21 January 2025
QUARTERLY ACTIVITIES REPORT
& 5B
For the quarter ended 31
December 2024
88 Energy Limited (ASX:88E, AIM:88E,
OTC:EEENF) (88 Energy, 88E
or the Company) provides
this summary of activities for the quarter ended 31 December
2024.
Highlights
Project Phoenix (~75% WI)
· Positive Joint Venture
Partner Progress:
Ø Burgundy
Xploration LLC (Burgundy)
settled US$1 million of a outstanding US$4 million cash call,
demonstrating its commitment to the project.
Ø Burgundy
reiterated its intention to provide a full carry for the
anticipated CY25/26 work program including horizontal well
drilling, fracturing costs and long term production test in
exchange for an increased working interest.
· Near-term
Progress:
Ø Ongoing
review by ResFrac to optimise future stimulation and flow design
for a potential extended horizontal well test.
Ø Continued
planning and design for an appraisal well in CY25/26.
Ø Studies
underway into using the existing Franklin Bluffs gravel pad in
order to reduce well costs.
Project Leonis (100% WI)
· Strategic Acreage
Expansion:
Ø Successful
bidder on four (4) additonal lease blocks, to add to the existing
Project Leonis acreage, signficantly increasing the project's scale
and multi-zone exploration potential.
Ø Newly
identified Canning prospect indicates significant resource
potential, with an approximate areal extent of 43km2
(~10,625 acres) and a thick reservoir succession of up to 336
feet.
Ø Formal
award of the new lease blocks is expected H1 CY25.
· Future Potential Well
Test:
Ø Progressing permitting and planning for the Tiri-1 exploration
well, targeting a Q1 CY26 spud.
Ø Farm-out
process underway to secure funding for future drilling.
Namibia PEL 93 (20% WI)
· Promising Initial
Interpretation of new 2D Seismic Data:
Ø Identification of an initial suite of ten (10) significant
independent structural closures within the PEL 93 licence
area.
Ø High-quality seismic acquisition confirmed, with strong
signal-to-noise ratios across all lines.
Ø Leads in
the southern area feature substantial interpreted structural
closures (some up to ~100km2) with clear hydrocarbon
charge potential.
Project Longhorn (~65% WI)
· Production
Performance:
Ø Q4 CY24
production averaged 358 BOE per day gross (~74% oil), down from 391
BOE per day in Q3 due to an incident at the independently operated
and owned gas plant.
· Cash flow
Contribution:
Ø A$0.4
million received in December 2024 for the Q4 CY24 period.
Corporate
·
Cash balance at the end of the quarter of A$7.2
million
· Staff
costs for FY24 of A$1.5 million compared to A$2.8 million in CY23,
representing a 46% reduction.
· Corporate costs for FY24 of A$2.0 million compared to A$2.6
million in FY23, representing a 23% reduction.
Project Phoenix (~75% WI)
Project Phoenix is an oil-bearing
conventional reservoir play identified during the drilling and
logging of Icewine-1 and Hickory-1 and adjacent to offset drilling
and testing. Project Phoenix is strategically located on the Dalton
Highway with the Trans-Alaskan Pipeline System bisecting the
acreage.
Background
The Hickory-1 discovery well was
drilled in February 2023 and flow tested in Q1/Q2 CY24. Testing
focused on the two shallower primary targets, the Upper SFS
(USFS) reservoir,
previously untested, and the SMD-B (SMD) reservoir. Each zone was
independently isolated, stimulated and flowed oil to the surface
either naturally or using nitrogen lift to facilitate efficient
well clean-up. In September 2024, a contingent resource for the
SMD-B, Upper SFS and Lower SFS reservoirs was issued by ERCE. This
contingent resource was added to the pre-existing contingent
resource in the BFF reservoir, issued by NSAI in Q4
CY23.
For full details of the test results
please refer to the ASX announcements dated 2 April 2024 (USFS) and
15 April 2024 (SMD-B); For full details of the combined 2C
Contingent Resource at Project Phoenix, please refer to the ASX
announcement dated 18 September 2024.
Joint Venture
Partner Progress
During the quarter, 88 Energy
advanced discussions with joint venture partner Burgundy.
Burgundy has reaffirmed its commitment to Project Pheonix and
expressed strong interest in providing a full carry to 88 Energy
for the CY25/26 work program in exchange for an additional working
interest in the project. The CY25/26 work program includes drilling
and completing a horizontal test well at the Franklin Bluffs pad
location, along with an extended well test on the SMD-B reservoir.
88 Energy is currently reviewing the terms of the proposal, which
will be subject to further negotiations. Any proposed carry is
subject to Burgundy raising the capital required through a
near-term public listing. Further, Burgundy must pay its
outstanding Hickory-1 cash call on 15 February 2025. There is no
guarantee that any transaction with Burgundy will be completed and
as such, 88E has stated its intention to launch a formal farm-out
process to ensure progress continues, irrespective of the outcome
of Burgundy's listing process. Burgundy settled US$1 million of a
outstanding US$4 million cash call, in a strong demonstration of
its commitment to the project.
