Koryx Copper Inc. (“
Koryx” or the
"
Company") (TSX-V: KRY) is pleased to announce its
2025 exploration and project development strategy for its
wholly-owned, advanced-stage, large-scale and long-life open-pit
Haib Copper Project (“
Haib” or the
“
Project”) in southern Namibia.
This 2025 technical strategy comprises an
intensive drill and study program, including more than 55,000m of
growth and quality improvement drilling, aiming to increase the
size and grade of the Haib Mineral Resource Estimate
(“MRE”) as well as multiple technical,
environmental and metallurgical studies. This program will result
in an updated Preliminary Economic Assessment
(“PEA”) and Pre-Feasibility Study
(“PFS”) for Haib, both to be published before the
end of 2025.
This fast-tracked technical strategy of
drilling, study, infrastructure and permitting activities
represents a major step-change in the development of Haib and is
geared towards the rapid development of the Project to the
bankability stage, with major permitting and all technical studies
to be concluded by the end of 2026.
Heye Daun, Koryx Copper’s President and
CEO commented: "We are very excited to have ended 2024
with a strong treasury of more than C$17 million in cash, no
liabilities and a clean share structure. With new leadership and a
top-tier technical team in place, we have hit the ground running
and spent the latter part of 2024 preparing for and planning this
transformative work program, which is already underway at Haib.
As part of the 2025 work program, we are
planning to 1) execute the largest drill program at Haib since its
discovery, aiming to improve the grade and size of the mineral
resource whilst 2) proving the economic feasibility of a much
larger conventional flotation concentrate process as well as
subsequent heap leaching for the lower grade material.
This work program will for the first time bring
together all of the quality work that was completed historically
and combine it with the updated and much more detailed work which
Koryx is carrying out this year, thereby delivering an integrated
Haib project approach with much larger planned copper production
than was contemplated historically. Under this scope Haib will
produce both clean copper concentrate and refined copper cathodes.
Right-sizing and optimizing the Haib Project is what our 2025 work
program will achieve.
Owing to its low altitude (500m amsl), its
proximity to world-class infrastructure, and the very favorable
permitting and mining-friendly jurisdiction of Namibia, Haib has
the genuine potential to become a high quality, low-risk global
copper development project. Given our track record of execution and
value creation in mining in Namibia, in addition to our blue-chip
shareholder base, we believe we are perfectly placed to achieve
this during 2025 and beyond.”
The updated PEA is designed to replace the
outdated historical PEA from 2021 and to describe the scope of the
new Haib project, thereby serving as the basis for the mine
permitting process (described further down). This is to be followed
up with a Definitive Feasibility Study (“DFS”)
planned to be published before the end of 2026.
2025 Planning Objectives for Haib
Koryx’s vision is to turn Haib into Namibia’s
next major mine development. This will require high-class
leadership, drive, innovation and technical expertise, coupled with
significant funding. To achieve this, the Company is aiming to
fulfil the following key objectives during 2025:
- Reinforcing the team and
establishing the infrastructure to execute a large-scale,
multi-year drilling and technical study program. The program will
be completed by multiple local and international service providers
and overseen by Koryx’ own team of competent professionals, aiming
to right-size (grow) and optimize (improve quality) Haib and to
fast-track the completion of a PFS by the end of 2025, followed by
the completion of a DFS and mine permitting before the end of
2026.
- Significantly improve the quality
of the MRE by increasing the mineral resource size and copper
equivalent grade.
- Proving the techno-economic
feasibility of a conventional flotation concentrate process flow
sheet for the higher grade material, in parallel with an innovative
leaching process for the lower grade material.
- This includes integrating the mine
plan with the two parallel process flow sheets to maximize value
(LOM, NPV, annual copper production rate).
- De-risking and advancing the
environmental and mine permitting, infrastructure, utilities and
project delivery aspects of the Project.
Led by a highly competent and experienced team
who have worked together on Namibian projects for many years, with
a strong track record of execution and value creation, the Koryx
team is perfectly placed to successfully execute on these
objectives.
