|
k tonnes
|
4,166
|
|
|
|
398
|
548
|
533
|
559
|
561
|
573
|
569
|
400
|
24
|
-
|
-
|
-
|
-
|
|
Gold Grade
|
g/t Au
|
7.12
|
|
|
|
7.36
|
7.03
|
7.23
|
6.89
|
6.75
|
7.35
|
7.48
|
6.90
|
7.01
|
-
|
-
|
-
|
-
|
|
Silver
Grade
|
g/t Ag
|
1.72
|
|
|
|
0.77
|
0.96
|
1.23
|
2.15
|
2.21
|
2.34
|
2.07
|
1.68
|
1.58
|
-
|
-
|
-
|
-
|
|
Contained
Gold
|
'000 oz Au
|
954
|
|
|
|
94.3
|
123.9
|
123.8
|
123.8
|
121.8
|
135.3
|
137.0
|
88.7
|
5.5
|
-
|
-
|
-
|
-
|
|
Contained
Silver
|
'000 oz Ag
|
230
|
|
|
|
9.8
|
17.0
|
21.1
|
38.6
|
39.9
|
43.2
|
37.8
|
21.7
|
1.2
|
-
|
-
|
-
|
-
|
|
Gold Average
Recovery
|
%
|
90 %
|
|
|
|
90 %
|
90 %
|
90 %
|
90 %
|
90 %
|
90 %
|
90 %
|
90 %
|
90 %
|
-
|
-
|
-
|
-
|
|
Silver Average
Recovery
|
%
|
10 %
|
|
|
|
10 %
|
10 %
|
10 %
|
10 %
|
10 %
|
10 %
|
10 %
|
10 %
|
10 %
|
-
|
-
|
-
|
-
|
|
Recovered
Gold
|
'000 oz Au
|
877
|
|
|
|
89.2
|
116.8
|
119.4
|
114.5
|
109.0
|
121.1
|
122.6
|
79.4
|
4.9
|
-
|
-
|
-
|
-
|
|
Recovered
Silver
|
'000 oz Ag
|
23
|
|
|
|
1.0
|
1.7
|
2.1
|
3.9
|
4.0
|
4.3
|
3.8
|
2.2
|
0.1
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Toll Mill
Processing
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Tonnes
Processed
|
k tonnes
|
230
|
|
26
|
203
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gold Grade
|
g/t Au
|
7.61
|
|
8.10
|
7.55
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Silver
Grade
|
g/t Ag
|
1.20
|
|
1.39
|
1.17
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contained
Gold
|
'000 oz Au
|
56
|
|
6.9
|
49.3
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Contained
Silver
|
'000 oz Ag
|
8.8
|
|
1.2
|
7.6
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Gold Average
Recovery
|
%
|
58 %
|
|
58 %
|
58 %
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Silver Average
Recovery
|
%
|
10 %
|
|
10 %
|
10 %
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Recovered
Gold
|
'000 oz Au
|
33
|
|
4.0
|
28.6
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Recovered
Silver
|
'000 oz Ag
|
1
|
|
0.1
|
0.8
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Tonnes
Processed
|
k tonnes
|
4,567
|
|
41.8
|
258.6
|
473.1
|
572.9
|
533.5
|
558.8
|
561.4
|
573.1
|
569.4
|
400.0
|
24.2
|
-
|
-
|
-
|
-
|
|
Total Gold
Production
|
'000 oz Au
|
928
|
|
5.7
|
34.2
|
97.1
|
119.8
|
119.5
|
114.5
|
109.0
|
121.1
|
122.6
|
79.4
|
4.9
|
-
|
-
|
-
|
-
|
|
Total Silver
Production
|
'000 oz Ag
|
24
|
|
0.2
|
0.9
|
1.2
|
1.8
|
2.1
|
3.9
|
4.0
|
4.3
|
3.8
|
2.2
|
0.1
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVENUE
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gold Price
|
$/oz Au
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
|
Silver
Price
|
$/oz Ag
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
|
Revenues
|
$M
|
$2,019
|
-
|
$12
|
$74
|
$211
|
$261
|
$260
|
$249
|
$237
|
$264
|
$267
|
$173
|
$11
|
-
|
-
|
-
|
-
|
|
OPERATING
COSTS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mining Costs
(Mineralized Material incl. Backfill)
|
$M
|
$594
|
-
|
$5.5
|
$32.4
|
$62.4
|
$76.0
|
$73.3
|
$72.1
|
$74.7
|
$71.8
|
$72.3
|
$51.0
|
$3.0
|
-
|
-
|
-
|
-
|
|
Mining Costs
(Waste)
|
$M
|
$156
|
-
|
$1.4
|
$11.4
|
$18.5
|
$22.3
|
$30.8
|
$14.4
|
$28.8
|
$9.7
|
$11.9
|
$6.0
|
$0.3
|
-
|
-
|
-
|
-
|
|
Heap Leach
Processing
|
$M
|
$1.2
|
-
|
$0.1
