Trading Symbol TSX: SVM
NYSE AMERICAN: SVM
VANCOUVER, BC, Feb. 24, 2022
/PRNewswire/ - Silvercorp Metals
Inc. ("Silvercorp" or the "Company") (TSX: SVM)
(NYSE American: SVM) provides updates on the construction plan and
progress on its new 3,000 tonne per day flotation mill (the
"New Mill") and tailings storage facility ("TSF") at the Ying
Mining District, Henan Province,
China.

The plan and the required regulatory approval process to build
the New Mill and the TSF were announced on November 16, 2021. Currently, the Company has
made progress in the following areas: i) agreements to lease 123.46
hectares of land have been negotiated with the local community; ii)
the environmental assessment report and safety assessment report
for the TSF have been completed and filed with the local county
government, and the reports for the New Mill have been drafted and
are to be finalized pending completion of the preliminary
engineering design of the New Mill; iii) seven drill rigs are
currently on site and 1,738 of 3,300 metres of foundation
engineering survey drilling have been completed; and iv) contractor
selection to construct 5,100 metres of drain tunnels at the TSF has
been initiated.
The updated budget is estimated to be approximately US$29.8 million for the New Mill and US$38.0 million for the TSF. The New Mill
will be equipped with a Knelson gold gravity separation circuit and
designed to produce silver-lead, zinc, copper, and gold
concentrates. The TSF may be constructed in two phases, with
approximately 10.2 million cubic metres of storage capacity in
Phase 1, and approximately 8.9 million cubic metres of capacity in
Phase 2, for a total storage capacity of 19.1 million cubic metres.
The Company expects that construction of the New Mill will be
completed by the end of 2023, and Phase 1 of the TSF by the end of
2024.
The following tables summarize the estimated budget and
construction schedules for the New Mill and TSF:
Category
|
Description
|
Target
Completion
Schedule
|
Estimated
Expenditures
|
(in millions of
US$)
|
Fiscal
2023
|
Beyond
Fiscal 2023
|
Total
|
3,000 tonne per
day mill
|
Design &
Permitting
|
Land Lease
& Rezoning
|
April-22
|
0.3
|
-
|
0.3
|
Design &
Engineering
|
August-22
|
0.5
|
-
|
0.5
|
Environmental
&
Safety Assessment
|
August-22
|
0.2
|
-
|
0.2
|
Construction
& Equipment
|
Site
Preparation
|
October-22
|
1.0
|
|
1.0
|
Road
Construction
|
October-23
|
1.7
|
0.3
|
2.0
|
Mill
Construction
|
October-23
|
7.5
|
4.6
|
12.1
|
Equipment
Acquisition
|
March-23
|
10.1
|
-
|
10.1
|
Installation
|
October-23
|
1.5
|
0.7
|
2.2
|
Contigency
|
December-23
|
1.0
|
0.4
|
1.4
|
Total
Expenditures
|
|
23.8
|
6.0
|
29.8
|
Category
|
Description
|
Target
Completion
Schedule
|
Estimated
Expenditures
|
(in millions of
US$)
|
Fiscal
2023
|
Beyond
Fiscal 2023
|
Total
|
Tailings Storage
Facility
|
Design &
Permitting
|
Land Lease &
Rezoning
|
April-22
|
3.1
|
-
|
3.1
|
Design &
Engineering
|
June-22
|
0.4
|
-
|
0.4
|
Environmental
&
Safety
Assessment
|
May-22
|
0.1
|
-
|
0.1
|
Construction
|
Site
Preparation
|
December-22
|
2.3
|
-
|
2.3
|
TSF
Construction
|
October-24
|
8.5
|
19.7
|
28.2
|
Contingency
|
December-24
|
1.7
|
2.2
|
3.9
|
Total
Expenditures
|
16.1
|
21.9
|
38.0
|
The New Mill and TSF are being constructed to provide the
Company with additional capacity to continue growing its existing
mining operations at the Ying Mining District in light of recent
successful drilling programs that have discovered new resources, to
process ore from recent acquisitions, and for potential
consolidation of other nearby projects. Once the New Mill is
completed, the Company will decommission its No. 1 mill to have
approximately 5,000 tonnes per day of milling capacity. A new
training facility and R&D centre are planned at No. 1 mill
site.
