This news release constitutes a "designated
news release" for the purposes of the Company's prospectus
supplement dated August 12, 2024, to
its short form base shelf prospectus dated June 21, 2024.
RENO,
Nev., Feb. 21, 2025 /PRNewswire/ - i-80 GOLD
CORP. (TSX:IAU) (NYSE:IAUX) ("i-80 Gold", or the
"Company") is pleased to announce the results of the
preliminary economic assessment (the "PEA") for the Mineral Point
Project ("Mineral Point" or the "Project"). Mineral Point is
situated within the Company's broader Ruby Hill Complex (the
"Complex"). The Complex is located along the southeastern end of
the Battle Mountain-Eureka Trend in northern Nevada, United
States. The PEA demonstrates that Mineral Point has the
potential to become the flagship asset within the Company's gold
portfolio.
"We are pleased to release PEA results for our Mineral Point
project as it marks another key step in our plan to establish i-80
Gold as a mid-tier gold producer with a robust pipeline of growth.
A key driver of future growth, Mineral Point is the largest of our
two planned oxide projects complementing our three high-grade
underground mines in northern Nevada. With significant production scale, a
long mine life, and low costs, Mineral Point is expected to be the
flagship project within our portfolio," stated Richard Young, Chief Executive Officer.
Mineral Point PEA Highlights
Mineral Estimates, Production and Mine Life
- Large open pit heap leach gold mine with a life of mine ("LOM")
of approximately 17 years.
- Annual gold equivalent production(1) of
approximately 280,000 ounces following ramp up.
- Estimated LOM cash costs(2) of $1,270 per ounce and all-in-sustaining
costs(2) of $1,400 per
ounce.
- Updated mineral resource estimate resulting in an indicated
gold mineral resource of 3.4 million ounces at 0.48 grams per tonne
("g/t") and an indicated silver resource of 104.3 million ounces at
15.0 g/t.
- Updated mineral resource estimate resulting in an inferred gold
mineral resource of 2.1 million ounces at 0.34 g/t and an inferred
silver resource of 91.5 million ounces at 14.6 g/t.
Project Economics
- Based on a $2,175/oz gold price,
the Project's undiscounted after-tax cash flows(3)(4)
total $1,470 million with an
after-tax net present value(3)(4)("NPV") of $614 million, assuming a 5% discount rate,
generating an 12% internal rate of return ("IRR").
- Based on spot gold and silver prices of $2,900/oz and $32.75/oz respectively, the Project's
undiscounted after-tax cash flows(2)(3) total
$3,665 million with an after-tax
NPV(3)(4) of $2,092
million, assuming a 5% discount rate, generating an IRR of
27%.
- Mine construction capital, including all pre-production
facilities and equipment is estimated at $708 million. This includes $299 million in mobile equipment for the initial
fleet. In addition, approximately 104 million tonnes of stripping
is required in the first year of production to gain access to the
body of mineralized material costing $287
million.
- LOM sustaining capital is estimated at $388 million, primarily for a leach pad expansion
and mobile equipment maintenance and replacements.
- Total capital includes a contingency of 15%, or $63 million applied to LOM mobile equipment of
$420 million. A 25% contingency of
$122 million has also been applied to
all other capital including earth works, infrastructure and heap
leach expansion costs.
- Project funding is expected to include a combination of cash
flow from the Company's existing operations and a corporate debt
facility.
Mining and Processing
- The primary mining method will be a conventional open pit truck
(24 trucks) and shovel (4 shovels) operation, moving approximately
100 million tonnes per year during a steady state of
production.
- The LOM strip ratio is 2.9:1, excluding capitalized
pre-stripping.
- Material mined will be crushed, stacked and processed at the
heap leach facility located on site at a rate of approximately 23
million tonnes per year during steady state.
- All mineralized material will be placed on leach pads following
two-stage crushing. Processing also includes a Merrill Crowe circuit for the recovery of
silver.
- Ultimate block recovery determined by mineral and rock
alteration type.
- Overall average gold grade processed of 0.39 g/t with an
expected average gold recovery of 78% and an average silver grade
processed of 15.37 g/t with an expected average silver recovery of
41%.
All amounts are in United
States dollars, unless otherwise stated.
A summary of key valuation, cost, and operating metrics is
presented in Table 1 below. For more detailed metrics presented on
an annual basis, see Mineral Point Project Detailed Cash Flow Model
in the Appendix.
Table 1: Summary of PEA Key Operating and Financial
Metrics
Project
Economics
|
Unit
|
|
Gold Price
|
$/oz
|
$2,175
|
Silver Price
|
$/oz
|
$27.25
|
Pre-Tax
NPV(5%)(3)
|
$M
|
$828
|
After-Tax
NPV(5%)(3)(4)
|
$M
|
$614
|
After-Tax
IRR(4)
|
%
|
12 %
|
After-Tax Cash
Flow(4)
|
$M
|
$1,470
|
Production
Profile
|
|
|
Mine Life
|
years
|
16.5
|
Mineralized Material
Mined
|
000s
tonnes
|
358,741
|
Gold Grade of
Mineralized Material Mined
|
g/t Au
|
0.39
|
Silver Grade of
Mineralized Material Mined
|
g/t Ag
|
15.37
|
Waste Tonnes
Mined
|
000s
tonnes
|
1,032,779
|
Capitalized Stripping
Tonnes Mined
|
000s
tonnes
|
104,236
|
Total Tonnes Moved
(incl. heap leach relocation)
|
000s
tonnes
|
1,519,756
|
Total Mineralized
Material Processed
|
000s
tonnes
|
358,741
|
Gold Grade
Processed
|
g/t Au
|
0.39
|
Silver Grade
Processed
|
g/t Ag
|
15.37
|
Strip Ratio (excluding
pre-strip)
|
(waste:mineralized
material)
|
2.9:1
|
Average Gold
Recovery
|
%
|
78 %
|
Average Silver
Recovery
|
%
|
41 %
|
Total Gold
Recovered
|
000s oz
|
3,529
|
Total Silver
Recovered
|
000s oz
|
72,028
|
Total Gold Equivalent
Recovered(1)
|
000's oz
|
4,432
|
Average Annual Gold
Equivalent
Production(1) (LOM)
|
000s oz
|
268
|
Average Annual Gold
Equivalent Production(1)
(following production ramp up)
|
000s oz
|
282
|
Unit Operating
Costs
|
|
|
LOM Operating
Cost
|
|
|
Mineralized Material
Mined
|
$/t mined
|
$2.76
|
Mineralized Waste
Mined
(incl. heap leach pad movement)
|
$/t mined
|
$2.73
|
Processed (heap
leach)
|
$/t
processed
|
$4.30
|
G&A
|
$/t
processed
|
$0.83
|
LOM Total Cash
Costs(2) (net of by-product credit)
|
$/oz
|
$1,270
|
LOM All-in Sustaining
Costs(2) (net of by-product credit)
|
$/oz
|
$1,400
|
Total Capital
Costs
|
|
|
Construction
Capital
|
$M
|
$707.5
|
Capitalized
Stripping
|
$M
|
$287.3
|
Sustaining
Capital
|
$M
|
$388.4
|
Reclamation &
Surety
|
$M
|
$69.8
|
Total Capital &
Closure Costs
|
$M
|
$1,453.1
|
"As a cornerstone of our growth strategy, Mineral Point
transforms our gold production profile and positions i-80 Gold as a
significant silver producer. This project's simple design and
proven technology, combined with its location on a brownfield site,
and our existing understanding of geology, hydrology and
metallurgy, substantially reduces execution risks typically
associated with projects of this scale. The Mineral Point PEA
confirms its potential to become one of Nevada's largest open-pit truck-and-shovel
mining operations," added Matthew
Gili, President and Chief Operating Officer.
