AngloGold Ashanti plc (“AngloGold Ashanti”, “AGA” or the
“Company”) today reported a 2% year-on-year increase in first
quarter gold production1, in line with its plans and despite the
previously reported impact of rains and flooding in Western
Australia on gold production which contributed to a drop of about
15,000oz in production in the first quarter relative to the
previous quarter. The Company reconfirmed its 2024 full-year gold
production guidance and its 2024 annual gold production forecast
for Obuasi in Ghana, which continues its ramp-up.
“This is a good start to the year, with another strong safety
result and a good overall performance from the portfolio,” said
Chief Executive Officer Alberto Calderon. “We’re seeing greater
consistency from most of our operations; in Brazil, both sites have
shown significantly better performance, with greater production
control and stability. Geita and Kibali were strong again, and
Obuasi’s ramp-up remains on track.”
Denver-headquartered AngloGold Ashanti continues to take steps
to close the value gap that exists with its North American peers by
improving safety, relative cost performance and cash conversion,
while increasing the life of its key mines and prioritising
successful development of major projects.
The Company’s Total Recordable Injury Frequency Rate (“TRIFR”)
was 1.08 injuries per million hours worked during the first quarter
of 2024, compared to the most recent average (2022) of 2.66 for
members of the International Council on Metals & Minerals
(“ICMM”). No fatalities were recorded at mines operated by the
Company in the first three months of 2024, for the eleventh
consecutive quarter.
Gold production1 was 2% higher year-on-year at 581,000oz for the
first quarter of 2024, compared to 572,000oz for the first quarter
of 2023, driven mainly by higher recovered grades, and partly
offset by lower tonnes processed. Strong improvements in gold
production versus the first quarter of last year were recorded at
Cuiabá (AGA Mineração) (+55%) and Serra Grande (+40%), where
initiatives have been taken to improve overall performance, as well
as at Kibali (+19%) and at Geita (+16%).
This increase in gold production was partly offset by lower gold
production at Siguiri (-35%), where carbonaceous ore in the Bidini
pit resulted in poor recoveries, and at Tropicana (-17%), where
severe flooding, caused by a tropical cyclone, inundated
underground and open pit mining areas as well as access roads to
the remote site. Both mines have since recovered to normalised gold
production levels. Sunrise Dam (-8%) also suffered from the heavy
rainfall in Western Australia, albeit to a lesser extent than
Tropicana, while gold production at Cerro Vanguardia (-7%) was
lower due to a planned plant stoppage.
At Obuasi, gold production was 54,000oz, in line with the mine
plan, as mining occurred in lower-grade areas. Obuasi’s underground
ore tonnes treated averaged 91,000t/pm for the first three months
of 2024. Underground tonnes treated and grade are expected to
increase in the second half of 2024, supported by additional
development. The mine remains on track to produce an anticipated
275,000oz – 320,000oz of gold in 2024.
As previously reported, gold production at Tropicana was
impacted by heavy rains and flooding during the month of March. The
area in which the Tropicana gold mine is located received 312mm of
rain in a 72-hour period from 9 March, almost 40% higher than its
average annual rainfall. The subsequent flooding interrupted power
supply to the processing plant and required mining operations to be
suspended. Since the flooding, remedial work to recommence
operations was successfully completed and mining and processing has
since restarted. Whilst gold production was impacted in the first
quarter of 2024, and consequently for the first half of 2024, the
Company expects to recover a significant portion of these
production losses in the second half of 2024.
The Company provided gold production guidance for 2024 in
February, which remains unchanged. Gold production is again
expected to be second half weighted, with fourth quarter gold
production expected to be the strongest quarter this year.
1 Excluding the Córrego do Sítio (“CdS”) operation which was
placed on care and maintenance in August 2023.
