Cheniere Achieves First LNG at the Corpus Christi Stage 3 Project
30 Décembre 2024 - 2:05PM
Business Wire
Cheniere Energy, Inc. (“Cheniere” or the “Company”) (NYSE: LNG)
today announced that liquefied natural gas (“LNG”) was produced for
the first time from the first train (“Train 1”) of the Company’s
Corpus Christi Stage 3 Liquefaction Project (“CCL Stage 3”). The
commissioning process continues, and Cheniere expects substantial
completion of Train 1 to be achieved at the end of the first
quarter of 2025, over six months ahead of the guaranteed completion
date. Upon substantial completion, Bechtel Energy, Inc. (“Bechtel”)
will transfer care, custody and control of the completed train to
Cheniere.
Full notice to proceed on CCL Stage 3 was issued to Bechtel by
Cheniere in June 2022. CCL Stage 3 consists of seven midscale
trains, with an expected total production capacity of over 10
million tonnes per annum (“mtpa”) of LNG. As of November 30, 2024,
overall project completion for CCL Stage 3 was 75.9%, which
reflects engineering 96.8% complete, procurement 97.2% complete,
subcontract work 87.7% complete and construction 39.2% complete.
Upon substantial completion of all seven trains of CCL Stage 3, the
expected total production capacity of the Corpus Christi
liquefaction facility will be over 25 mtpa of LNG.
About Cheniere
Cheniere Energy, Inc. is the leading producer and exporter of
LNG in the United States, reliably providing a clean, secure, and
affordable solution to the growing global need for natural gas.
Cheniere is a full-service LNG provider, with capabilities that
include gas procurement and transportation, liquefaction, vessel
chartering, and LNG delivery. Cheniere has one of the largest
liquefaction platforms in the world, consisting of the Sabine Pass
and Corpus Christi liquefaction facilities on the U.S. Gulf Coast,
with total production capacity of approximately 45 mtpa of LNG in
operation and an additional 10+ mtpa of expected production
capacity under construction. Cheniere is also pursuing liquefaction
expansion opportunities and other projects along the LNG value
chain. Cheniere is headquartered in Houston, Texas, and has
additional offices in London, Singapore, Beijing, Tokyo, and
Washington, D.C.
For additional information, please refer to the Cheniere website
at www.cheniere.com and Quarterly Report on Form 10-Q for the
quarter ended September 30, 2024, filed with the Securities and
Exchange Commission.
Forward-Looking Statements
This press release contains certain statements that may include
“forward-looking statements” within the meanings of Section 27A of
the Securities Act of 1933 and Section 21E of the Securities
Exchange Act of 1934. All statements, other than statements of
historical or present facts or conditions, included herein are
“forward-looking statements.” Included among “forward-looking
statements” are, among other things, (i) statements regarding
Cheniere’s financial and operational guidance, business strategy,
plans and objectives, including the development, construction and
operation of liquefaction facilities, (ii) statements regarding
regulatory authorization and approval expectations, (iii)
statements expressing beliefs and expectations regarding the
development of Cheniere’s LNG terminal and pipeline businesses,
including liquefaction facilities, (iv) statements regarding the
business operations and prospects of third-parties, (v) statements
regarding potential financing arrangements, (vi) statements
regarding future discussions and entry into contracts, (vii)
statements relating to Cheniere’s capital deployment, including
intent, ability, extent, and timing of capital expenditures, debt
repayment, dividends, share repurchases and execution on the
capital allocation plan and (viii) statements relating to our
goals, commitments and strategies in relation to environmental
matters. Although Cheniere believes that the expectations reflected
in these forward-looking statements are reasonable, they do involve
assumptions, risks and uncertainties, and these expectations may
prove to be incorrect. Cheniere’s actual results could differ
materially from those anticipated in these forward-looking
statements as a result of a variety of factors, including those
discussed in Cheniere’s periodic reports that are filed with and
available from the Securities and Exchange Commission. You should
not place undue reliance on these forward-looking statements, which
speak only as of the date of this press release. Other than as
required under the securities laws, Cheniere does not assume a duty
to update these forward-looking statements.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20241224723405/en/
Cheniere Energy, Inc. Investors Randy Bhatia 713-375-5479
Frances Smith 713-375-5753 Media Relations Eben Burnham-Snyder
713-375-5764 Bernardo Fallas 713-375-5593
Cheniere Energy (NYSE:LNG)
Graphique Historique de l'Action
De Déc 2024 à Jan 2025
Cheniere Energy (NYSE:LNG)
Graphique Historique de l'Action
De Jan 2024 à Jan 2025