Mineral Resource Update
The PEA includes all drilling conducted by the previous owners
up to 2021 when i-80 Gold acquired the property. The updated
mineral resource estimate includes a total of 3,376,000 ounces of
gold with an average grade of 0.48 g/t Au in the indicated category
and 2,117,000 ounces of gold with average grade of 0.34 g/t Au in
the inferred category of resources (see Table 2). Additionally, the
resource hosts 104,332,000 ounces of silver at 15.0 g/t in the
inferred category and 91,473,000 ounces of silver at 14.6 g/t in
the indicated category. The reported mineral resource estimate is
constrained to a selected optimized pit shell using Lerchs-Grossman
(LG) mining software (see Figure 1).
The majority of the economic material is hosted within the
Hamburg Dolomite constrained by the Dunderberg Shale hanging wall
and the Secret Canyon Formation foot wall lithology units.
Grade estimation was carried out using a probability assigned
constrained kriging (PACK) methodology in Vulcan software to define potentially
mineralized high and low-grade domains using different grade
threshold values (see Figure 2). Low and high-grade indicators
were estimated, and an estimated indicator probability value was
selected as the probability threshold to define blocks for the
high-grade domain. A block size of 25 ft × 25 ft × 25 ft
was selected based on a bench height of proposed mining operations,
along with historical mining in the Archimedes pits and future open
pit mining considerations. Soft boundaries for the low-grade
and high-grade domains were used for selection of drill hole
10-foot composites to estimate grade values to blocks.
Updates to the mineral resource estimate include incorporating a
current topographic surface, modified block model coding for
certain fields, and refined specific gravity measurements and
tonnage factor conversions.
In addition to advancing the project permitting, an updated
mineral resource estimate is expected to be completed in 2029 for
inclusion in the planned feasibility study. The updated resource is
expected to include 50,000 meters of drilling targeting additional
sample material for metallurgical test work, resource definition to
upgrade current resource classification, and potential expansion.
The timing of the anticipated feasibility study is planned to align
with the expected completion of the permitting process. The
objective is to have an up-to-date feasibility study at the time
permits are received to support a planned corporate debt facility,
which combined with expected cash flows from the Company's existing
operations, is expected to finance the construction of Mineral
Point.
Table 2: Mineral Point Mineral Resource Estimate Statement as
of December 31, 2024
|
Indicated Mineral
Resources
|
|
|
Tonnes
|
Au
|
Ag
|
Au
|
Ag
|
|
|
(000)
|
(g/t)
|
(g/t)
|
(000
oz)
|
(000
oz)
|
|
Mineral
Point
|
216,982
|
0.48
|
15.0
|
3,376
|
104,332
|
|
Total
Indicated
|
216,982
|
0.48
|
15.0
|
3,376
|
104,332
|
|
|
|
|
|
|
Inferred Mineral
Resources
|
|
|
Tonnes
|
Au
|
Ag
|
Au
|
Ag
|
|
|
(000)
|
(g/t)
|
(g/t)
|
(000
oz)
|
(000
oz)
|
|
Mineral
Point
|
194,442
|
0.34
|
14.6
|
2,117
|
91,473
|
|
Total
Inferred
|
194,442
|
0.34
|
14.6
|
2,117
|
91,473
|
|
Notes to table
above:
I. Mineral resources have an effective date of
December 31, 2024
II. Mineral resources are not
mineral reserves and do not have demonstrated economic
viability
III.
Mineral resources are the portion of Mineral Point that can be
mined profitably by open pit mining
method and processed by heap leaching
IV.
Mineral resources are below an updated topographic
surface
V. Mineral resources are
constrained to economic material inside a conceptual open pit
shell. The main
parameters for pit shell construction are a gold price of $2,175/oz
Au, a silver price of $26.00/oz,
average gold recovery of 77%, average silver recovery of 40%, open
pit mining costs of $3.31/tonne,
heap leach average processing costs of $3.47/tonne, general and
administrative cost of $0.83/tonne
processed, gold refining cost of $1.85/oz, silver refining cost of
$0.50, and a 3% royalty
VI.
Mineral resources are reported above a 0.1 g/t Au cutoff
grade
VII.
Mineral resources are stated as in situ
VIII.
Mineral resources have not been adjusted for metallurgical
recoveries
IX.
Reported units are metric tonnes
X. Reported table numbers
have been rounded as required by reporting guidelines and may
result in
summation discrepancies
|
Economic Analysis
The Project's NPV and IRR in relation to fluctuations in the
long-term gold and silver price are outlined in Table 3.
Table 3: Mineral Point Gold Price Sensitivity After-tax
Analysis
Note: Project NPV at 8% is $296
million.
Project Overview
Mineral Point is a component of the broader Ruby Hill
Complex located along the southeastern end of the Battle Mountain/Eureka gold trend; a northwest-trending
geological belt located in north-central Nevada (see Figure 3). The Project is an open
pit heap leach project and is an extension of the historically
mined Archimedes open pit, which was a major past-producing asset.