Quarter
Quarter
Quarter
Year
ended
ended
ended
ended
Mar
Dec
Mar
Dec
2024
2023
2023
2023
Gold produced (1)
– Subsidiaries (2) (3)
oz (000)
505
632
508
2,250
– Joint ventures
oz (000)
76
93
64
343
– Group (2) (3)
oz (000)
581
725
572
2,593
Tonnes treated
Open-pit
– Subsidiaries
tonnes (000)
5,608
6,741
6,065
25,094
– Joint ventures
tonnes (000)
509
478
538
2,065
– Group
tonnes (000)
6,117
7,219
6,603
27,159
Underground
– Subsidiaries
tonnes (000)
2,216
2,596
2,104
9,511
– Joint ventures
tonnes (000)
416
433
342
1,635
– Group
tonnes (000)
2,632
3,029
2,446
11,146
Other
– Subsidiaries
tonnes (000)
726
859
635
3,007
– Joint ventures
tonnes (000)
—
—
—
—
– Group
tonnes (000)
726
859
635
3,007
Total
– Subsidiaries
tonnes (000)
8,550
10,196
8,804
37,612
– Joint ventures
tonnes (000)
925
911
880
3,700
– Group
tonnes (000)
9,475
11,107
9,684
41,312
Recovered grade
Open-pit
– Subsidiaries
g/tonne
1.03
1.30
1.18
1.23
– Joint ventures
g/tonne
0.97
1.72
1.32
1.58
– Group
g/tonne
1.03
1.33
1.19
1.25
Underground
– Subsidiaries
g/tonne
3.72
3.51
3.63
3.48
– Joint ventures
g/tonne
4.48
4.76
3.71
4.54
– Group
g/tonne
3.84
3.69
3.64
3.63
Other
– Subsidiaries
g/tonne
2.32
2.05
1.58
2.05
– Joint ventures
g/tonne
—
—
—
—
– Group
g/tonne
2.32
2.05
1.58
2.05
Total
– Subsidiaries
g/tonne
1.84
1.93
1.80
1.86
– Joint ventures
g/tonne
2.55
3.17
2.25
2.89
– Group
g/tonne
1.91
2.03
1.84
1.95
(1)
On an attributable basis.
(2)
Adjusted to exclude the Córrego do Sítio
(CdS) operation that was placed on care and maintenance in August
2023. CdS produced nil koz, 2koz and 12koz for the quarters ended
31 March 2024, 31 December 2023 and 31 March 2023, respectively.
CdS produced 42koz for the year ended 31 December 2023.
(3)
Includes gold concentrate from the Cuiabá
mine sold to third parties.
Rounding of figures may result in
computational discrepancies
OPERATING HIGHLIGHTS
In the Africa region – subsidiaries, gold production (on
an attributable basis) was 271,000oz for the quarter ended 31 March
2024, compared to 284,000oz for the quarter ended 31 March 2023. In
the Africa region – joint ventures, gold production (on an
attributable basis) was 76,000oz for the quarter ended 31 March
2024, compared to 64,000oz for the quarter ended 31 March 2023.
In Ghana, at Iduapriem, gold production was 62,000oz for
the quarter ended 31 March 2024, compared to 63,000oz for the same
period last year, mainly due to a marginal decrease in recovered
grade, partly offset by higher tonnes processed.
At Obuasi, gold production was 54,000oz for the quarter ended 31
March 2024, in line with the mine plan, compared to 60,000oz for
the same period last year. Total ore tonnes mined and treated were
18% higher when compared with the first quarter of 2023, while
grade was 24% lower, in line with the mine plan. During the first
quarter of 2024, underground ore tonnes treated averaged 91kt/pm,
supported by additional development. The site is contending with
intermittent power disruptions from the public utility. Obuasi is
forecast to produce between 275,000oz and 320,000oz of gold in 2024
and between 325,000oz and 375,000oz of gold in 2025, as it
continues its ramp-up to steady state production.
In Guinea, at Siguiri, gold production (on an
attributable basis) was 41,000oz for the quarter ended 31 March
2024, compared to 63,000oz for the same period last year. Gold
production was lower year-on-year mainly due to poor equipment
availability, lower feed grades and a significant decline in
metallurgical recoveries in the plant, associated with highly
carbonaceous ore feed from parts of the Bidini pit. The mine has
taken delivery of a new excavator in April 2024 and subsequently
prioritised ore from alternative mining areas, which has assisted a
recovery in gold production rates after the quarter-end.
