TORONTO, Nov. 22,
2022 /CNW/ - Denison Mines
Corp. ("Denison" or the "Company") (TSX: DML) (NYSE
American: DNN) is pleased to announce additional
highlights from the completion of the highly successful
leaching phase of the ongoing Phoenix in-situ recovery
("ISR") Feasibility Field Test ("FFT") at the Company's 95% owned
Wheeler River project ("Wheeler River" or the "Project"). View PDF
version
- Recovered approximately 14,400 lbs
U3O8 over ten days of active
leaching following completion of initial acidification of
the Leaching Area (defined below).
- Returned maximum uranium head grade of recovered
solution of 43 grams per litre ("g/l") when the leaching
phase of the FFT was completed, with
grades still rising (indicative of the ramp-up segment of
a well production profile).
- Achieved suitable acidification for ISR mining within
7 days post initial injection at 5 metre well spacing (GWR-41)
and within 17 days for 10 metre well spacing (GWR-38).
- Demonstrated ability to achieve and
maintain uranium mass flow rate consistent with the
assumptions in the Pre-Feasibility Study ("PFS") prepared for the
Project in 2018.
- Further demonstrated hydraulic control of injected solution
during the FFT, reporting no responses in the monitoring
wells outside of the designed FFT test area.
- Confirmed breakthrough times between injection and
recovery wells, consistent with the Project's hydrogeological
model and the previously completed tracer test.
David Cates, Denison's President
& CEO, commented, "The detailed results
from the leaching phase of the Phoenix
ISR FFT are very encouraging. Using only one
injection well and two recovery wells for a period of active
leaching of only ten days, we
recovered an estimated 14,400 lbs
U3O8 –
representing approximately 1% of the
mineral reserves estimated to be
within the perimeter of the
FFT test area.
These results provide further tangible evidence
of the viability of the ISR mining method at the Company's
high-grade Phoenix uranium
deposit."
Kevin Himbeault, Denison's Vice
President of Plant Operations & Regulatory Affairs, added,
"Uranium
head grades were increasing at the
time the leaching phase of the FFT was completed – returning a
maximum uranium head grade of 43
g/l. This is over 300% higher than the
head grade assumed in the 2018 PFS, and further
supports the Company's
decision to increase the assumed ISR mining
head grade by 50% for the
feasibility study. Overall, the leaching
phase of the FFT has been highly
successful – accomplishing
our
objectives for uranium head grade recovery,
uranium mass
flow rates, and
hydraulic conductivity within the
ore zone. These results further
support the
hydrogeological and
metallurgical modelling expected
to be incorporated into the feasibility
study."
This press release constitutes a "designated
news release" for the purposes of the
Company's prospectus supplement dated September 28, 2021, to its short form base shelf
prospectus dated September 16,
2021.
In 2021, following the completion of various metallurgical
tests, Denison announced a decision to adapt its plans for further
metallurgical test work and project designs to reflect a 50%
increase in the assumed head grade of uranium bearing solution
to be recovered from the Phoenix
well-field – from 10 g/L (as outlined in the PFS) to 15 g/L
(see news release dated August 4,
2021 for details). An increase in head grade is
expected to allow for optimization of operating parameters and
processing plant designs in the feasibility study for the
Project (see news release dated September 22, 2021).
The increasing uranium head grade observed during the
leaching phase of the FFT, including results that exceeded 15
g/L, provide additional support for the decision
to increase the assumed head grade in the
feasibility study. In a production setting, the uranium
bearing solution recovered from 'new' production
wells, yielding higher than average
head grades during the ramp-up segment of a well
production profile, is expected to be combined with recovered
solution from 'existing' production wells producing gradually
decreasing head grades over the life of well production
profile.