Mineral Point contains a large oxide gold and silver deposit, as
well as multiple base metal deposits, and has the potential to
become the Company's largest gold producing asset.
The Complex also includes the Archimedes Underground Project,
comprised of the Ruby Deeps and 426 zone, which are located
immediately northwest and below the historic Archimedes
Pit.
Current processing infrastructure at the Complex includes a
primary and secondary crushing plant, grinding mill, leach pad, and
carbon-in-column circuit, which are designed to process oxide
material. Some of these installations are applicable to Ruby Deeps
within the Archimedes Underground, however, their capacity
does not meet the requirements of Mineral Point, a larger
deposit. The existing heap leach pad on the property will be
moved in years 7 and 14 of operation as the open pit boundaries for
Mineral Point expand.
The Mineral Point deposit is composed of oxide and transitional
material, which is amenable to heap leaching after a two-stage
crush. Appropriate facilities are planned to the west of the
current facilities to minimize haulage distances and optimize
facility layout for the approximately 17-year mine life.
Geology and Mineralization
The Mineral Point deposit is a large, disseminated gold-silver
mineralized zone located immediately west of the Archimedes Pit and
the Archimedes Underground. Mineral Point is hosted within a north
trending and plunging fold hinge. Stratigraphically, most
mineralization is contained within the Cambrian Hamburg dolomite
with lesser quantities in the Dunderberg shale.
Locally the deposit contains high-grade gold and silver in what
were formerly massive sulfide veins that are now oxidized. The
deposit spans a length of over 2.5 kilometers with a width of
nearly 1 kilometer at its widest.
Mining and Processing
The PEA demonstrates an initial mine life of approximately 17
years with an average annual gold equivalent
production(1) of approximately 280,000 ounces of gold
following production ramp up. The PEA represents a preliminary
point-in-time estimate of the mine plan.
Open pit optimization produced a series of nested pit shells
that prioritize early extraction of the most economically viable
and robust material. The mine will be developed in consecutive
phases to manage the stripping ratio and to provide consistent
process feed.
The mine will be accessed by a set of ramps designed for 320-ton
haul trucks on the west side of the pit. Mining will be conducted
by rope and hydraulic shovels with an annual production rate of
23,000,000 processed tonnes.
The PEA incorporates a two-stage crush for the process material
placed on the heap leach. Due to the silver in the deposit, a
Merrill Crowe plant has been
included in the process. A LOM processing schedule is illustrated
in Figure 4.
Capital Cost Summary
Mine construction capital, which includes all pre-production
facilities and equipment, is estimated to total $708 million.
This includes $299 million in mobile equipment for the
initial fleet. In addition, approximately 104 million tonnes
of stripping is required in the first year of production to gain
access to the body or mineralized material costing
$287 million.
LOM sustaining capital is estimated at $388 million, primarily for leach pad expansion
and mobile equipment maintenance and rebuilds.
Mineral Point is expected to generate an estimated $1,470 million in after-tax cash flow over the
current mine life (see Figure 5).
Table 4: Capital Cost Estimates
|
Mine
Construction
|
Sustaining
|
($M)
|
($M)
|
Capitalized
Waste
|
$287.3
|
|
Construction
Capital
|
$290.9
|
|
Mining
Equipment
|
$298.7
|
$14.3
|
Sustaining
Capital
|
|
$306.5
|
Contingency
(15% Mobile Equipment; 25% Facilities)
|
$117.9
|
$67.6
|
Total Capital
Cost
|
$994.8
|
$388.4
|
Operating Cost Summary
The PEA estimates cash costs(2) of $1,270 per ounce of gold and all-in sustaining
costs(2) of $1,400 per
ounce of gold for the LOM (see Table 5).
Figure 6 illustrates these operating costs over
the Project's estimated production profile.
Table 5: Total and Unit Operating Costs
|
Total
Costs
|
Unit
Cost
|
Cost per
Ounce
|
($M)
|
($/t
)
|
($/oz
Au)
|
Mining
|
$3,874.4
|
$10.80
|
$1,097.8
|
Processing
|
$1,542.2
|
$4.30
|
$437
|
G&A
|
$296.6
|
$0.83
|
$84
|
Refining, Royalties
& Net Proceeds Tax
|
$722.3
|
$2.01
|
$205
|
By-Product
Credits
|
($1,953.0)
|
($5.4)
|
($553)
|
Total Operating
Cost/Cash Costs(2)
|
$4,482.6
|
$12.50
|
$1,270.1
|
Closure &
Reclamation
|
$69.8
|
$0.19
|
$19.8
|
Sustaining
Capital
|
$388.4
|
$1.08
|
$110.1
|
All-in Sustaining
Costs(2)
|
$4,940.8
|
$13.77
|
$1,399.9
|
Permitting
Base line work began in the fall of 2024 to allow for Mineral
Point permitting to commence in the second half of 2027 following
regulatory agency approvals of the Lower Archimedes Underground
permitting actions. Baseline studies commenced in late 2024 to
facilitate the permit application. Based on the anticipated
disturbance footprint and associated dewatering, it is expected
that National Environmental Policy Act ("NEPA") related permitting
activities will result in the need to complete an Environmental
Impact Statement ("EIS") through the Bureau of Land Management
("BLM").
Nevada Division of Environmental Protection ("NDEP") permitting
will also be required with modifications to the site Water
Pollution Control Permits, a modification to the Reclamation
Permit, and a revision to the Class II Air Quality Operating
Permit.
Additionally, due to the sensitivity surrounding water in
Diamond Valley, water rights will
be a primary focus based on pumping and potential impacts, in
addition to, the formation of a pit lake following cessation of
mining. With the level of detail that is anticipated for the
various permitting actions, the projected timeline for regulatory
agency approvals is by the end of 2029.
Next Steps to Feasibility Study
A feasibility study in accordance with National Instrument
43-101 - Standards of Disclosure for Mineral Projects ("NI
43-101") and Subpart 1300 of Regulation S-K ("S-K 1300") with
an updated mineral resource estimate is expected to be completed in
2029. The updated resource is expected to include 50,000 meters of
drilling. Below is a summary of additional work to be
conducted.
Resource Delineation and Exploration
- Begin resource conversion drilling to upgrade inferred mineral
resource and to better define the types or mineralized material and
mining limits.
- Include geotechnical drilling in the expansion program to
better understand the pit slopes and operating safety factors.
