Ascot Resources Ltd. (
TSX: AOT; OTCQX:
AOTVF) (“
Ascot” or the
“
Company”) is pleased to announce the Company’s
unaudited financial results for the three months and six months
ended June 30, 2023 (“
Q2 2023”), and also to
provide a construction update on the Company’s Premier Gold Project
(“
PGP” or the “
project”), located
on Nisga’a Nation Treaty Lands in the prolific Golden Triangle of
northwestern British Columbia. For details of the unaudited
condensed interim consolidated financial statements and
Management's Discussion and Analysis for the three and six months
ended June 30, 2023, please see the Company’s filings at
www.ascotgold.com or on SEDAR+ (www.sedarplus.ca).
Derek White, President and CEO, commented,
"Construction activity at the Premier Gold Project continued to
increase in the second quarter, with much progress being made on
the critical outdoor and earthworks areas, including the tailings
storage facility and new water treatment plant. As of Q2 2023,
detailed engineering and major procurement are substantially
complete, and project construction excluding mine development is at
48%.
Additionally, at the corporate level we have
made steady progress on important agreements including the signing
of a 3-year mining contract with Procon, the US$15 million
equipment lease facility with CAT Financial, and the US$14 million
convertible facility with Nebari.
The 2023 exploration program has been steadily
progressing, with encouraging results encountered in both the
drilling program and the IP geophysics program. We anticipate
starting to release exploration results in the coming weeks as we
receive them.”
All amounts herein are reported in $000s of
Canadian dollars (“C$”) unless otherwise
specified.
Q2 2023 AND RECENT
HIGHLIGHTS
- The earthworks
contract for the tailings storage facility was signed in March 2023
and the contractor was mobilized to the site in April 2023.
Tailings pond de-watering was completed in June 2023 and the
construction of the tailings storage facility commenced.
- On April 20,
2023, the Company closed a previously announced non-brokered
private placement (the “Offering”). The Offering raised total gross
proceeds of $4,050 and consisted of 5,000,000 common shares of the
Company, which qualify as "flow-through shares" within the meaning
of the Income Tax Act (Canada) (the “FT Shares”), at a price of
C$0.81 per FT Share. The proceeds from the Offering will be used to
fund the 2023 exploration program at PGP.
- On May 11, 2023,
the Company announced the 2023 exploration program at PGP. The
program consists of an initial 10,000 metres of surface drilling
and will include exploration drilling for resource expansion as
well as in-fill drilling of initial mining areas at the Big
Missouri and Premier deposits. The exploration drilling will focus
on extending the Day Zone at Big Missouri and the Sebakwe Zone
north of the Premier mill. Up to an additional 4,000 meters of
drilling have been budgeted and will be deployed towards surface
and underground drilling depending on results of the initial 10,000
metres. The 2023 exploration program commenced on June 21,
2023.
- On June 27,
2023, the Company closed a previously announced US$14 million
subordinated convertible credit facility (the “Convertible
Facility”) with Nebari Gold Fund 1, LP (“Nebari”). The full
proceeds from the Convertible Facility were used to repay
principal, accrued interest and fees of Ascot’s existing
subordinated convertible credit facility with Beedie Investments
Ltd. (“Beedie”).
- On July 31,
2023, the Company entered into a master lease agreement with
Caterpillar Financial Services (“CAT Financial”) for an equipment
lease facility up to US$15 million on an uncommitted basis for
surface mining equipment and construction equipment. The lease
terms of the equipment are 4 to 5 years at an interest rate of the
Canadian Dollar Offered Rate plus 4.25%.
- On August 8,
2023, the Company entered into a contract with Procon Mining &
Tunnelling Ltd. for underground mining services for an initial term
of 3 years with option to renew for two consecutive 1-year
periods.