2025 Development Study
Approach
The PEA will describe an integrated and enhanced
process flowsheet for Haib, comprising flotation and concentrate
production for the higher-grade ROM material, and a
hydrometallurgical process including heap leaching and solvent
extraction / electrowinning (SX/EW) for the lower grade ROM
material.
As a part of the PEA, Koryx will evaluate
alternative metallurgical process flow sheets and carry out
infrastructure related trade-off studies. The Company is confident
that a high degree of confidence can be ascribed to the trade-off
studies as the input data will be based on actual test results
and/or benchmarked data from similar projects.
The PEA will be followed up immediately by a
PFS, aiming to right-size and optimize the project definition so
that the team can focus on engineering the unit processes and
infrastructure requirements which would generate the optimal
economic outcomes for Haib.
A key aspect of the 2025 PEA is right-sizing the
operation to optimise the life-of-mine (multi decade) whilst
maximizing copper production. Koryx is evaluating a processing
plant throughput operating range of 15 to 25mtpa crushed material
(run-of-mine). Applying industry average copper recovery factors,
the project could produce 50 – 100ktpa of copper (combination of
copper contained in concentrate and refined copper cathode) over a
life of mine of 15 – 30 years.
In developing a credible project implementation
plan, Koryx will consider a staged implementation model wherein the
conventional comminution and flotation processing facilities will
be constructed and operated as Stage 1, followed by construction
and operation of the leaching and hydrometallurgical facilities in
Stage 2.
Phase 2 Drilling (Q1 2025) and Mineral
Resource Planning for 2025
During 2024 the Company completed a small
(3,500m), but highly successful Phase 1 drill program at Haib. The
program specifically targeted higher grade, more structurally
controlled areas of the Haib mineralisation with inclined drilling,
which are not typical for a porphyry-type of deposit, and which had
been missed by Rio Tinto’s prior vertical drilling. These areas
were previously identified by Koryx geologists through extensive
fieldwork campaigns and were successfully traced through the 2024
Phase 1 drill program.
This 2024 drilling culminated in the publication
of a new MRE for Haib, reflecting a 13% increase in Cu grade (from
0.31 to 0.35% Cu, refer to the press release dated September 10,
2024), and was immediately followed up with a larger Phase 2 drill
program.
The objectives of the Phase 2 program are as
follows:
- Extending and further targeting the
structurally controlled, higher grade mineralisation which was
identified and drilled during the 2024 Phase 1 drill program.
- Drilling and assaying for
by-products, specifically molybdenum and gold, which both have the
potential to be recovered in the updated mineral processing
flowsheet now envisaged for Haib. The aim is to generate a
sufficient sample density to be able to reflect the byproducts in
the next MRE update, thereby assisting in further improving the
Haib Cu equivalent grade instead of reporting just a pure Cu grade
for the Haib mineralisation, as was done previously.
- Refining the geological model
wireframes and improving the resolution of waste, low grade and
high grade interfaces through in-fill drilling of the current 150m
x 150m drill grid.
The Phase 2 drill program which commenced in
November 2024 comprises 8,200m of which 3,550m was completed by the
end of 2024. The complete program is due to be completed during Q1
2025 with assay results to be reported throughout Q1 2025.
Phase 3 and 4 Drilling (Q2 and Q3
2025)
Planning for the follow-on Phase 3 drill program
(29,000m) has been completed and drilling will commence immediately
after the completion of the Phase 2 program late in Q1 2025. This
drilling has been planned to further extend the higher grade areas
(10,000m) plus infill and mineral resource extension drilling
(19,000m).
A further 20,000m of Phase 4 infill drilling
(reducing average drill spacing from 150m down to 75m) will be
required to convert at least 80% of the mineral resource to the
“Indicated” category. This drilling is expected to be completed
during Q3 of 2025, thereby allowing for inclusion into the planned
PFS to be published at the end of 2025. This will likely also
fulfil the minimum confidence level required for the follow-on DFS
study to be published at the end of 2026, although a significant
quantum of additional infill and expansion drilling will likely be
completed before then.