- Enhance the metallurgical testing with samples specifically
collected to improve the understanding of Mineral Point in contrast
to the other projects within the Ruby Hill Complex.
Permitting
- Commence permitting process.
- Complete hydrology and hydrological studies.
The Company expects to spend approximately $25 million to complete permitting, drilling and
the feasibility studies through before construction commences.
Technical Disclosure and Qualified Persons
The PEA was prepared in accordance with NI 43-101. The PEA will
be filed within 45 days of the Company's related Archimedes press
release issued on February 18, 2025
under the Company's issuer profile on SEDAR+ at www.sedarplus.ca.
An Initial Assessment for the Mineral Point Open Pit Project ("S-K
1300 Report") was also prepared in accordance with S-K 1300 and
Item 601 of the Regulation S-K and the S-K 1300 Report will be
filed on EDGAR at www.sec.gov. Both reports will be available on
the Company's website at www.i80gold.com. The mineral estimates and
project economics are the same under the PEA and the S-K 1300
Report.
The technical information contained in this press release has
been prepared under the supervision of, and has been reviewed and
approved by Aaron Amoroso, MMSA QP
(01548QP) and Jonathan Heiner, P.E., SME-RM
(4143808) of Forte Dynamics, Inc, and Tyler Hill CPG., Vice
President Geology for the Company, who are all qualified persons
within the meaning of NI 43-101 and S-K 1300.
For a description of the data verification, assay procedures and
the quality assurance program and quality control measures applied
by the Company, please see the Company's Annual Information Form
dated March 12, 2024 filed under the
Company's profile on SEDAR+ at www.sedarplus.ca and filed with the
Company's Form 40-F under the Company's profile on EDGAR at
www.sec.gov. Further information about the PEA referenced in this
news release, including information in respect of data
verification, key assumptions, parameters, risks and other factors,
will be contained in the PEA.
The PEA is preliminary in nature and includes an economic
analysis that is based, in part, on inferred mineral resources.
Inferred mineral resources that are considered too speculative
geologically to have for the application of economic considerations
applied to them that would enable them to be categorized as mineral
reserves, and there is no certainty that the results of the PEA
will be realized. Mineral resources do not have demonstrated
economic viability and are not mineral reserves.
Endnotes
- Gold equivalent ounces (AuEq oz) defined as recovered Au oz
plus recovered Ag oz times the price ratio of Ag to Au. AuEq
= Au recovered oz + [(Ag recovered oz) x ($27.25/$2,175)]. LOM overall recoveries for Au and
Ag are 78% and 41% respectively. Production defined as process
recovered ounces.
- This is a non-IFRS/non-GAAP measure. Please see the section
titled "Non-IFRS Performance Measures/Non-GAAP Financial
Performance Measures" below.
- Cash flow and NPV are calculated as of the start of
construction, which is anticipated to commence in early 2030,
subject to obtaining the necessary permits by December 31, 2029, as anticipated.
- After tax metrics assume the Company consumes existing net
operating losses.
About i-80 Gold Corp.
i-80 Gold Corp. is a Nevada-focused mining company with the fourth
largest gold mineral resources in the state of Nevada. The recapitalization plan underway is
designed to unlock the value of the Company's high-grade gold
deposits to create a Nevada
mid-tier gold producer. i-80 Gold's common shares are listed on the
TSX and the NYSE American under the trading symbol IAU:TSX and
IAUX:NYSE. Further information about i-80 Gold's portfolio of
assets and long-term growth strategy is available at
www.i80gold.com or by email at info@i80gold.com.
Forward-Looking Information
Certain statements in this release constitute "forward-looking
statements" or "forward-looking information" within the meaning of
applicable securities laws, including but not limited to,
statements regarding the updated results of the PEA on the Project,
such as future estimates of internal rates of return, net present
value, future production, estimates of cash cost, proposed mining
plans and methods, mine life estimates, cash flow forecasts, metal
recoveries, estimates of capital and operating costs, timing for
permitting and environmental assessments, timing, completion and
results of feasibility studies, and the size and timing of phased
development of the Project. Furthermore, forward-looking statements
are necessarily based upon a number of estimates and assumptions
that, while considered reasonable by the Company as of the date of
such statements, are inherently subject to significant business,
economic and competitive uncertainties and contingencies. With
respect to this specific forward-looking information concerning the
development of the Project, the Company has based its assumptions
and analysis on certain factors that are inherently uncertain.
Uncertainties include: (i) the adequacy of infrastructure; (ii)
geological characteristics; (iii) metallurgical characteristics of
the mineralization; (iv) the ability to develop adequate processing
capacity; (v) the price of gold, silver and other commodities; (vi)
the availability of equipment and facilities necessary to complete
development; (vii) the cost of consumables and mining and
processing equipment; (viii) unforeseen technological and
engineering problems; (ix) natural disasters and/or accidents; *
currency fluctuations; (xi) changes in regulations; (xii) the
compliance by and/or key suppliers with terms of agreements; (xiii)
the availability and productivity of skilled labour; (xiv) the
regulation of the mining industry by various governmental agencies,
including permitting and environmental assessments; (xv) the
ability to raise sufficient capital to develop such projects; (xiv)
changes in project scope or design; and (xv) political factors.
Such statements can be identified by the use of words such as
"may", "would", "could", "will", "intend", "expect", "believe",
"plan", "anticipate", "estimate", "scheduled", "forecast",
"predict" and other similar terminology, or state that certain
actions, events or results "may", "could", "would", "might" or
"will" be taken, occur or be achieved. These statements reflect the
Company's current expectations regarding future events, performance
and results and speak only as of the date of this release and are
expressly qualified in their entirety by this cautionary statement.
Subject to applicable securities laws, the Company does not assume
any obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after
the date of this release.
This release also contains references to estimates of mineral
resources. The estimation of mineral resources is inherently
uncertain and involves subjective judgments about many relevant
factors. Mineral resources that are not mineral reserves do not
have demonstrated economic viability. The accuracy of any such
estimates is a function of the quantity and quality of available
data, and of the assumptions made and judgments used in engineering
and geological interpretation (including estimated future
production from the Project, the anticipated tonnages and grades
that will be mined and the estimated level of recovery that will be
realized), which may prove to be unreliable and depend, to a
certain extent, upon the analysis of drilling results and
statistical inferences that may ultimately prove to be inaccurate.