|
$0.4
|
$0.5
|
$0.2
|
$0.0
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Processing
Autoclave
|
$M
|
$489
|
-
|
-
|
-
|
$46.8
|
$64.3
|
$62.5
|
$65.6
|
$65.9
|
$67.2
|
$66.8
|
$46.9
|
$2.8
|
-
|
-
|
-
|
-
|
|
Transportation
|
$M
|
$192
|
-
|
$1.4
|
$10.9
|
$17.2
|
$23.7
|
$23.0
|
$24.1
|
$24.2
|
$24.7
|
$24.6
|
$17.3
|
$1.0
|
-
|
-
|
-
|
-
|
|
Electrical
Power
|
$M
|
$29
|
-
|
$0.6
|
$1.5
|
$2.9
|
$3.4
|
$3.7
|
$4.0
|
$3.4
|
$2.6
|
$2.6
|
$2.5
|
$2.3
|
-
|
-
|
-
|
-
|
|
G&A
|
$M
|
$79
|
-
|
$3.9
|
$7.5
|
$7.5
|
$7.5
|
$7.5
|
$7.5
|
$7.5
|
$7.5
|
$7.5
|
$7.5
|
$7.5
|
-
|
-
|
-
|
-
|
|
Total Operating
Cost
|
$M
|
$1,541
|
-
|
$12.9
|
$64.1
|
$155.9
|
$197.4
|
$200.8
|
$187.7
|
$204.4
|
$183.6
|
$185.7
|
$131.2
|
$17.1
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Refining &
Sales
|
$M
|
$1.7
|
-
|
$0.0
|
$0.1
|
$0.2
|
$0.2
|
$0.2
|
$0.2
|
$0.2
|
$0.2
|
$0.2
|
$0.1
|
$0.0
|
-
|
-
|
-
|
-
|
|
Royalties & State
Taxes
|
$M
|
$100.2
|
-
|
$0.4
|
$3.0
|
$10.8
|
$13.1
|
$12.8
|
$12.5
|
$10.6
|
$14.0
|
$14.2
|
$8.5
|
$0.3
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mining Costs
(Mineralized Material)
|
$/t mined
|
$130.2
|
-
|
$132
|
$125
|
$132
|
$133
|
$137
|
$129
|
$133
|
$125
|
$127
|
$127
|
$126
|
-
|
-
|
-
|
-
|
|
Mining Costs
(Waste)
|
$/t mined
|
$114.9
|
-
|
$119
|
$119
|
$115
|
$115
|
$116
|
$116
|
$113
|
$115
|
$113
|
$111
|
$110
|
-
|
-
|
-
|
-
|
|
Mining Costs
(Mineralized material & Waste )
|
$/t mined
|
$126.7
|
-
|
$129
|
$123
|
$128
|
$128
|
$130
|
$127
|
$127
|
$124
|
$125
|
$125
|
$124
|
|
|
|
|
|
Processing
(Heap leach)
|
$/t milled
|
$6.8
|
-
|
$7
|
$6
|
$7
|
$8
|
$5
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Processing
(Autoclave)
|
$/t milled
|
$117.3
|
-
|
-
|
-
|
$117
|
$117
|
$117
|
$117
|
$117
|
$117
|
$117
|
$117
|
$117
|
-
|
-
|
-
|
-
|
|
Transportation
|
$/t milled
|
$42.1
|
-
|
$34
|
$42
|
$36
|
$41
|
$43
|
$43
|
$43
|
$43
|
$43
|
$43
|
$43
|
-
|
-
|
-
|
-
|
|
Electrical
Power
|
$/t milled
|
$6.4
|
-
|
$14
|
$6
|
$6
|
$6
|
$7
|
$7
|
$6
|
$5
|
$5
|
$6
|
$97
|
-
|
-
|
-
|
-
|
|
G&A
|
$/t milled
|
$17.3
|
-
|
$94
|
$29
|
$16
|
$13
|
$14
|
$13
|
$13
|
$13
|
$13
|
$19
|
$310
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total
|
$/t milled
|
$337.4
|
-
|
$309
|
$248
|
$329
|
$345
|
$376
|
$336
|
$364
|
$320
|
$326
|
$328
|
$707
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CAPITAL
EXPENDITURES
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Construction
Capital
|
$M
|
$47.3
|
$16.5
|
$30.8
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Definition &
Conversion Drilling(1)
|
$M
|
$10.6
|
$2.1
|
-
|
$8.5
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Sustaining
Capital
|
$M
|
$97.6
|
-
|
-
|
$22.5
|
$33.7
|
$26.0
|
$4.0
|
$5.2
|
$3.5
|
$2.8
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Total
Capital
|
$M
|
$155.5
|
$18.6
|
$30.8
|
$31.0
|
$33.7
|
$26.0
|
$4.0
|
$5.2
|
$3.5
|
$2.8
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Reclamation(2)
|
$M
|
$8.9
|
$0.4
|
$0.4
|
$0.4
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.6
|
$0.6
|
$0.6
|
$0.6
|
$1.8
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CASH COSTS &
AISC
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Cash Costs
(Incl. Royalty)
|
$/oz
|
$1,769
|
-
|
$2,321
|
$1,961
|
$1,718