The increase in planned drill metres has
resulted in 3 additional rigs being mobilised to site in Q1 2025
and the Company expects to have 5 of the 6 rigs planned on site by
the end of February 2025, with at least 3 of them on double shift
operations, aiming to maximize drilling rates to achieve the
targeted PEA and PFS publication dates from mid and late 2025
respectively.
The figures below show the planned drilling for
Phase 2, 3 & 4. Phase 3 drilling is expected to be completed at
half year and Phase 4 drilling by the end of 2025.
Figure 1: Plan view showing historical drill
collar locations and drill collars for Koryx actual 2024 and
planned 2025 drilling
Figure 2: Long section showing the planned
future drill programs. Detailed planning of the extension drilling
program as part of Phase 2 is currently underway and target areas
are indicated by yellow stars
Metallurgical Testwork Including
Innovative Technologies
Koryx’s metallurgical test work campaign is well
advanced and builds on the high-quality work done by others since
1996, which built on the exploration activities completed by Rio
Tinto and Teck Resources since the 1970’s and 1990’s
respectively.
The objective of Koryx’s metallurgical testing
is to a) demonstrate the feasibility of a conventional processing
route (crushing, grinding, flotation), producing a high quality
clean concentrate from the higher grade material at Haib
(>0.275% Cu) and b) demonstrating the feasibility of a
heap-leach processing route to treat the lower grade material
(<0.275% Cu) in parallel with, but staged after the conventional
flotation process.
There are several innovative and relatively
novel technologies with laboratory test, site demonstration plant
or small-scale commercial references, that have the potential to be
applicable to the Haib mineralised material. In this context,
preliminary discussions have taken place with Mintek, CSIRO, Jetti,
Ceibo, Nuton and MJOI in respect of the planned leach tests, and we
expect to test at least two alternatives with the assistance of the
technology suppliers and test laboratories as well as independent
consultants specialising in chalcopyrite leach processes.
These technologies are relevant because of their
ability to overcome the passivation challenge associated with
leaching of the chalcopyrite mineral which is the dominant form of
copper mineralisation at Haib. The Koryx study team has also
evaluated the potential for bacterial heap leaching with or without
the addition of catalytic reagents, as well as nitrate or chloride
based chemical heap leach processes.
Composited borehole core samples for a total of
about 4 tonnes of material have been selected. These samples
exhibit a range of copper, gold and molybdenum grades as well as
some variation in mineralogical composition.
Samples amounting to about 2 tonnes have already
been despatched to Maelgwyn in Johannesburg for minerals processing
tests on materials containing above 0.275% Cu. Testwork has begun
to confirm or enhance the results of laboratory and pilot tests
carried out in 1996, with the following tasks to be performed in
the laboratory:
- Crushing and milling tests to
support comminution circuit modelling.
- Mineralogical examination for
pre-concentrate, concentrate and tailings samples.
- Chemical analyses to include
copper, molybdenum and gold.
- Bulk sorting tests and simulations
of both low- and high-grade mineralisation, to enable modelling of
pre-concentration after primary crushing.
- Dense medium separation
(“DMS”) tests to enable modelling of
pre-concentration
- Coarse particle flotation with and
pre-concentration test aiming potentially significantly reduce
tonnage to regrind and cleaner flotation.
- Conventional milling and flotation
tests of fresh sulphide and oxide/transitional material.
- Dewatering and transportability
tests of final flotation concentrate and tailings
- Geochemical column leach tests of
low grade, waste rock and filtered tailings to determine potential
for acid generation and acid rock drainage.
- Geotechnical tests of filtered
tailings to confirm likely stability.
- Acid heap leaching of
oxide/transitional material samples.
In addition, about 2 tonnes of low grade samples
(containing 0.15% to 0.35% Cu) are being collected in Q1 2025 for
hydrometallurgical variability tests, likely to take place at
multiple laboratories still to be selected. These are expected to
include:
- Crushing tests to confirm
differences in physical characteristics from higher grade
material.
- Mineralogical and chemical analyses
of material.
- Bacterial acclimatisation,
compatibility and culture development tests.
- Bacterial heap leach tests using 1m
or 6m diameter columns for about 9 months.