FFT Leaching
Phase
The leaching phase of the FFT commenced in September 2022 (see news release dated
September 26, 2022), designed to
assess the effectiveness and efficiency of the leaching process in
the ore zone located approximately 400m below the surface, is now complete. The
leaching phase consisted of the controlled injection of an acidic
mining solution into a portion of the existing Test Pattern
(defined below) within the ore zone (the "Leaching Zone") and the
recovery of the solution back to the surface using existing test
wells. Commercial-scale test well GWR-40 was used as the
injection well, while uranium bearing solution was recovered from
commercial-scale test wells GWR-41 and GWR-38. These wells are
located within Phase 1 of the planned mining areas for Phoenix (See Figure 1 and 2 for photos from
the FFT site). Additional details about Phase 1 and
the estimated Probable mineral reserves contained therein are
provided below.
Throughout the test program, both vertical and horizontal
containment of the mining solution was maintained, with no
migration of the mining solution observed above, below or outside
of the designed FFT test area along the leaching zone. These
results were consistent with the findings from the 2021 tracer test
(see news release dated October 28,
2021) and further confirmed that both targeted mining
head grades and flow rates are
achievable while maintaining containment of ISR mining
activities to defined areas in the ore zone.
Following the completion of the leaching phase of the
FFT in mid-October, field activities transitioned to the
neutralization phase of the FFT. The final phase of the FFT,
which involves the management of the recovered solution, is
expected to begin in the spring of 2023.
Feasibility Field
Test Background
The FFT is designed to use the existing commercial-scale ISR
test pattern ("Test Pattern"), installed at Phoenix in 2021 (see news releases dated
July 29, 2021, and October 28, 2021), to facilitate a combined
assessment of the Phoenix
deposit's hydraulic flow properties with the leaching
characteristics that have been assessed through the metallurgical
core-leach testing program.
The FFT is fully permitted, having been authorized by both the
Saskatchewan Minister of
Environment (see news release dated July 12,
2022) and the Canadian Nuclear Safety Commission (see news
release dated August 8, 2022).
Overall, the FFT is intended to provide further verification of
the permeability, leachability, and containment parameters needed
for the successful application of the ISR mining method at
Phoenix and is expected to
validate and inform various feasibility study design elements –
including the expected production and remediation profiles.
The operation of the FFT is planned to occur in three phases:
(1) the leaching phase, (2) the neutralization phase, and (3) the
recovered solution management phase.
As described above, the leaching phase is now complete. The
neutralization phase was initiated in mid-October 2022, and is intended to verify
the efficiency and effectiveness of the process for returning the
Leaching Zone to environmentally acceptable conditions. During this
phase, a mild alkaline (basic) solution is injected into the
Leaching Zone to neutralize the area and reverse the residual
effects of the acidic solution injected during the leaching
phase.
The recovered solution management phase involves separating the
solution recovered from both the leaching phase and the
neutralization phase into (i) mineralized precipitates and (ii) a
neutralized treated solution.
About Phoenix Phase
1
As outlined in the Company's news release dated
December 1, 2020, Denison has decided
to adapt its plans for the Project to use a phased mining approach,
which is expected to allow for the targeted extraction of the least
capital-intensive reserves first, based on the grade and
distribution of ore in various areas of the deposit. The supporting
trade-off study provides for mining to occur over 5 phases.
Phase 1 of the deposit is estimated to contain approximately
22.2 million pounds
U3O8 (37,242
tonnes at 27.1%
U3O8, above a
cut-off grade of 0.8%
U3O8) in
Probable mineral reserves. Based on current designs, the
Company estimates approximately 6.6 million pounds
U3O8 (7,717
tonnes at 39.2%
U3O8, above a
cut-off grade of 0.8%
U3O8) in
Probable mineral reserves are contained within the expected
operating perimeter of the commercial scale wells in the
5-spot Test Pattern. Of these estimated
Probable mineral reserves, the Company further
estimates that
1.4 million pounds
U3O8 (2,326 tonnes
at 26.2%
U3O8, above a
cut-off grade of 0.8%
U3O8) are
contained within the operating perimeter of GWR-38,
GWR-40, and GWR-41. These estimates are
derived as a direct subset of those reported in the Technical
Report titled "Pre-feasibility Study for the Wheeler River Uranium
Project, Saskatchewan, Canada"
dated October 30, 2018 with an
effective date of September 24,
2018 (the "PFS Report"). The key
assumptions, parameters and methods used to estimate the mineral
reserves herein remain unchanged.