In Tanzania, at Geita, gold production was 114,000oz for
the quarter ended 31 March 2024, compared to 98,000oz for the same
period last year. Gold production was higher year-on-year mainly
due to higher total recovered grade of 2.85g/t, compared to total
recovered grade of 2.70g/t in the same period in 2023. Underground
treated material increased mainly due to a stronger underground
performance, partly offset by a relatively weaker open pit
performance. A strong end to 2023 from the underground mining areas
enabled additions to ore stockpiles, supporting the increased feed
ratio from underground during the first quarter of 2024. In
addition, tonnes treated were higher in the quarter ended 31 March
2024 given the impact of the SAG mill shutdown to replace the girth
gear in the same period last year.
In the DRC, at Kibali, gold production (on an
attributable basis) was 76,000oz for the quarter ended 31 March
2024, compared to 64,000oz for the same period last year. Gold
production was higher year-on-year mainly due to higher recovered
grades resulting from a higher proportion of underground ore tonnes
treated at a higher feed grade as a result of increased underground
efficiency in the quarter ended 31 March 2024 as compared to the
same period in 2023 during which time the mine was converting to
underground multi-lite mining.
In the Americas, gold production (excluding CdS) was
125,000oz of gold (on an attributable basis) for the quarter ended
31 March 2024, compared to 99,000oz for the quarter ended 31 March
2023.
Brazil delivered a significant turnaround following the
operational issues encountered in 2023, with improvements on most
production metrics across both operations. At Cuiabá (AGA
Mineração), gold production was 65,000oz for the quarter ended 31
March 2024, compared to 42,000oz for the same period last year.
Gold production was higher year-on-year mainly due to higher tonnes
processed and higher recovered grades. Cuiabá’s gold production
comprised 21,000oz of gravimetric gold and 44,000oz of
gold-in-concentrate.
At Serra Grande, gold production was 21,000oz for the quarter
ended 31 March 2024, compared to 15,000oz for the same period last
year. Gold production was higher year-on-year mainly due to higher
recovered grades, partly offset by lower tonnes processed.
In Argentina, at Cerro Vanguardia, gold production (on an
attributable basis) was 39,000oz for the quarter ended 31 March
2024, compared to 42,000oz for the same period last year. Gold
production was lower year-on-year mainly due to lower plant
throughput as a result of a planned plant stoppage that was carried
out in March 2024, partly offset by the placement of higher heap
leach tonnes due to operational efficiencies.
In Australia, gold production was 109,000oz of gold (on
an attributable basis) for the quarter ended 31 March 2024,
compared to 125,000oz for the quarter ended 31 March 2023.
At Sunrise Dam, gold production was 56,000oz for the quarter
ended 31 March 2024, compared to 61,000oz for the same period last
year. Gold production was lower year-on-year mainly due to lower
recovered grades, partly offset by higher tonnes processed.
At Tropicana, gold production (on an attributable basis) was
53,000oz for the quarter ended 31 March 2024, compared to 64,000oz
for the same period last year. Gold production was lower
year-on-year mainly due to lower tonnes processed. As noted above,
gold production was impacted by heavy rains and flooding during the
month of March. The area in which the Tropicana gold mine is
located received 312mm of rain in a 72-hour period from 9 March,
almost 40% higher than its average annual rainfall. The subsequent
flooding interrupted power supply to the processing plant and
required mining operations to be temporarily suspended. Since the
flooding, remedial work to recommence operations was successfully
completed and mining and processing has since restarted. The impact
of the rainfall event at Tropicana is expected to continue into the
second quarter of 2024 as water continues to be pumped out of the
Havana 5 pit, which was scheduled to be the main source of open pit
ore in the first half of 2024. The operation expects to process
proportionally more ore from stockpiles whilst ore from Havana 5
has been deferred into the second half of 2024. The impact on gold
production at Tropicana during the first half of 2024 is expected
to be partly offset in the second half of the year, as higher-grade
ore from the Havana 5 pit becomes available and the Havana 4 pit
ramps up production.
GUIDANCE
The Company provided gold production guidance for 2024 in
February, which remains unchanged. Gold production is again
expected to be second half weighted, with fourth quarter gold
production expected to be the strongest quarter this year.