Mineral resource estimates may have to be re-estimated based on:
(i) fluctuations in commodities prices; (ii) results of drilling,
(iii) metallurgical testing and other studies; (iv) proposed mining
operations, including dilution; (v) the evaluation of mine plans
subsequent to the date of any estimates; and (vi) the possible
failure to receive required permits, approvals and licenses or
changes to existing mining licenses.
Forward-looking statements and information involve significant
known and unknown risks and uncertainties, should not be read as
guarantees of future performance or results and will not
necessarily be accurate indicators of whether or not such results
will be achieved. A number of factors could cause actual results to
differ materially from the results expressed or implied by such
forward-looking statements or information, including, but not
limited to: the Company's ability to finance the development of its
mineral properties; assumptions and discount rates being
appropriately applied to the PEA and S-K 1300 Report, uncertainty
as to whether there will ever be production at the Company's
mineral exploration and development properties; risks related to
the Company's ability to commence production at the Project and
generate material revenues or obtain adequate financing for its
planned exploration and development activities; uncertainties
relating to the assumptions underlying resource and reserve
estimates; mining and development risks, including risks related to
infrastructure, accidents, equipment breakdowns, labour disputes,
bad weather, non-compliance with environmental and permit
requirements or other unanticipated difficulties with or
interruptions in development, construction or production; the
geology, grade and continuity of the Company's mineral deposits;
the uncertainties involving success of exploration, development and
mining activities; permitting timelines; government regulation of
mining operations; environmental risks; unanticipated reclamation
expenses; prices for energy inputs, labour, materials, supplies and
services; uncertainties involved in the interpretation of drilling
results and geological tests and the estimation of reserves and
resources; unexpected cost increases in estimated capital and
operating costs; the need to obtain permits and government
approvals; material adverse changes, unexpected changes in laws,
rules or regulations, or their enforcement by applicable
authorities; the failure of parties to contracts with the company
to perform as agreed; social or labour unrest; changes in commodity
prices; and the failure of exploration programs or studies to
deliver anticipated results or results that would justify and
support continued exploration, studies, development or
operations. For a more detailed discussion of such risks and
other factors that could cause actual results to differ materially
from those expressed or implied by such forward-looking statements,
refer to i-80 Gold's filings with Canadian securities regulators,
including the most recent Annual Information Form, available on
SEDAR+ at www.sedarplus.ca.
Non-IFRS/Non-GAAP Financial Performance Measures
The Company has included certain terms or performance measures
in this news release that commonly used in the gold mining industry
that are not defined under International Financial Reporting
Standards ("IFRS") or United States Generally Accepted Accounting
Principles ("US GAAP"). This includes: all-in sustaining costs per
ounce and cash cost per ounce. Non-IFRS/Non-GAAP financial
performance measures do not have any standardized meaning
prescribed under IFRS or US GAAP, and therefore, they may not be
comparable to similar measures employed by other companies. The
data presented is intended to provide additional information and
should not be considered in isolation or as a substitute for
measures prepared in accordance with IFRS US GAAP and should be
read in conjunction with the Company's financial statements.
Because the Company has provided these measures on a
forward-looking basis, it is unable to present a quantitative
reconciliation to the most directly comparable financial measure
calculated and presented in accordance with IFRS or US GAAP without
unreasonable efforts. This is due to the inherent difficulty of
forecasting the timing or amount of various reconciling items that
would impact the most directly comparable forward-looking IFRS or
US GAAP measure that have not yet occurred, are outside of the
Company's control and/or cannot be reasonably predicted.
Definitions
"All-in sustaining costs" is a non-IFRS or US GAAP financial
measure calculated based on guidance published by the World Gold
Council ("WGC"). The WGC is a market development organization for
the gold industry and is an association whose membership comprises
leading gold mining companies. Although the WGC is not a mining
industry regulatory organization, it worked closely with its member
companies to develop these metrics. Adoption of the all-in
sustaining cost metric is voluntary and not necessarily standard,
and therefore, this measure presented by the Company may not be
comparable to similar measures presented by other issuers. The
Company believes that the all-in sustaining cost measure
complements existing measures and ratios reported by the Company.
All-in sustaining cost includes both operating and capital costs
required to sustain gold production on an ongoing basis. Sustaining
operating costs represent expenditures expected to be incurred at
the Project that are considered necessary to maintain production.
Sustaining capital represents expected capital expenditures
comprising mine development costs, including capitalized waste, and
ongoing replacement of mine equipment and other capital facilities,
and does not include expected capital expenditures for major growth
projects or enhancement capital for significant infrastructure
improvements.
"Cash cost per gold ounce" is a common financial performance
measure in the gold mining industry but has no standard meaning
under IFRS or US GAAP. The Company believes that, in addition to
conventional measures prepared in accordance with IFRS or US GAAP,
certain investors use this information to evaluate the Company's
performance and ability to generate cash flow. Cash cost figures
are calculated in accordance with a standard developed by The Gold
Institute. The Gold Institute ceased operations in 2002, but the
standard is considered the accepted standard of reporting cash cost
of production in North America. Adoption of the standard is
voluntary, and the cost measures presented may not be comparable to
other similarly titled measures of other companies.