PROJECT CONSTRUCTION
In January 2023, the Company closed a project
financing package consisting of US$110 million as a deposit in
respect of gold and silver streaming agreements (the “Stream”) and
a strategic equity investment (the “Strategic Investment”) of
C$45 million, a portion of which is structured as Canadian
Development Expenditures flow through shares, such that the total
gross proceeds to the Company were C$50 million. Upon securing the
new project financing, Ascot re-mobilized various contractors to
progress activities for the remainder of construction scope for the
Project. At the start of Q2 2023, there were approximately 118
employees and contractors working at the project site, and by the
end of the quarter on June 30, 2023, there were over 180 people
working at site.
Progress key performance indicators
(“KPI”) and budgetAt the end of Q2 2023, overall
construction excluding mine development was 48% complete, with
engineering at 99% and procurement at 99%. The Project remains on
schedule and budget for first gold production in the first quarter
of 2024. Capital costs, including mining, incurred as of June 30,
2023 were $200 million. As of June 30, 2023, the remaining project
construction capital required to complete construction and achieve
the first gold pour is approximately $110 million including mining
but excluding certain pre-operating costs and working capital. This
is slightly higher than the most recent total project budget of
$300 million to achieve first gold production reported in the
Company’s News Release dated December 12, 2022. The modest cost
increase is attributable to a slight delay of several weeks to
achieve initial gold production, which arose as the Company
progressed the detailed commissioning schedule. However, the target
for initial gold production in Q1 of 2024 is unchanged. The company
is assessing the working capital requirements as the project
progresses from commissioning to production and ramp up phases, and
is evaluating various potential financing options should additional
funding be required.
SafetyThe Project continues to
have an excellent safety record with 633,224 hours of work to date
and zero lost time incidents. The total recordable incident
frequency has been reduced from 1.28 at the end of Q1 2023, to 0.95
by the end of Q2 2023. However, with the increased activity on site
and additional work areas, the number of incidents has increased
including property damage, first aid injuries, and near misses.
Reporting activity has been encouragingly high, and the Company
will continue to work on proactive safety training and measures to
reduce overall incidents at the Project site.
Processing PlantMechanical work
continued in the mill during Q2 2023; various trommels, dust
collection and chute infrastructure were installed around the SAG
and Ball mills. The Intensive Leach Reactor was assembled.
Electricians continued installing electrical cabinetry, pulling
wire, installing cable trays, and working in the mine control
centre room. Piping installation at the mill is approximately 50%
complete. The tailings thickener and cyanide destruction tank
outside the mill was also substantially completed in the quarter.
Concrete and structural steel contractors also have been restarted
and their scope updated for the mill completion.
Tailings Storage Facility (“TSF”) and
Cascade Creek Diversion Channel (“CCDC”)The earthworks
contract for the TSF and CCDC was signed in March 2023 and the
contractor was mobilized to the site in April 2023. In order to
de-water the tailings facility for the required earthworks, an
additional temporary water treatment plant (“WTP”) was mobilized to
site and commissioned in May 2023. Despite minor issues with
initial ramp up, at the end of May the plant was operating at full
capacity and in combination with other discharge points, the TSF
was discharging near the permitted rate of 20,000 m3 per day.
By the end of June 2023, dewatering was completed and the temporary
WTP was demobilized. Drilling and blasting were started on the CCDC
in May, with a target of one blast of 7,000 to 8,000 m3 every other
day. To date, geological monitoring hasn’t noted potentially acid
generating (“PAG”) material, and work is progressing well. Work
continued at the TSF with earthworks contractors producing and
placing T-zone material at the south dam, preparing the foundation
at the east dam, blasting rock from the CCDC and bringing it to the
crusher plant. The earthworks contractor added a night shift at the
end of June to increase productivity.
Water Treatment Plant
(“WTP”)Crews have also made progress on the new WTP and
associated infrastructure, including the tailings thickener, lime
silos, moving bed bio-reactor (“MBBR”) tanks and clarifier
foundation pedestals. Construction remains targeted for July and
August to coincide with new WTP completion in September and
subsequent commissioning.
Site InfrastructureDuring Q2
2023, much work was completed on constructing the new electrical
substation near the Premier mill. With the substation mostly
complete, crews are now working on the 138kV power line to connect
to the power grid less than 500 metres away. Crews also have been
making progress on relocating the Big Missouri water pipeline from
one side of the Big Missouri haul road to the other, which is
expected to enhance the long-term safety and integrity of the
pipeline.