2024
Gold Production (000oz)
Gold Production
– Subsidiaries
2,270 - 2,430
– Joint ventures
320 - 360
– Group
2,590 - 2,790
Estimates assume neither operational or labour interruptions
(including any further delays in the ramp-up of the Obuasi
redevelopment project), or power disruptions, nor further changes
to asset portfolio and/or operating mines. Other unknown or
unpredictable factors, or factors outside the Company’s control,
could also have material adverse effects on AngloGold Ashanti’s
future gold production and no assurance can be given that any
expectations expressed by AngloGold Ashanti will prove to have been
correct. Measures taken at AngloGold Ashanti’s operations together
with AngloGold Ashanti’s business continuity plans aim to enable
its operations to deliver in line with its gold production targets.
Actual gold production could differ from guidance and any
deviations may be significant. Please refer to the Risk Factors
section in AngloGold Ashanti’s annual report on Form 20-F for the
year ended 31 December 2023 filed with the United States Securities
and Exchange Commission (“SEC”).
SAFETY UPDATE
The Company recorded a fatality-free first quarter of 2024 at
the mines it operates. The TRIFR, the broadest measure of workplace
safety, was 1.08 injuries per million hours worked for the first
quarter of 2024 and 0.85 injuries per million hours worked for the
fourth quarter of 2023. By comparison, the most recent ICMM average
(2022) amounts to 2.66 injuries per million hours worked.
UPDATE ON CAPITAL PROJECTS
Obuasi
UHDF trial update
The underhand drift and fill (“UHDF”) mining method trial in
Block 8 Lower progressed well during the first quarter of 2024. The
UHDF trial aims to test the mining method to ensure it can be used
safely and effectively to mine high-grade ore in areas with poor
ground conditions associated with weak graphitic shears and
increasing mining depth.
Milestones achieved in the first quarter of 2024:
- Developed alongside paste-filled 3,300 level drive to expose
and test paste strength.
- Confirmed in-situ paste strength in this parallel drive, and
installed ground support.
- Trialed slag-based binders to increase backfill strength and
reduce curing times.
- Paste backfill commenced on 24 April 2024 and completed
successfully in single pour.
- Paste curing successfully achieved required strength within 14
days.
Next steps:
- Development beneath paste-fill scheduled to commence on 9 May
2024.
- Annualised production rate of 360,000oz is expected in the
third quarter of 2024.
Phase 3
Phase 3 of the Obuasi redevelopment project relates primarily to
capital expenditure required to refurbish and return to service the
KMS shaft and associated infrastructure. This infrastructure
project, which provides direct access to the high-grade Block 11
and other underground mining areas and augments current underground
materials handling capacity, is expected to be completed by the end
of 2024 after being extended during 2023 when mud, encountered on
5,000 and 5,100 levels, had to be cleared.
Phase 3 achieved the following milestones in the first quarter
of 2024:
- Commissioned the first 100 l/sec pumping system of the three
pumping systems planned.
- Completed reaming of the 945m vent raise marking a significant
achievement for a raise bore.
- Completed the man winder upgrades to a modern thyristor
controlled winder.
- Re-entered 50 level to complete the final works ahead of
starting the installation of the lower shaft loading system.
The next key project milestones include:
- Completion of two new ore passes between upper mine and the
rail transport level.
- Completion of new pump stations and pump columns allowing 300
l/sec shaft pumping.
- Installation and commissioning of the new vent shaft.
- Commissioning the rail system.
- Clearing mud on 5,100 level and shaft bottom.
Tropicana
The Havana underground feasibility study commenced in the third
quarter of 2023 and is expected to continue into the first half of
2024. A final investment decision is expected to be made in 2024.
Development of a link drive began during the first quarter of 2024
to provide access to additional drill areas between Tropicana and
Havana. The link drive is expected to ultimately link up with the
Havana underground.
Tropicana ESG renewables
The Tropicana renewable energy project is on track with the
delivery and installation of the wind turbines and solar plant
expected to commence in the second quarter of 2024. The renewable
energy project is expected to be commissioned in the first quarter
of 2025 and, upon completion, is expected to reduce greenhouse gas
(“GHG”) emissions at Tropicana by 65,000 tonnes per annum on
average over the 10-year life of the power purchase agreement.
North Bullfrog Project (“NBP”)
AngloGold Ashanti’s board of directors approved the feasibility
study for the NBP to proceed into detailed engineering. The NBP
received spend approval from AngloGold Ashanti’s Management
Investment Committee to pursue detailed engineering during 2024.