For a more detailed breakdown on how these measures were
calculated, please see the table below:
|
Total
Costs
|
Unit
Cost
|
Cost per
Ounce
|
($M)
|
($/t
)
|
($/oz
Au)
|
Mining
|
$3,874.4
|
$10.80
|
$1,097.8
|
Processing
|
$1,542.2
|
$4.30
|
$437
|
G&A
|
$296.6
|
$0.83
|
$84
|
Refining, Royalties
& Net Proceeds Tax
|
$722.3
|
$2.01
|
$205
|
By-Product
Credits
|
($1,953.0)
|
($5.4)
|
($553)
|
Total Operating
Cost/Cash Costs(2)
|
$4,482.6
|
$12.50
|
$1,270.1
|
Closure &
Reclamation
|
$69.8
|
$0.19
|
$19.8
|
Sustaining
Capital
|
$388.4
|
$1.08
|
$110.1
|
All-in Sustaining
Costs(2)
|
$4,940.8
|
$13.77
|
$1,399.9
|
APPENDIX
Mineral Point Open Pit Project Detailed Cash Flow
Model
Mineral
Point
|
UNITS
|
TOTAL /
LOM
|
2030E
|
2031E
|
2032E
|
2033E
|
2034E
|
2035E
|
2036E
|
2037E
|
2038E
|
2039E
|
2040E
|
2041E
|
2042E
|
2043E
|
2044E
|
2045E
|
2046E
|
2047E
|
2048E
|
2049E
|
2050E
|
2051E
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MINING
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mine Life
|
Years
|
16.5
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mineralized
Material
Mined
|
k tonnes
|
358,741
|
|
7,377
|
22,680
|
22,742
|
22,065
|
22,680
|
22,680
|
22,742
|
22,680
|
22,680
|
22,680
|
22,742
|
22,680
|
22,680
|
22,680
|
22,742
|
22,680
|
11,537
|
-
|
-
|
-
|
-
|
|
Expensed Waste
Moved
|
k tonnes
|
1,032,779
|
|
6,244
|
96,926
|
98,462
|
96,662
|
100,239
|
82,750
|
69,303
|
71,561
|
72,913
|
80,701
|
80,377
|
71,389
|
72,956
|
8,629
|
6,224
|
15,872
|
1,571
|
-
|
-
|
-
|
-
|
|
Existing Heap
Leach
Relocation(1)
|
k tonnes
|
24,000
|
|
-
|
-
|
-
|
-
|
-
|
-
|
8,266
|
-
|
-
|
-
|
-
|
-
|
-
|
15,734
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Total Moved
|
k tonnes
|
1,415,520
|
-
|
13,621
|
119,605
|
121,204
|
118,727
|
122,919
|
105,430
|
100,311
|
94,241
|
95,593
|
103,381
|
103,118
|
94,068
|
95,635
|
47,042
|
28,966
|
38,552
|
13,107
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Strip Ratio
|
(waste:mineralized
material)
|
2.9:1
|
|
0.8:1
|
4.3:1
|
4.3:1
|
4.4:1
|
4.4:1
|
3.6:1
|
3.0:1
|
3.2:1
|
3.2:1
|
3.6:1
|
3.5:1
|
3.1:1
|
3.2:1
|
0.4:1
|
0.3:1
|
0.7:1
|
0.1:1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Daily Mining Rate
(Mineralized Material)
|
tpd
|
57,815
|
-
|
20,210
|
62,136
|
62,306
|
60,452
|
62,136
|
62,136
|
62,306
|
62,136
|
62,136
|
62,136
|
62,306
|
62,136
|
62,136
|
62,136
|
62,306
|
62,136
|
31,607
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capitalized
Mining
|
k tonnes
|
104,236
|
|
104,236
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROCESSING
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Heap Leach
Processing
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Tonnes
Processed
|
k tonnes
|
358,741
|
|
7,377
|
22,680
|
22,742
|
22,065
|
22,680
|
22,680
|
22,742
|
22,680
|
22,680
|
22,680
|
22,742
|
22,680
|
22,680
|
22,680
|
22,742
|
22,680
|
11,537
|
|
|
|
|
|
Gold Grade
|
g/t Au
|
0.39
|
-
|
0.26
|
0.35
|
0.38
|
0.61
|
0.34
|
0.34
|
0.40
|
0.41
|
0.39
|
0.48
|
0.50
|
0.37
|
0.47
|
0.41
|
0.24
|
0.28
|
0.32
|
-
|
-
|
-
|
-
|
|
Silver
Grade
|
g/t Au
|
15.37
|
-
|
16.00
|
14.06
|
14.77
|
25.60
|
10.23
|
9.28
|
10.82
|
11.54
|
8.57
|
10.90
|
18.97
|
36.11
|
22.29
|
17.99
|
13.03
|
9.20
|
10.05
|
-
|
-
|
-
|
-
|
|
Contained
Gold
|
'000 oz Au
|
4,525
|
|
60.7
|
253.3
|
277.0
|
433.3
|
246.2
|
249.8
|
294.5
|
300.7
|
280.7
|
348.9
|
364.4
|
269.1
|
344.7
|
301.2
|
175.3
|
206.0
|
118.7
|
|
|
|
|
|
Contained
Silver
|
'000 oz Ag
|
177,293
|
|
3,795
|
10,251
|
10,801
|
18,164
|
7,462
|
6,768
|
7,913
|
8,411
|
6,249
|
7,947
|
13,867
|
26,333
|
16,255
|
13,121
|
9,524
|
6,705
|
3,726
|
|
|
|
|
|
Gold Average
Recovery
|
%
|
78 %
|
-
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
78 %
|
-
|
-
|
-
|
-
|
|
Silver Average
Recovery
|
%
|
41 %
|
-
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
41 %
|
-
|
-
|
-
|
-
|
|
Recovered
Gold
|
'000 oz Au
|
3,529
|
|
50.5
|
210.9
|
223.7
|
348.3
|
200.1
|
204.0
|
243.4
|
244.0
|
215.9
|
275.1
|
274.8
|
209.8
|
207.1
|
210.4
|
143.9
|
168.9
|
98.5
|
|
|
|
|
|
Recovered
Silver
|
'000 oz Ag
|
72,028
|
|
1,601
|
4,250
|
4,456
|
7,318
|
3,125
|
2,783
|
3,284
|
3,471
|
2,578
|
3,273
|
5,579
|
10,533
|
6,507
|
5,248
|
3,809
|
2,717
|
1,495
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Tonnes
Processed
|
k tonnes
|
358,741
|
-
|
7,377
|
22,680
|
22,742
|
22,065
|
22,680
|
22,680
|
22,742
|
22,680
|
22,680
|
22,680
|
22,742
|
22,680
|
22,680
|
22,680
|
22,742
|
22,680
|
11,537
|
-
|
-
|
-
|
-
|
|
Total Gold
Production
|
'000 oz Au
|
3,529
|
-
|
50
|
211
|
224
|
348
|
200
|
204
|
243
|
244
|
216
|
275
|
275
|
210
|
207
|
210
|
144
|
169
|
99
|
-
|
-
|
-
|
-
|
|
Total Silver
Production
|
'000 oz Ag
|
72,028
|
-
|
1,601
|
4,250
|
4,456
|
7,318
|
3,125
|
2,783
|
3,284
|
3,471
|
2,578
|
3,273
|
5,579
|
10,533
|
6,507
|
5,248
|
3,809
|
2,717
|
1,495
|
-
|
-
|
-
|
-
|
|
Total Gold
Equiv.