- Chemical heap leach tests in
columns, using 2-3 different commercial techniques intended to
overcome chalcopyrite passivation.
- Geotechnical and geochemical tests
of residue from the column leach tests.
As is the case for milling and flotation of
higher grade mineralisation, successful historical
hydrometallurgical test work has been carried out on low grade
mineralisation samples. The new tests listed above will be scoped
and designed to supplement and enhance the earlier work. The aim
will be to generate results that will support both the PEA and the
PFS technical and financial evaluations of Haib.
Trade-off Studies and Additional
Technical Assessments
At this early stage of this type of mining and
processing project, there are many possible alternatives in each
link of the value chain. It is rarely immediately clear which of
these alternatives will provide a combination of low technical risk
and high value, especially when the links are combined into the
entire chain. At the PEA stage of project development, it is
relatively inexpensive to consider the techno-economic potential of
most alternatives. We plan to do this, with a subsequent
significant reduction in the number of alternatives to be
considered in more depth when the project proceeds to the PFS
stage.
The metallurgical test results will be used to
support or confirm the expected results of the following process
trade-off studies:
- Comparison of different
pre-concentration flowsheets including rock sorting, DMS and coarse
particle flotation.
- Assessment of optimal crushing and
milling configuration.
- Concentrator plant capacity revenue
versus cost trade-offs.
- Technical comparison of alternative
leach processes to recover copper from chalcopyrite
mineralisation.
- Techno-economic comparison of sale
or toll treatment of flotation concentrate versus on-site leaching
and refining of concentrate with copper metal being transported to
market.
The following additional studies and assessments
will be completed, aimed at firming up important project aspects
and assumptions which have previously not been addressed.
- Site assessment for alternative
metallurgical plant location including civils geotechnical
evaluation and impact analysis.
- Mining and processing value chain
optimisation, to identify how best to increase head grade and
revenue in early years of production.
- Stockpile optimisation (strategic
and tactical use of low grade stockpiles)
- Process equipment and tailings
storage facility (“TSF”) comparisons, based on
thickened, paste and filtered tailings.
- Cost and modes of transport for
concentrate from mine to customer/smelter.
- Electrical power supply and
self-generation using renewable energy sources and battery storage
technology.
- Consideration of alternative water
supply sources with conceptual design and costing.
Site Environmental and Hydrogeological
Studies
Environmental studies specific to the Haib area
began in 2024 to evaluate the wider area which is being targeted
for development. A screening study has confirmed that there are no
fatal flaws impeding the project development and have made
recommendations for specialist studies to take place during 2025.
Some of the studies will commence as the results of certain
technical trade-off studies listed above provide more detail on the
specific mine design:
- Conceptual site wide water balance
and stormwater management plan for the proposed pit and
infrastructure areas, including sizing of key cost areas.
- Specialist baseline studies to
include;
- Biodiversity specialist field
assessment
- Aquatic specialist study to focus
on riparian environments including the Orange River proximal to the
site.
- Hydrogeology ground water
modelling
- Geochemistry study to utilise
tailings material from ongoing met lab testwork, stockpile
materials and waste rock dump material determined by mine
planning.
- Update to Archaeological study
completed in 2024 which will confirm specific infrastructure
footprint.
- Air quality and noise specialist
study will be performed at chosen receptor sites to create a
pre-project baseline.
- Social specialist study will
investigate key areas to be addressed to inform IFC
requirements.
Exploration and Studies Schedule and
Timelines
The Haib project team will continue to fast
track the development studies throughout 2025 with the intension to
update the PEA by the second half of the year and announce the PFS
by the end of the year.
Figure 3: Drilling, Studies & Permitting
Activity Schedule for 2025-2027
This will put the project in a strong position
to execute the DFS in 2026 and progress to Front End Engineering
and Design (“FEED”) in conjunction with project
financing in 2027.
Budget
The budgeting process is ongoing and is expected
to be concluded before the end of January 2025. It is anticipated
that this work program will cost up to C$20 million, which is
expected to be covered with Koryx current treasury plus expected
warrant exercises between now and the end of the year. This budget
is expected to be approved at Koryx next Board of Directors meeting
to be held before the end of January 2025.