Mine DevelopmentAfter an
extensive and competitive process involving six contracting
companies, Ascot selected Procon Mining & Tunnelling (“Procon”)
for a 3-year contract to advance the underground portion of the
project. Procon is headquartered in Burnaby, BC and has extensive
underground mining experience in the province, including its
current mining and development contract at the nearby Brucejack
underground gold mine.
In 2022, work commenced on the S1 portal and
approximately 907 metres of underground development was completed
in the Big Missouri area before being paused for the winter. Procon
will pick up from this existing development and continue the ramp
and ore accesses as planned in September 2023, eventually
connecting over to the Silver Coin deposit.
In late summer 2023, Procon will also start a
new ramp development at the Premier deposit immediately adjacent to
the existing mill facilities. They will drive the initial access
ramp from surface down into the Premier deposit for initial mining
at the Prew zone and will eventually connect a footwall ramp over
to 602 area in the Premier deposit to commence mining there.
RecruitmentDuring Q2 2023,
Ascot hired and onboarded a full-time recruitment professional to
lead the Company’s staffing efforts as it advances towards
operations in 2024. Recruitment has already begun to ramp up for a
number of key positions added recently, including Health, Safety,
Training and Emergency Preparedness, Human Resources and Fixed
Maintenance Planner.
As recruitment efforts continue to ramp up in
the coming months. The interest in Ascot is high and many good
quality candidates continue to apply for open positions.
Encouragingly, local interest is high, as many applications are
coming from candidates in the area of Stewart and northwestern
B.C.
Permitting and Environmental
ComplianceAs a result of the project slowdown in 2022 due
to the required re-financing process, a Joint Permit Amendment
Application (“JPAA”) will be submitted in August 2023 to change
targeted conditions within the permit, mostly due to the delay of
meeting the new water treatment and quality requirements from
December 2022 to Q4 2023. In addition, a Mines Act Permit Amendment
(“MAPA”) was submitted in mid-June 2023 with respect to changing
the planned location of the Premier mine portal from the southern
location to an area much closer to the mill facility. All comments
and information requests from the Nisga’a Lisims Government have
been addressed and closed, and comments from the regulator are
expected to be finalized in the coming weeks.
2023 EXPLORATION PROGRAM
The exploration program commenced on June 21,
2023 when a drill rig was mobilized to the Prew zone of the Premier
deposit. The first nine drill holes have been completed and have
intercepted visual sulfide mineralization very close to expected
depth and corresponding stope locations. Visible gold was
intercepted in at least one of the drill holes. It appears that the
location and geometry of the mineralization at the Prew is well
defined and should provide a good starting point for mining
operations. Four more holes are planned in this area aiming at
extensions of stopes and gaps between designed stopes. On
completion of the drilling at the Prew zone, the rig will move up
to Big Missouri to conduct additional drilling in that area.
The ground geophysical induced polarization
(“IP”) survey commenced on June 26, 2023 and is now approximately
70% complete. The crew completed two grids, one near the Premier
mill targeting the western extension of the Sebakwe Zone that
yielded very good exploration results last year. The grid has been
designed to cover approximately 1,000 metres of strike extent to
the west of the drilling in 2022. It is not known if the Sebakwe
Zone extends further west and if so, where it is located in terms
of northing. The mineralization at Premier shows very well in
induced polarization data and preliminary results are highly
anticipated.
The second grid was completed around the
Dilworth deposit in the northern part of the property. The geology
of this area is not as well understood as Premier and Big Missouri
and the exploratory induced polarization data should help with
effective targeting of prospective areas. A third grid is currently
being laid out at the northern extension of the Day Zone. This area
has yielded very good exploration results in the last two years and
mineralization remains open towards the north and south. The strike
extent to the north could potentially connect the Day Zone with the
Martha Ellen deposit further north. The results from the IP survey
will be utilized for drill targeting in the second half of the 2023
field season.