Production(5)
|
'000 oz Au
|
4,432
|
-
|
70.5
|
264.2
|
279.5
|
440.0
|
239.2
|
238.9
|
284.5
|
287.5
|
248.2
|
316.1
|
344.7
|
341.8
|
288.6
|
276.2
|
191.7
|
203.0
|
117.3
|
-
|
-
|
-
|
-
|
|
Recoverable Ag
ounces remaining (BOP)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVENUE
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gold Price
|
US$/oz Au
|
$2,175
|
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
$2,175
|
|
Silver
Price
|
US$/oz Ag
|
$27.25
|
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
$27.25
|
|
Gold
Revenues
|
US$M
|
$7,668.8
|
-
|
$110
|
$458
|
$486
|
$757
|
$435
|
$443
|
$529
|
$530
|
$469
|
$598
|
$597
|
$456
|
$450
|
$457
|
$313
|
$367
|
$214
|
-
|
-
|
-
|
-
|
|
Silver
Revenue
|
|
$1,953.0
|
-
|
$43
|
$115
|
$121
|
$198
|
$85
|
$75
|
$89
|
$94
|
$70
|
$89
|
$151
|
$286
|
$176
|
$142
|
$103
|
$74
|
$41
|
-
|
-
|
-
|
-
|
|
Total
Revenue
|
|
$9,621.7
|
-
|
$153
|
$ 574
|
$ 607
|
$ 955
|
$ 519
|
$ 519
|
$ 618
|
$ 624
|
$ 539
|
$ 686
|
$ 748
|
$ 741
|
$ 626
|
$ 599
|
$ 416
|
$ 441
|
$ 255
|
|
|
|
|
|
OPERATING
COSTS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mining
Costs
|
US$M
|
$988.6
|
|
$20.3
|
$62.5
|
$62.7
|
$60.8
|
$62.5
|
$62.5
|
$62.7
|
$62.5
|
$62.5
|
$62.5
|
$62.7
|
$62.5
|
$62.5
|
$62.5
|
$62.7
|
$62.5
|
$31.8
|
-
|
|
|
|
|
Mining Costs (Waste
&
Relocation )
|
US$M
|
$2,885.8
|
|
$17.2
|
$267.1
|
$271.3
|
$266.4
|
$276.2
|
$228.0
|
$204.7
|
$197.2
|
$200.9
|
$222.4
|
$221.5
|
$196.7
|
$201.0
|
$49.8
|
$17.2
|
$43.7
|
$4.3
|
-
|
|
|
|
|
Heap Leach
Processing
|
US$M
|
$1,542.2
|
|
$31.7
|
$97.5
|
$97.8
|
$94.9
|
$97.5
|
$97.5
|
$97.8
|
$97.5
|
$97.5
|
$97.5
|
$97.8
|
$97.5
|
$97.5
|
$97.5
|
$97.8
|
$97.5
|
$49.6
|
-
|
|
|
|
|
G&A
|
US$M
|
$296.6
|
|
$6.1
|
$18.7
|
$18.8
|
$18.2
|
$18.7
|
$18.7
|
$18.8
|
$18.7
|
$18.7
|
$18.7
|
$18.8
|
$18.7
|
$18.7
|
$18.7
|
$18.8
|
$18.7
|
$9.5
|
-
|
|
|
|
|
Total Operating
Cost
|
US$M
|
$5,713.2
|
-
|
$75.3
|
$445.9
|
$450.6
|
$440.3
|
$455.0
|
$406.8
|
$383.9
|
$376.0
|
$379.7
|
$401.1
|
$400.7
|
$375.5
|
$379.8
|
$228.5
|
$196.4
|
$222.5
|
$95.3
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Refining &
Sales
|
US$M
|
$42.5
|
|
$0.9
|
$2.5
|
$2.6
|
$4.3
|
$1.9
|
$1.8
|
$2.1
|
$2.2
|
$1.7
|
$2.1
|
$3.3
|
$5.7
|
$3.6
|
$3.0
|
$2.2
|
$1.7
|
$0.9
|
-
|
-
|
-
|
-
|
|
Royalties &
State
Taxes(2)
|
US$M
|
$679.8
|
|
$16.2
|
$38.6
|
$41.1
|
$78.0
|
$32.7
|
$32.2
|
$40.5
|
$40.7
|
$32.0
|
$43.3
|
$51.6
|
$63.9
|
$44.9
|
$46.5
|
$30.7
|
$28.8
|
$18.1
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mining costs
(Mineralized Material)
|
US$/t mined
|
$2.76
|
-
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
-
|
-
|
-
|
-
|
|
Mining Costs
(Waste & Relocation)
|
US$/t mined
|
$2.73
|
-
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.64
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.76
|
$2.04
|
$2.76
|
$2.76
|
$2.76
|
-
|
-
|
-
|
-
|
|
Processing (Heap
leach)
|
US$/t
process
|
$4.30
|
-
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
$4.30
|
-
|
-
|
-
|
-
|
|
G&A
|
US$/t
process
|
$0.83
|
-
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
$0.83
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total
|
US$/t
process
|
$15.9
|
-
|
$10.21
|
$19.66
|
$19.81
|
$19.95
|
$20.06
|
$17.94
|
$16.88
|
$16.58
|
$16.74
|
$17.69
|
$17.62
|
$16.56
|
$16.75
|
$10.08
|
$8.64
|
$9.81
|
$8.26
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CAPITAL
EXPENDITURES
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Initial &
Construction
Capital
|
US$M
|
$707.5
|
$667.0
|
$40.6
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Capitalized
Stripping
|
US$M
|
$287.3
|
-
|
$287.3
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
|
Sustaining
Capital
|
US$M
|
$388.4
|
-
|
$2.6
|
$21.4
|
$8.4
|
$71.0
|
$10.6
|
$9.2
|
$71.5
|
$9.0
|
$9.4
|
$71.8
|
$9.0
|
$9.4
|
$69.1
|
$4.7
|
$5.1
|
$4.0
|
$2.3
|
-
|
-
|
-
|
-
|
|
Total
Capital
|
US$M
|
$1,383.2
|
$667.0
|
$330.5
|
$21.4
|
$8.4
|
$71.0
|
$10.6
|
$9.2
|
$71.5
|
$9.0
|
$9.4
|
$71.8
|
$9.0
|
$9.4
|
$69.1
|
$4.7
|
$5.1
|
$4.0
|
$2.3
|
-
|
-
|
-
|
-
|
|
Reclamation &
Surety
|
US$M
|
$69.8
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$0.5
|
$18.7
|
$12.5
|
$12.5
|
$12.5
|
$3.1
|
$3.1
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CASH COSTS &