About Silvercorp
Silvercorp is a profitable Canadian mining company producing silver, lead, and zinc metals in concentrates
from mines in China. The Company's
goal is to continuously create healthy returns to shareholders
through efficient management, organic growth, and the acquisition
of profitable projects. Silvercorp balances profitability, social
and environmental relationships, employees' wellbeing, and
sustainable development. For more information, please visit our
website at www.silvercorp.ca.
CAUTIONARY DISCLAIMER - FORWARD LOOKING
STATEMENTS
Certain of the statements and information in this press
release constitute "forward-looking statements" within the meaning
of the United States Private Securities Litigation Reform Act of
1995 and "forward-looking information" within the meaning of
applicable Canadian provincial securities laws. Any statements or
information that express or involve discussions with respect to
predictions, expectations, beliefs, plans, projections, objectives,
assumptions or future events or performance (often, but not always,
using words or phrases such as "expects", "is expected",
"anticipates", "believes", "plans", "projects", "estimates",
"assumes", "intends", "strategies", "targets", "goals",
"forecasts", "objectives", "budgets", "schedules", "potential" or
variations thereof or stating that certain actions, events or
results "may", "could", "would", "might" or "will" be taken, occur
or be achieved, or the negative of any of these terms and similar
expressions) are not statements of historical fact and may be
forward-looking statements or information. Forward-looking
statements or information relate to, among other things: the price
of silver and other metals; the accuracy of mineral resource and
mineral reserve estimates at the Company's material properties; the
sufficiency of the Company's capital to finance the Company's
operations; estimates of the Company's revenues and capital
expenditures; estimated production from the Company's mines in the
Ying Mining District; timing of receipt of permits and regulatory
approvals; availability of funds from production to finance the
Company's operations; and access to and availability of funding for
future construction, use of proceeds from any financing and
development of the Company's properties.
Forward-looking statements or information are subject to a
variety of known and unknown risks, uncertainties and other factors
that could cause actual events or results to differ from those
reflected in the forward-looking statements or information,
including, without limitation, social and economic impacts of
COVID-19; risks relating to: fluctuating commodity prices;
calculation of resources, reserves and mineralization and precious
and base metal recovery; interpretations and assumptions of mineral
resource and mineral reserve estimates; exploration and development
programs; feasibility and engineering reports; permits and
licenses; title to properties; property interests; joint
venture partners; acquisition of commercially mineable mineral
rights; financing; recent market events and conditions; economic
factors affecting the Company; timing, estimated amount, capital
and operating expenditures and economic returns of future
production; integration of future acquisitions into the Company's
existing operations; competition; operations and
political conditions; regulatory environment in China and Canada; environmental risks;
legislative and regulatory initiatives addressing global climate
change or other environmental concerns; foreign exchange rate
fluctuations; insurance; risks and hazards of mining operations;
key personnel; conflicts of interest; dependence on management;
internal control over financial reporting as per the requirements
of the Sarbanes-Oxley Act; and bringing actions and enforcing
judgments under U.S. securities laws.
This list is not exhaustive of the factors that may affect
any of the Company's forward-looking statements or information.
Forward-looking statements or information are statements about the
future and are inherently uncertain, and actual achievements of the
Company or other future events or conditions may differ materially
from those reflected in the forward-looking statements or
information due to a variety of risks, uncertainties and other
factors, including, without limitation, those referred to in the
Company's Annual Information Form for the year ended March 31, 2021 under the heading "Risk
Factors". Although the Company has attempted to identify
important factors that could cause actual results to differ
materially, there may be other factors that cause results not to be
as anticipated, estimated, described or intended.
Accordingly, readers should not place undue reliance on
forward-looking statements or information.
The Company's forward-looking statements and information are
based on the assumptions, beliefs, expectations and opinions of
management as of the date of this press release, and other than as
required by applicable securities laws, the Company does not assume
any obligation to update forward-looking statements and information
if circumstances or management's assumptions, beliefs, expectations
or opinions should change, or changes in any other events affecting
such statements or information. For the reasons set forth above,
investors should not place undue reliance on forward-looking
statements and information.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/silvercorp-provides-updates-to-the-construction-plan-and-progress-on-its-new-3-000-tonne-per-day-mill-and-associated-tailings-storage-facility-for-the-ying-mining-district-301490217.html
SOURCE Silvercorp Metals Inc