Permitting processes are underway for the NBP. In early April 2024,
the U.S. Bureau of Land Management (“BLM”) published the Notice of
Intent to Prepare an Environmental Impact Statement in the Federal
Register.
Good progress was made during the first quarter of 2024, with
the hiring of the owner’s engineering team largely completed along
with the completion of the front-end engineering and design of the
mill facility, and earthworks for the heavy mobile equipment
assembly yard. The NBP remains on schedule, contingent on receipt
of the requisite permits, to commence anticipated gold production
in 2026.
Merlin
Successful completion of the concept study at the end of 2023
allowed the Merlin project to proceed to the next stage gate of the
pre- feasibility study (“PFS”). The PFS programme is expected to be
performed through the middle of 2025 with a focus on an extensive
drilling programme and further optimisation of development options
considered as part of the framing review in the first half of
2024.
Quebradona
Following the decision of Colombia’s national environmental
agency (“ANLA”) in November 2021 to archive the Company’s
environmental licence application related to the Quebradona
Project, and the confirmation of such decision in April 2022,
AngloGold Ashanti has been working to complete the data acquisition
required by ANLA. AngloGold Ashanti is in the process of preparing
a new Environmental Impact Assessment in connection with its
environmental licence application for the project, which is
currently expected to be submitted to ANLA in 2027. In addition, an
optimised feasibility study is currently underway to implement
improvements in water management, operational flexibility,
maintainability, and constructability.
CORPORATE UPDATE
Proposed Tarkwa / Iduapriem Joint Venture
In March 2023, AngloGold Ashanti announced the proposed joint
venture between the Iduapriem mine and Gold Fields neighbouring
Tarkwa mine in Ghana, that has the potential to create Africa’s
largest gold mine. In addition to leveraging operating efficiencies
to unlock higher grades and enabling an extension of life to at
least 18 years, the proposed joint venture is expected to create
compelling shared value for all stakeholders.
Since the announcement, AngloGold Ashanti and Gold Fields have
been in ongoing engagement with the Government of Ghana with
respect to the proposed transaction. While significant progress has
been made, agreement has not yet been reached. The Company will
continue to keep the market updated on any significant developments
in this regard.
AngloGold Ashanti makes a strategic investment in G2
Goldfields Inc.
On 19 January 2024, AngloGold Ashanti completed its acquisition
of an 11.7% interest in G2 Goldfields Inc., a Canadian gold mining
company with exploration properties in Guyana, South America, for a
consideration of approximately CAD $22.1m.
Appointment of Group Company Secretary
The Company has appointed Ms. Catherine Stead as Group Company
Secretary of AngloGold Ashanti plc with effect from 1 April 2024.
The mandate of Ms. Helen Grantham as Interim Group Company
Secretary expired at the end of March 2024.
Reporting Update
AngloGold Ashanti qualifies as a foreign private issuer (“FPI”)
in the United States for purposes of the US Securities Exchange Act
of 1934, as amended (the “US Exchange Act”), is filing annual
reports on Form 20-F and is furnishing current reports on Form 6-K
with the SEC as the SEC has prescribed for FPIs. AngloGold Ashanti
had previously announced that it was planning to voluntarily file
annual reports on Form 10-K, quarterly reports on Form 10-Q and
current reports on Form 8-K with the SEC, that is, the forms that
the SEC has prescribed for more comprehensive reporting by US
domestic issuers, instead of filing on the reporting forms
available to FPIs, starting with the 10-Q filing for the second
quarter of 2024. AngloGold Ashanti remains committed to voluntarily
transition to reporting on US domestic forms, but now plans to do
so at a later date which will be communicated to the market in
advance of that transition. Until it commences voluntary reporting
on US domestic forms, AngloGold Ashanti will provide full financial
and operational updates, including unaudited condensed consolidated
interim financial statements, on a quarterly basis, which will be
furnished on current reports on Form 6-K with the SEC.