FINANCIAL RESULTS FOR THE THREE MONTHS
ENDED JUNE 30, 2023
The Company reported a net loss of $3,073 for Q2
2023 compared to $1,054 for Q2 2022. The higher net loss in current
quarter is driven by a $2,262 loss on extinguishment of convertible
debt.
LIQUIDITY AND CAPITAL
RESOURCES
As at June 30, 2023, the Company had cash &
cash equivalents of $119,324 and working capital of $103,147. In H1
2023, the Company issued 120,048,007 common shares, no vested
warrants, 613,334 stock options, 32,665 deferred share units, no
restricted share units and no performance share units. Also,
520,250 stock options expired and 55,530 stock options, 352,006
deferred share units and 683,398 restricted share units were
exercised in H1 2023.
As at August 11, 2023, the Company had
555,909,153 common shares outstanding, 23,822,382 stock options,
13,710,500 vested share purchase warrants, 1,557,071 deferred share
units, 3,796,930 restricted share units and 108,108 performance
share units outstanding. Also, 25,767,777 unvested Prepayment
Warrants issued to Nebari are outstanding.
MANAGEMENT’S OUTLOOK FOR
2023
With the financing package closed on January 19,
2023 and refinancing of the existing convertible debt on June 28,
2023, the Company is focusing on the completion of construction of
the Project and achieving first gold production in early 2024. The
key activities for remainder of 2023 include:
- Construction of
the processing plant and associated surface infrastructure such
that the plant is expected to be in pre-commissioning by the end of
2023
- Completion of
the tailings dam improvements and start up of the new water
treatment plant by Q4 2023
- Advancement of
the Premier portal and underground development and additional
underground development of the Big Missouri mine, as well as
initial production stoping to provide mill feed for
commissioning.
- Maintaining a
Health and Safety record of zero lost time incidents and achieving
the 2023 goals outlined in the Company’s 2022 Sustainability
Report
- Advancing the
recruitment of site personnel in line with the site personnel plan
by the end of 2023
- Maintaining
permitting and environmental compliance so that there are no delays
in the project construction schedule
- More exploration
and infill drilling north and west of existing resources at the
Premier Northern Light and Day zone resources areas
CONSTRUCTION PROGRESS
PHOTOS
Figure 1 – New electrical substation
constructionhttps://www.globenewswire.com/NewsRoom/AttachmentNg/f4031c7f-d5dd-4684-bcc5-a6386ed781c1
Figure 2 – New WTP
overviewhttps://www.globenewswire.com/NewsRoom/AttachmentNg/642c8f63-f145-45ef-99ce-a5d54f897a2f
Figure 3 – New WTP clarifier
constructionhttps://www.globenewswire.com/NewsRoom/AttachmentNg/b3285f8d-f345-4bd2-8ef6-194c26bbf579
Figure 4 – New WTP MBBR tanks and
electrical
buildinghttps://www.globenewswire.com/NewsRoom/AttachmentNg/2bafa887-b5e7-46a1-8ba4-7161d952f378
Figure 5 – Tailings thickener and CN
destruction
tankhttps://www.globenewswire.com/NewsRoom/AttachmentNg/06e91084-3316-4373-88e1-63762df9fd29
Figure 6 – CCDC excavation
overviewhttps://www.globenewswire.com/NewsRoom/AttachmentNg/8e7bd5df-bf39-4ad0-b617-ba4609314307
Figure 7 – CCDC excavation looking
southhttps://www.globenewswire.com/NewsRoom/AttachmentNg/ecbed584-0a96-4e08-8ae7-bcb1d107d5f8
Figure 8 – Tailings south dam
earthworkshttps://www.globenewswire.com/NewsRoom/AttachmentNg/8de29e0f-56b0-44a9-bf0f-7cbb22739a66
Figure 9 – Temporary crushing plant for
tailings
earthworkshttps://www.globenewswire.com/NewsRoom/AttachmentNg/036c60dd-d6d5-48aa-b2b0-3c7c6b53d573
Qualified Person
John Kiernan, P.Eng., Chief Operating Officer of
the Company is the Company’s Qualified Person (QP) as defined by
National Instrument 43-101 and has reviewed and approved the
technical contents of this news release.