About Wheeler
River
Wheeler River is the largest undeveloped uranium project in
the infrastructure rich eastern portion of the Athabasca Basin region, in northern
Saskatchewan – including combined
Indicated Mineral Resources of 132.1 million pounds
U3O8 (1,809,000
tonnes at an average grade of 3.3%
U3O8), plus
combined Inferred Mineral Resources of 3.0 million pounds
U3O8 (82,000
tonnes at an average grade of 1.7%
U3O8). The
Project is host to the high-grade Phoenix and Gryphon uranium deposits,
discovered by Denison in 2008 and 2014, respectively, and is a
joint venture between Denison (operator) and JCU (Canada) Exploration Company Limited
("JCU"). Denison has an effective
95% ownership interest in Wheeler River (90% directly, and 5%
indirectly through a 50% ownership in JCU).
The PFS was completed for Wheeler River in 2018,
considering the potential economic merit of developing the
Phoenix deposit as an ISR
operation and the Gryphon deposit as a conventional underground
mining operation. Taken together, the Project is estimated to have
mine production of 109.4 million pounds
U3O8 over a
14-year mine life, with a base case pre-tax NPV of $1.31 billion (8% discount rate), Internal Rate
of Return ("IRR") of 38.7%, and initial
pre-production capital expenditures of $322.5 million. The Phoenix ISR operation is
estimated to have a stand-alone base case pre-tax NPV of
$930.4 million (8% discount
rate), IRR of 43.3%, initial pre-production capital expenditures of
$322.5 million, and industry-leading
average operating costs of US$3.33/lb
U3O8. The
PFS is prepared on a project (100% ownership) and pre-tax basis, as
each of the partners to the Wheeler River Joint Venture are subject
to different tax and other obligations.
Further details regarding the PFS, including additional
scientific and technical information, as well as after-tax results
attributable to Denison's ownership interest, are
described in greater detail in the PFS Report, a copy of
which is available on Denison's website
and under its profile on SEDAR at www.sedar.com and on EDGAR at
www.sec.gov/edgar.shtml.
Denison suspended certain activities at Wheeler River during
2020, including the EA process, which is on the critical path to
achieving the project development schedule outlined in the
PFS. While the EA process has resumed, the Company is not
currently able to estimate the impact to the project development
schedule outlined in the PFS, and users are cautioned against
relying on the estimates provided therein regarding the start of
pre-production activities in 2021 and first production in
2024.
About Denison
Denison is a uranium exploration and development company with
interests focused in the Athabasca
Basin region of northern Saskatchewan,
Canada. In addition to its effective 95% interest in the
Wheeler River project, Denison's interests in the Athabasca Basin include a 22.5% ownership
interest in the McClean Lake joint venture, which includes several
uranium deposits and the McClean Lake uranium mill that is
contracted to process the ore from the Cigar Lake mine under a toll
milling agreement, plus a 25.17% interest in the Midwest Main and
Midwest A deposits, and a 67.01% interest in the Tthe Heldeth Túé
("THT," formerly J Zone) and Huskie deposits on the Waterbury Lake
property. The Midwest Main, Midwest A, THT and Huskie deposits are
each located within 20 kilometres of the McClean Lake mill.
Through its 50% ownership of JCU, Denison holds additional
interests in various uranium project joint ventures in Canada, including the Millennium project (JCU
30.099%), the Kiggavik project (JCU 33.8118%) and Christie Lake (JCU 34.4508%). Denison's
exploration portfolio includes further interests in properties
covering ~300,000 hectares in the Athabasca Basin region.
Denison is also engaged in post-closure mine care and
maintenance services through its Closed Mines group, which manages
Denison's reclaimed mine sites in the Elliot Lake region and provides related
services to certain third-party projects.