Operations at a glance
for the quarters ended 31
March 2024, 31 December 2023 and 31 March 2023
Gold production
oz (000)
Open-pit treated
000 tonnes
Underground milled /
treated
000 tonnes
Other milled / treated
000 tonnes
Open-pit recovered
grade
g/tonne
Underground recovered
grade
g/tonne
Other recovered grade
g/tonne
Total recovered grade
g/tonne
Mar-24
Dec-23
Mar-23
Mar-24
Dec-23
Mar-23
Mar-24
Dec-23
Mar-23
Mar-24
Dec-23
Mar-23
Mar-24
Dec-23
Mar-23
Mar-24
Dec-23
Mar-23
Mar-24
Dec-23
Mar-23
Mar-24
Dec-23
Mar-23
AFRICA Joint Ventures
76
93
64
509
478
538
416
433
342
—
—
—
0.97
1.72
1.32
4.48
4.76
3.71
—
—
—
2.55
3.17
2.25
Kibali - Attributable 45% (1)
76
93
64
509
478
538
416
433
342
—
—
—
0.97
1.72
1.32
4.48
4.76
3.71
—
—
—
2.55
3.17
2.25
AFRICA Subsidiaries
271
338
284
3,972
4,924
4,138
902
1,118
784
50
87
38
1.07
1.15
1.24
4.59
4.24
4.68
1.05
1.15
1.05
1.71
1.72
1.78
Iduapriem
62
79
63
1,273
1,516
1,233
—
—
—
—
—
—
1.53
1.61
1.58
—
—
—
—
—
—
1.53
1.61
1.58
Obuasi
54
61
60
—
—
—
273
286
235
50
87
38
—
—
—
5.91
6.30
7.74
1.05
1.15
1.05
5.15
5.10
6.81
Siguiri - Attributable 85%
41
56
63
2,084
2,700
2,324
—
—
—
—
—
—
0.61
0.65
0.86
—
—
—
—
—
—
0.61
0.65
0.86
Geita
114
142
98
615
708
581
629
832
549
—
—
—
1.65
2.10
2.06
4.02
3.53
3.38
—
—
—
2.85
2.87
2.70
AUSTRALIA
109
158
125
1,449
1,616
1,716
892
1,002
890
—
—
—
0.83
1.64
0.93
2.45
2.24
2.59
—
—
—
1.45
1.87
1.50
Sunrise Dam
56
62
61
325
377
349
648
631
603
—
—
—
0.98
1.25
1.27
2.19
2.31
2.44
—
—
—
1.78
1.91
2.01
Tropicana - Attributable 70%
53
96
64
1,124
1,239
1,367
244
371
287
—
—
—
0.79
1.76
0.84
3.14
2.13
2.91
—
—
—
1.21
1.85
1.20
AMERICAS (2)
125
136
99
187
201
211
422
476
430
676
772
597
1.86
2.24
2.10
4.53
4.45
3.87
2.41
2.15
1.61
3.03
2.92
2.48
Cerro Vanguardia - Attributable
92.50%
39
38
42
187
178
205
90
125
85
434
432
406
1.86
2.35
2.13
6.96
5.04
8.03
0.57
0.32
0.46
1.71
1.62
1.87
AngloGold Ashanti Mineração (2)
(3)
65
73
42
—
—
—
117
84
109
242
340
191
—
—
—
5.50
9.00
4.70
5.72
4.47
4.05
5.65
5.37
4.29
Serra Grande
21
25
15
—
23
6
215
267
236
—
—
—
—
1.39
1.07
2.98
2.74
1.99
—
—
—
2.98
2.63
1.97
Subsidiaries (2)
505
632
508
5,608
6,741
6,065
2,216
2,596
2,104
726
859
635
1.03
1.30
1.18
3.72
3.51
3.63
2.32
2.05
1.58
1.84
1.93
1.80
Joint Ventures
76
93
64
509
478
538
416
433
342
—
—
—
0.97
1.72
1.32
4.48
4.76
3.71
—
—
—
2.55
3.17
2.25
Total including equity-accounted joint
ventures (2)
581
725
572
6,117
7,219
6,603
2,632
3,029
2,446
726
859
635
1.03
1.33
1.19
3.84
3.69
3.64
2.32
2.05
1.58
1.91
2.03
1.84
(1)
Equity-accounted joint venture.
(2)
Adjusted to exclude the Córrego do Sítio
(CdS) operation that was placed on care and maintenance in August
2023. CdS produced nil koz, 2koz and 12koz for the quarters ended
31 March 2024, 31 December 2023 and 31 March 2023,
respectively.