On behalf of the Board of Directors of
Ascot Resources Ltd.“Derek C. White”President &
CEO
For further information
contact:
David Stewart, P.Eng.VP, Corporate Development & Shareholder
Communicationsdstewart@ascotgold.com778-725-1060 ext. 1024
About Ascot Resources Ltd.
Ascot is a Canadian junior exploration and
development company focused on re-starting the past producing
Premier gold mine, located on Nisga’a Nation Treaty Lands, in
British Columbia’s prolific Golden Triangle. Ascot shares trade on
the TSX under the ticker AOT. Concurrent with progressing the
development of Premier, the Company continues to successfully
explore its properties for additional high-grade underground
resources. Ascot is committed to the safe and responsible
development of Premier in collaboration with Nisga’a Nation as
outlined in the Benefits Agreement.
For more information about the Company, please
refer to the Company’s profile on SEDAR+ at www.sedar.ca or visit
the Company’s web site at www.ascotgold.com, or for a virtual tour
visit www.vrify.com under Ascot Resources.
The TSX has not reviewed and does not accept
responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding
Forward-Looking Information
All statements and other information contained
in this press release about anticipated future events may
constitute forward-looking information under Canadian securities
laws ("forward-looking statements"). Forward-looking statements are
often, but not always, identified by the use of words such as
"seek", "anticipate", "believe", "plan", "estimate", "expect",
"targeted", "outlook", "on track" and "intend" and statements that
an event or result "may", "will", "should", "could" or "might"
occur or be achieved and other similar expressions. All statements,
other than statements of historical fact, included herein are
forward-looking statements, including statements in respect of the
advancement and development of the PGP and the timing related
thereto, the exploration of the Company’s properties and
management’s outlook for the remainder of 2023 and beyond. These
statements involve known and unknown risks, uncertainties and other
factors that may cause actual results or events to differ
materially from those anticipated in such forward-looking
statements, including risks associated with the business of Ascot;
risks related to exploration and potential development of Ascot's
projects; business and economic conditions in the mining industry
generally; fluctuations in commodity prices and currency exchange
rates; uncertainties relating to interpretation of drill results
and the geology, continuity and grade of mineral deposits; the need
for cooperation of government agencies and indigenous groups in the
exploration and development of properties and the issuance of
required permits; the need to obtain additional financing to
develop properties and uncertainty as to the availability and terms
of future financing; the possibility of delay in exploration or
development programs and uncertainty of meeting anticipated program
milestones; uncertainty as to timely availability of permits and
other governmental approvals; risks associated with COVID-19
including adverse impacts on the world economy, construction timing
and the availability of personnel; and other risk factors as
detailed from time to time in Ascot's filings with Canadian
securities regulators, available on Ascot's profile on SEDAR+ at
www.sedar.ca including the Annual Information Form of the Company
dated March 23, 2023 in the section entitled "Risk Factors".
Forward-looking statements are based on assumptions made with
regard to: the estimated costs associated with construction of the
Project; the timing of the anticipated start of production at the
Project; the ability to maintain throughput and production levels
at the Premier Mill; the tax rate applicable to the Company; future
commodity prices; the grade of Resources and Reserves; the ability
of the Company to convert inferred resources to other categories;
the ability of the Company to reduce mining dilution; the ability
to reduce capital costs; and exploration plans. Forward-looking
statements are based on estimates and opinions of management at the
date the statements are made. Although Ascot believes that the
expectations reflected in such forward-looking statements and/or
information are reasonable, undue reliance should not be placed on
forward-looking statements since Ascot can give no assurance that
such expectations will prove to be correct. Ascot does not
undertake any obligation to update forward-looking statements. The
forward-looking information contained in this news release is
expressly qualified by this cautionary statement.
Ascot Resources (TSX:AOT)
Graphique Historique de l'Action
De Déc 2024 à Jan 2025
Ascot Resources (TSX:AOT)
Graphique Historique de l'Action
De Jan 2024 à Jan 2025