Qualified Person
Mr. Dean Richards Pr.Sci.Nat., MGSSA – BSc.
(Hons) Geology is the Qualified Person for the Haib Copper Project
and has reviewed and approved the scientific and technical
information in this news release and is a registered Professional
Natural Scientist with the South African Council for Natural
Scientific Professions (Pr. Sci. Nat. No. 400190/08) and a
Qualified Person for the purposes of National Instrument
43-101.
About Koryx Copper Inc.
Koryx Copper Inc. is a Canadian copper
development Company focused on advancing the 100%-owned Haib Copper
Project in Namibia whilst also building a portfolio of copper
exploration licenses in Zambia. Haib is a large and advanced
(PEA-stage) copper/molybdenum porphyry deposit in southern Namibia
with a long history of exploration and project development by
multiple operators. More than 70,000m of drilling has been
conducted at Haib since the 1970’s with significant exploration
programs led by companies including Falconbridge (1964), Rio Tinto
(1975) and Teck (2014). Teck remains a strategic and
supportive shareholder.
In addition to extensive drilling and
metallurgical testing various technical studies have been completed
at Haib to date. Haib has a current mineral resource of 414Mt @
0.35% Cu for 1,459mt of contained copper in the Indicated category
and 345Mt @ 0.33% Cu for 1136Mt of contained copper in the Inferred
category (0.25% Cu cut-off). Mineralisation at Haib is typical of a
porphyry copper deposit. Porphyry copper deposits are a major
global source of copper with the best-known examples being
concentrated around the Pacific Rim, North America and South
America.
Haib is one of a few examples of a
Paleoproterozoic porphyry copper deposit in the world and one of
only two in southern Africa (both in Namibia). Due to its age, the
deposit has been subjected to multiple metamorphic and deformation
events, but still retains many of the classic mineralisation and
alteration features typical of these deposits. The mineralisation
is dominantly chalcopyrite with minor bornite and chalcocite
present and only minor secondary copper minerals at surface due to
the arid environment.
Further details are available on the Company's
website at https://koryxcopper.com and under the Company's profile
on SEDAR+ at www.sedarplus.ca.
More information is available by contacting the
Company:
Julia Becker Corporate
Communications jbecker@koryxcopper.com+1-604-785-0850
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
Cautionary Statement Regarding
Forward-Looking Information
This press release contains "forward-looking
information" within the meaning of applicable Canadian securities
legislation. Forward-looking information includes, without
limitation, statements regarding the use of proceeds from the
Company's recently completed financings and the future or prospects
of the Company. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as
"plans", "expects" or "does not expect ", "is expected ", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or
"does not anticipate", or "believes", or variations of such words
and phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved". Forward-looking statements are necessarily based upon a
number of assumptions that, while considered reasonable by
management, are inherently subject to business, market, and
economic risks, uncertainties, and contingencies that may cause
actual results, performance, or achievements to be materially
different from those expressed or implied by forward-looking
statements. Although the Company has attempted to identify
important factors that could cause actual results to differ
materially from those contained in forward-looking information,
other factors may cause results not to be as anticipated,
estimated, or intended. There can be no assurance that such
information will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such
statements. Accordingly, readers should not place undue reliance on
forward-looking information. Other factors which could materially
affect such forward-looking information are described in the risk
factors in the Company's most recent annual management discussion
and analysis. The Company does not undertake to update any
forward-looking information, except in accordance with applicable
securities laws.
Photos accompanying this announcement are available
at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/c0b388ab-95f8-41e2-a9a7-0af0e410676a
https://www.globenewswire.com/NewsRoom/AttachmentNg/e6c37c38-d270-4c41-9367-221e68904cbd
https://www.globenewswire.com/NewsRoom/AttachmentNg/2ad2de10-4437-4b13-8b0a-c345460b851d
Koryx Copper (TSXV:KRY)
Graphique Historique de l'Action
De Jan 2025 à Fév 2025
Koryx Copper (TSXV:KRY)
Graphique Historique de l'Action
De Fév 2024 à Fév 2025