|
$1,758
|
$1,789
|
$1,749
|
$1,973
|
$1,632
|
$1,631
|
$1,760
|
$3,569
|
-
|
-
|
-
|
-
|
|
All-in Sustaining
Costs(2)
|
$/oz
|
$1,893
|
-
|
$2,385
|
$2,877
|
$2,070
|
$1,979
|
$1,826
|
$1,798
|
$2,009
|
$1,659
|
$1,635
|
$1,766
|
$3,685
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CASH FLOW
ANALYSIS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revenue
|
$M
|
$2,018.9
|
-
|
$12
|
$74
|
$211
|
$261
|
$260
|
$249
|
$237
|
$264
|
$267
|
$173
|
$11
|
-
|
-
|
-
|
-
|
|
Operating Costs Gold
and Royalties
|
$M
|
($1,642.6)
|
-
|
($13)
|
($67)
|
($167)
|
($211)
|
($214)
|
($200)
|
($215)
|
($198)
|
($200)
|
($140)
|
($17)
|
-
|
-
|
-
|
-
|
|
Reclamation
Accrual
|
$M
|
($8.9)
|
-
|
($0.1)
|
($0.3)
|
($0.9)
|
($1.1)
|
($1.1)
|
($1.1)
|
($1.0)
|
($1.2)
|
($1.2)
|
($0.8)
|
($0.0)
|
-
|
-
|
-
|
-
|
|
Depreciation
|
$M
|
($270.0)
|
-
|
($1)
|
($7)
|
($24)
|
($34)
|
($34)
|
($34)
|
($33)
|
($38)
|
($38)
|
($25)
|
($2)
|
-
|
-
|
-
|
-
|
|
Net Operating Income
(Pre-Tax)
|
$M
|
$97.4
|
-
|
($2)
|
($0)
|
$19
|
$15
|
$11
|
$14
|
($12)
|
$27
|
$27
|
$7
|
($8)
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Income
Taxes
|
$M
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Net
Income
|
$M
|
$97.4
|
-
|
($2)
|
($0)
|
$19
|
$15
|
$11
|
$14
|
($12)
|
$27
|
$27
|
$7
|
($8)
|
-
|
-
|
-
|
-
|
|
Depreciation
|
$M
|
$270.0
|
-
|
$1.0
|
$7.2
|
$24.1
|
$33.7
|
$34.3
|
$33.9
|
$33.2
|
$37.9
|
$38.4
|
$24.8
|
$1.5
|
-
|
-
|
-
|
-
|
|
Reclamation
|
$M
|
$0.0
|
($0.4)
|
($0.3)
|
($0.0)
|
$0.5
|
$0.7
|
$0.7
|
$0.6
|
$0.6
|
$0.7
|
$0.7
|
$0.3
|
($0.5)
|
($0.6)
|
($0.6)
|
($0.6)
|
($1.8)
|
|
Working
Capital
|
$M
|
$0.0
|
-
|
($1.5)
|
($6.2)
|
($11.5)
|
($5.1)
|
($0.4)
|
$1.5
|
($1.7)
|
$2.0
|
($0.3)
|
$7.0
|
$14.1
|
$2.0
|
-
|
-
|
-
|
|
Operating Cash
Flow
|
$M
|
$367.4
|
($0)
|
($3)
|
$1
|
$32
|
$44
|
$45
|
$50
|
$20
|
$67
|
$66
|
$39
|
$7
|
$1
|
($1)
|
($1)
|
($2)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capital
Expenditures
|
$M
|
($155.5)
|
($19)
|
($31)
|
($31)
|
($34)
|
($26)
|
($4)
|
($5)
|
($3)
|
($3)
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
NET CASH
FLOW
|
$M
|
$211.9
|
($19)
|
($34)
|
($30)
|
($1)
|
$18
|
$41
|
$45
|
$16
|
$65
|
$66
|
$39
|
$7
|
$1
|
($1)
|
($1)
|
($2)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROJECT
ECONOMICS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
After-tax NPV 5%
Discounting
|
$M
|
|
$127
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
23 %
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Notes to table
above:
(1) A portion of the
drilling capital ($2.1M) is included in construction capital, while
the remaining $8.5M is classified as sustaining capital.
(2) The annual
calculation for all-in sustaining costs include reclamation costs
on a cash basis rather than on an accrual basis. As such, the
weighted average of the annual all-in sustaining costs amounts will
not agree to the life of mine all-in sustaining costs.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|

View original content to download
multimedia:https://www.prnewswire.com/news-releases/i-80-gold-announces-positive-preliminary-economic-assessment-on-the-archimedes-underground-project-nevada-after-tax-npv5-of-127-million-with-an-after-tax-irr-of-23-at-us2-175oz-au-302378734.html
SOURCE i-80 Gold Corp