(3)
Includes gold concentrate from the Cuiabá
mine sold to third parties. Rounding of figures may result in
computational discrepancies.
Administration and corporate information
AngloGold Ashanti plc Incorporated in England & Wales
Registration No. 14654651 LEI No. 2138005YDSA7A82RNU96
Share codes: ISIN: GB00BRXH2664 CUSIP: G0378L100 NYSE: AU
JSE: ANG A2X: ANG GhSE (Shares): AGA GhSE (GhDS): AAD
JSE Sponsor: The Standard Bank of South Africa
Limited
Auditors: PricewaterhouseCoopers Inc.
Offices Registered and Corporate 4th Floor,
Communications House South Street Staines-upon-Thames Surrey TW18
4PR United Kingdom Telephone: +44 (0) 203 968 3320 Fax: +44 (0) 203
968 3325
Australia Level 10, AMP Building 140 St George’s Terrace
Perth, WA 6000 (PO Box Z5046, Perth WA 6831) Australia Telephone:
+61 8 9425 4602 Fax: +61 8 9425 4662
Ghana Gold House Patrice Lumumba Road (PO Box 2665) Accra
Ghana Telephone: +233 303 773400 Fax: +233 303 778155
Directors Executive A Calderon▲ (Chief Executive
Officer) GA Doran▲ (Chief Financial Officer)
Non-Executive MDC Ramos^ (Chairman) KOF Busia△ AM
Ferguson* AH Garner# R Gasant^ SP Lawson# J Magie§ MC Richter#~ DL
Sands# JE Tilk§
* British § Canadian #American ▲Australian ~Panamanian ^South
African △Ghanaian
Officers C Stead Company Secretary
Company secretarial e-mail
Companysecretary@anglogoldashanti.com
AngloGold Ashanti website www.anglogoldashanti.com
Share Registrars United States Computershare Trust
Company, N.A. 150 Royall Street Suite 101 Canton, MA 02021 United
States of America Telephone US: 866-644-4127 Telephone non-US:
+1-781-575-2000 Shareholder Online Inquiries:
https://www-us.computershare.com/Investor/#Contact Website:
www.computershare.com/investor
South Africa Computershare Investor Services (Pty)
Limited Rosebank Towers, 15 Biermann Avenue Rosebank, 2196 (PO Box
61051, Marshalltown 2107) South Africa Telephone: 0861 100 950 (in
SA) Fax: +27 11 688 5218 E-mail: queries@computershare.co.za
Website: www.computershare.com
Ghana Central Securities Depository (GH) LTD 4th Floor,
Cedi House PMB CT 465, Cantonments Accra, Ghana Telephone: +233 302
689313 Fax: +233 302 689315
Ghana depositary NTHC Limited 18 Gamel Abdul Nasser
Avenue Ringway Estate Accra, Ghana Telephone: +233 302 235814/6
Fax: +233 302 229975
AngloGold Ashanti posts information that may be important to
investors on the main page of its website at
www.anglogoldashanti.com and under the “Investors” tab on the main
page. This information is updated periodically. AngloGold Ashanti
intends to use its website as a means of disclosing material
non-public information to the public in a broad, non-exclusionary
manner and for complying with its disclosure obligations.
Accordingly, investors should visit this website regularly to
obtain important information about AngloGold Ashanti, in addition
to following its press releases, documents it files with, or
furnishes to, the United States Securities and Exchange Commission
(SEC) and public conference calls and webcasts. No material on the
AngloGold Ashanti website forms any part of, or is incorporated by
reference into, this document. References herein to the AngloGold
Ashanti website shall not be deemed to cause such
incorporation.
PUBLISHED BY ANGLOGOLD ASHANTI
Forward-looking statements
Certain statements contained in this document, other than
statements of historical fact, including, without limitation, those
concerning the economic outlook for the gold mining industry,
expectations regarding gold prices, production, total cash costs,
all-in sustaining costs, all-in costs, cost savings and other
operating results, return on equity, productivity improvements,
growth prospects and outlook of AngloGold Ashanti’s operations,
individually or in the aggregate, including the achievement of
project milestones, commencement and completion of commercial
operations of certain of AngloGold Ashanti’s exploration and
production projects and the completion of acquisitions,
dispositions or joint venture transactions, AngloGold Ashanti’s
liquidity and capital resources and capital expenditures, the
consequences of the COVID-19 pandemic and the outcome and
consequences of any potential or pending litigation or regulatory
proceedings or environmental, health and safety issues, are
forward-looking statements regarding AngloGold Ashanti’s financial
reports, operations, economic performance and financial condition.