AISC
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Cash Costs
(Inc. Royalty) (net of by-
product credit)
|
US$/oz
|
$1,270
|
-
|
$971
|
$1,762
|
$1,670
|
$931
|
$2,024
|
$1,791
|
$1,386
|
$1,331
|
$1,591
|
$1,301
|
$1,107
|
$760
|
$1,216
|
$645
|
$875
|
$1,061
|
$748
|
-
|
-
|
-
|
-
|
|
All-in Sustaining
Costs(3)
|
US$/oz
|
$1,400
|
-
|
$1,033
|
$1,866
|
$1,710
|
$1,136
|
$2,079
|
$1,838
|
$1,682
|
$1,370
|
$1,637
|
$1,563
|
$1,142
|
$807
|
$1,553
|
$670
|
$1,040
|
$1,159
|
$898
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CASH FLOW
ANALYSIS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revenue
|
US$M
|
$9,621.7
|
|
$153
|
$574
|
$607
|
$955
|
$519
|
$519
|
$618
|
$624
|
$539
|
$686
|
$748
|
$741
|
$626
|
$599
|
$416
|
$441
|
$255
|
-
|
-
|
-
|
-
|
|
Operating Costs
Gold
& Royalties
|
US$M
|
($6,435.5)
|
|
($92)
|
($487)
|
($494)
|
($523)
|
($490)
|
($441)
|
($426)
|
($419)
|
($413)
|
($447)
|
($456)
|
($445)
|
($428)
|
($278)
|
($229)
|
($253)
|
($114)
|
-
|
-
|
-
|
-
|
|
Depreciation
|
US$M
|
($1,383.2)
|
|
($28)
|
($279)
|
($79)
|
($73)
|
($47)
|
($49)
|
($60)
|
($68)
|
($62)
|
($80)
|
($95)
|
($74)
|
($76)
|
($100)
|
($70)
|
($86)
|
($56)
|
-
|
-
|
-
|
-
|
|
Net Operating
Income (Pre-Tax)
|
US$M
|
$1,803.0
|
-
|
$33
|
($192)
|
$33
|
$359
|
($18)
|
$29
|
$132
|
$137
|
$64
|
$160
|
$198
|
$222
|
$122
|
$221
|
$117
|
$102
|
$84
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Income
Taxes
|
US$M
|
($263.1)
|
|
($1)
|
-
|
($1)
|
($12)
|
-
|
($1)
|
($4)
|
($5)
|
($8)
|
($29)
|
($38)
|
($39)
|
($22)
|
($46)
|
($24)
|
($18)
|
($15)
|
-
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Net
Income
|
US$M
|
$1,539.9
|
|
$31
|
($192)
|
$32
|
$347
|
($18)
|
$28
|
$128
|
$132
|
$56
|
$131
|
$160
|
$183
|
$101
|
$175
|
$92
|
$85
|
$69
|
-
|
-
|
-
|
-
|
|
Depreciation &
Depletion
|
US$M
|
$1,383.2
|
|
$27.9
|
$278.7
|
$79.2
|
$73.4
|
$47.4
|
$49.2
|
$59.7
|
$68.4
|
$61.6
|
$80.1
|
$95.0
|
$74.3
|
$75.7
|
$100.3
|
$70.3
|
$85.7
|
$56.3
|
-
|
-
|
-
|
-
|
|
Reclamation
|
US$M
|
($69.8)
|
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($0.5)
|
($18.7)
|
($12.5)
|
($12.5)
|
($12.5)
|
($3.1)
|
($3.1)
|
|
Working
Capital
|
US$M
|
-
|
|
$8.7
|
$42.8
|
$0.5
|
($1.2)
|
$1.7
|
($5.6)
|
($2.6)
|
($0.9)
|
$0.4
|
$2.5
|
($0.0)
|
($2.9)
|
$0.5
|
($17.5)
|
($3.7)
|
$3.0
|
($14.7)
|
($11.0)
|
-
|
-
|
-
|
|
Operating Cash
Flow
|
US$M
|
$2,853.3
|
-
|
$68
|
$129
|
$111
|
$419
|
$31
|
$71
|
$184
|
$199
|
$118
|
$213
|
$254
|
$254
|
$176
|
$257
|
$158
|
$155
|
$98
|
($23)
|
($12)
|
($3)
|
($3)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capital
Expenditures
|
US$M
|
($1,383.2)
|
($667)
|
($330)
|
($21)
|
($8)
|
($71)
|
($11)
|
($9)
|
($72)
|
($9)
|
($9)
|
($72)
|
($9)
|
($9)
|
($69)
|
($5)
|
($5)
|
($4)
|
($2)
|
-
|
-
|
-
|
-
|
|
NET CASH
FLOW
|
US$M
|
$1,470.0
|
($667)
|
($263)
|
$107
|
$103
|
$348
|
$20
|
$62
|
$113
|
$190
|
$108
|
$141
|
$245
|
$245
|
$107
|
$252
|
$153
|
$151
|
$96
|
($23)
|
($12)
|
($3)
|
($3)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cumulative
CF
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROJECT
ECONOMICS
(as of Jan. 1 2029)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
After-tax NPV
5%
discounting
|
US$M
|
|
$
614.1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.1 %
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Notes to table
above:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1) Relocation of
existing heap leach material at Ruby Hill
2) Includes 3% royalty
on Au & Ag, and 10% stream on Ag
3) AISC calculated on
cash basis, not accrual basis
4) Project NPV at 8% is
$296 million
5) Gold equivalent
ounces (AuEq oz) defined as recovered Au oz plus recovered Ag oz
times the price ratio of Ag to Au. AuEq = Au recovered oz +
[(Ag recovered oz) x ($27.25/$2,175)].
LOM overall recoveries for Au and Ag are 78% and 41% respectively.
Production defined as process recovered ounces
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|

View original content to download
multimedia:https://www.prnewswire.com/news-releases/i-80-gold-announces-positive-preliminary-economic-assessment-on-the-mineral-point-open-pit-project-nevada-after-tax-npv5-of-614-million-with-an-after-tax-irr-of-12-at-us2-175oz-au-302382216.html
SOURCE i-80 Gold Corp