Follow Denison on Twitter @DenisonMinesCo
Qualified Persons
The disclosure of scientific or technical information related
to the FFT or Wheeler River project contained in this release has
been reviewed and approved, as applicable, by Mr. David Bronkhorst, P.Eng, Denison's Vice
President, Operations or Mr. Andrew
Yackulic, P. Geo., Denison's Director, Exploration, who are
Qualified Persons in accordance with the requirements of NI
43-101.
Cautionary Statement Regarding
Forward-Looking Statements
Certain information contained in this news release
constitutes 'forward-looking information', within the meaning of
the applicable United States and
Canadian legislation, concerning the business, operations and
financial performance and condition of Denison. Generally,
these forward-looking statements can be identified by the use of
forward-looking terminology such as 'potential', 'plans',
'expects', 'budget', 'scheduled', 'estimates', 'forecasts',
'intends', 'anticipates', or 'believes', or the negatives and/or
variations of such words and phrases, or state that certain
actions, events or results 'may', 'could', 'would', 'might' or
'will' 'be taken', 'occur' or 'be
achieved'.
In particular, this news release contains forward-looking
information pertaining to the following: expectations with respect
to the FFT program, scope, timing and the anticipated
results thereof; the interpretation of the results of the
FFT obtained to-date; scope, objectives and interpretations
of the feasibility study process for the
proposed ISR operation for the Phoenix deposit, including metallurgical
testing programs described herein and the interpretation of the
results therefrom; the interpretations of the PFS as
reflected in the PFS Report; and expectations regarding its
joint venture ownership interests and the continuity of its
agreements with its partners and third parties.
Forward looking statements are based on the opinions and
estimates of management as of the date such statements are made,
and they are subject to known and unknown risks, uncertainties and
other factors that may cause the actual results, level of activity,
performance or achievements of Denison to be materially different
from those expressed or implied by such forward-looking statements.
For example, the modelling and assumptions upon which the work
plans for exploration and/or the Wheeler River Project
are based may not be maintained after further work is
completed. In addition, Denison may decide or otherwise be
required to discontinue exploration, testing, evaluation and
development work if it is unable to maintain or otherwise secure
the necessary resources (such as testing facilities, capital
funding, regulatory approvals, etc.). Denison believes that the
expectations reflected in this forward-looking information are
reasonable but no assurance can be given that these expectations
will prove to be accurate and results may differ materially from
those anticipated in this forward-looking information. For a
discussion in respect of risks and other factors that could
influence forward-looking events, please refer to the factors
discussed in Denison's Annual Information Form dated
March 25, 2022 or subsequent
quarterly financial reports under the heading 'Risk Factors'. These
factors are not, and should not be construed as being
exhaustive.
Accordingly, readers should not place undue reliance on
forward-looking statements. The forward-looking information
contained in this news release is expressly qualified by this
cautionary statement. Any forward-looking information and the
assumptions made with respect thereto speaks only as of the date of
this news release. Denison does not undertake any obligation to
publicly update or revise any forward-looking information after the
date of this news release to conform such information to actual
results or to changes in Denison's expectations except as otherwise
required by applicable legislation.
Cautionary Note to United States Investors Concerning
Estimates of Mineral Resources and Mineral Reserves:
This press release may use terms such as
"measured",
"indicated" and/or
"inferred" mineral resources and
"proven" or
"probable" mineral reserves, which are
terms defined with reference to the guidelines set out in the
Canadian Institute of Mining, Metallurgy and Petroleum
("CIM") Definition Standards on Mineral
Resources and Mineral Reserves ("CIM
Standards"). The Company's
descriptions of its projects using CIM Standards may not be
comparable to similar information made public by U.S. companies
subject to the reporting and disclosure requirements under
the United States federal
securities laws and the rules and regulations thereunder.
United States investors are
cautioned not to assume that all or any part of measured or
indicated mineral resources will ever be converted into mineral
reserves. United States investors
are also cautioned not to assume that all or any part of an
inferred mineral resource exists, or is economically or legally
mineable.

View original content to download
multimedia:https://www.prnewswire.com/news-releases/denison-announces-additional-highlights-from-highly-successful-leaching-phase-of-phoenix-isr-feasibility-field-test-301684907.html
SOURCE Denison Mines Corp.