These forward-looking statements or forecasts are not based on
historical facts, but rather reflect our current beliefs and
expectations concerning future events and generally may be
identified by the use of forward-looking words, phrases and
expressions such as “believe”, “expect”, “aim”, “anticipate”,
“intend”, “foresee”, “forecast”, “predict”, “project”, “estimate”,
“likely”, “may”, “might”, “could”, “should”, “would”, “seek”,
“plan”, “scheduled”, “possible”, “continue”, “potential”,
“outlook”, “target” or other similar words, phrases, and
expressions; provided that the absence thereof does not mean that a
statement is not forward-looking. Similarly, statements that
describe our objectives, plans or goals are or may be
forward-looking statements. These forward-looking statements or
forecasts involve known and unknown risks, uncertainties and other
factors that may cause AngloGold Ashanti’s actual results,
performance, actions or achievements to differ materially from the
anticipated results, performance, actions or achievements expressed
or implied in these forward-looking statements. Although AngloGold
Ashanti believes that the expectations reflected in such
forward-looking statements and forecasts are reasonable, no
assurance can be given that such expectations will prove to have
been correct. Accordingly, results, performance, actions or
achievements could differ materially from those set out in the
forward-looking statements as a result of, among other factors,
changes in economic, social, political and market conditions,
including related to inflation or international conflicts, the
success of business and operating initiatives, changes in the
regulatory environment and other government actions, including
environmental approvals, fluctuations in gold prices and exchange
rates, the outcome of pending or future litigation proceedings, any
supply chain disruptions, any public health crises, pandemics or
epidemics (including the COVID-19 pandemic), the failure to
maintain effective internal control over financial reporting or
effective disclosure controls and procedures, the inability to
remediate one or more material weaknesses, or the discovery of
additional material weaknesses, in the Company’s internal control
over financial reporting, and other business and operational risks
and challenges and other factors, including mining accidents. For a
discussion of such risk factors, refer to AngloGold Ashanti’s
annual report on Form 20-F for the year ended 31 December 2023
filed with the United States Securities and Exchange Commission
(SEC). These factors are not necessarily all of the important
factors that could cause AngloGold Ashanti’s actual results,
performance, actions or achievements to differ materially from
those expressed in any forward-looking statements. Other unknown or
unpredictable factors could also have material adverse effects on
AngloGold Ashanti’s future results, performance, actions or
achievements. Consequently, readers are cautioned not to place
undue reliance on forward-looking statements. AngloGold Ashanti
undertakes no obligation to update publicly or release any
revisions to these forward-looking statements to reflect events or
circumstances after the date hereof or to reflect the occurrence of
unanticipated events, except to the extent required by applicable
law. All subsequent written or oral forward-looking statements
attributable to AngloGold Ashanti or any person acting on its
behalf are qualified by the cautionary statements herein.
Non-GAAP financial measures
This communication may contain certain “Non-GAAP” financial
measures. AngloGold Ashanti utilises certain Non-GAAP performance
measures and ratios in managing its business. Non-GAAP financial
measures should be viewed in addition to, and not as an alternative
for, the reported operating results or cash flow from operations or
any other measures of performance prepared in accordance with IFRS.
In addition, the presentation of these measures may not be
comparable to similarly titled measures other companies may
use.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20240509438167/en/
Investor Relations contacts Yatish Chowthee Telephone:
+27 11 637 6273 Mobile: +27 78 364 2080 E-mail:
yrchowthee@anglogoldashanti.com
Andrea Maxey Telephone: +61 08 9425 4603 Mobile: +61 400
072 199 E-mail: amaxey@anglogoldashanti.com
AngloGold Ashanti (NYSE:AU)
Graphique Historique de l'Action
De Jan 2025 à Fév 2025
AngloGold Ashanti (NYSE:AU)
Graphique Historique de l'Action
De Fév 2024 à Fév 2025