Near Neighbour
Activities
The Company is closely monitoring
neighbouring leaseholder, Pantheon Resources PLC
(Pantheon),
following the successful spud of its Megrez-1 well in December
2024, ahead of an extended well test scheduled for Q1 CY25.
Pantheon is targeting the Ahpun Eastern Topset reservoir. This test
is a crucial step towards confirming the commercial viability and
development potential of this reservoir. If successful, it would
enhance the understanding of its production potential, further
supporting the regional development potential and commercialisation
pathways, which will positively impact on the Company's plans to
commercialise Project Phoenix.
Project Leonis (100% WI)
During December 2024, 88 Energy (via
its wholly owned subsidiary, Captivate Energy Alaska, Inc) was
announced as the successful bidder on four (4) additional leases,
covering approximately 10,203 acres immediately adjacent to the
existing Project Leonis leases3. The lease blocks were
specifically targeted due to additional prospectivity identified
and mapped within the deeper Canning Formation reservoir interval.
Upon formal award, expected in H1 CY25, Project Leonis will
comprise 14 leases, across 35,634 contiguous acres.
New Blocks
create an Expanded Multi-Zone Opportunity of Significant
Magnitude
The
expansion of Project Leonis' acreage position and the addition of
the Canning Formation reservoir are significant for 88 Energy. The
Upper Schrader Bluff (USB) reservoir provides an attractive
appraisal drilling opportunity, targeting a Prospective Resource of
381 MMbbls of oil (net mean, unrisked)1,2. The USB
formation is the same proven producing zone as found in nearby
Polaris, Orion and West Sak oil fields to the
north-west.
The addition of the Canning
Formation as a secondary reservoir further enhances Project Leonis'
multi-zone drilling potential. Volumetric analysis of the Canning
Formation reservoir is underway and is anticipated to rival the USB
Prospective Resources in magnitude. In parallel, AVO analysis for
both the USB and Canning intervals continues, aiming to identify
sweet spots and refine drilling locations for a potential
exploration well in H1 CY26.
This multi-zone opportunity presents
a compelling case for future exploration and potential
development.
Guided by modern seismic
re-evaluation and aided by a strategic location, Project Leonis is
firmly positioned as a key asset in 88 Energy's
portfolio.
1. Refer
announcement released to ASX on 4 June 2024 for further
details
2. Cautionary Statement in
relation to Prospective Resources: The estimated quantities of petroleum that may be potentially
recovered by the application of a future development project relate
to undiscovered accumulations. These estimates have both an
associated risk of discovery and a risk of development. Further
exploration, appraisal and evaluation are required to determine the
existence of a significant quantity of potentially recoverable
hydrocarbons. 88E is not aware of any new information or data that
materially affects the information included in the relevant market
announcement and that all material assumptions and technical
parameters underpinning the estimates continue to apply and have
not materially changed.
3. Subject to
adjudication and regulatory approvals prior to formal award
expected in 1H 2025
|
Additional
Prospectivity Identified: Canning Formation
Reprocessing
and interpretation of the Storms 3D seismic data identified a
significant geological feature attributed to basin-wide erosion
during the Mid Campanian. The erosional event led to canyon-like
scours within the Hue shale providing prominent accommodation space
for the subsequent deposition of high-energy Canning Formation
toe-of-slope turbidite sequences. These turbidites, which form a
thick reservoir succession of up to 336 feet thick and have an
aerial extent of 43km2, represent a prospect of
considerable scale. Notably, this feature is yet to be penetrated
by offset wells in the immediate vicinity. However, oil shows,
("oil over shakers") and calculated pay was observed at the
chronostratigraphic equivalent sequence in the Hemi Springs Unit 3
well. The corresponding Canning Interval in Hemi Springs Unit 3 has
porosities of up to 28%, with the reservoir within the canyon-like
feature anticipated to be greater. Analogous to the USB prospect,
high net-to-gross turbidites are being produced from Hue Shale
scours in Conoco Phillips' Tabasco field, just 23 miles to the
north-west. Encouragingly, the Tabasco field outline bears a
remarkable resemblance to the Canning prospect at
Leonis.
Project Leonis: Forward
Program
· Fairweather LLC are engaged to plan and permit the Tiri-1
exploration well, which will target the USB and Canning reservoir
zones at an optimal location within Project Leonis;
· A
comprehensive Quantitative Interpretation (QI) study commenced in Q3 CY24 to
leverage the reprocessed Storms 3D seismic data. The primary
objective of the study is to identify anomalous responses within
the Canning, while the secondary aim is to pinpoint "sweet spots"
within the Upper Schrader Bluff. Results from the AVO and inversion
analysis are expected in early Q1 2025.
· Analysis utilising the Storms 3D seismic data continues,
focusing on refining exploration targets and identifying an optimal
drilling location. The USB reservoir's mapped amplitude anomalies
and fault-bound trapping mechanism highlight its robust technical
case. Similarly, ongoing analysis of the Canning Formation will
enhance the overall understanding of the acreage's
potential.
· Llamas
and Bannister Energy Advisors Ltd (LAB) has been appointed to manage a
relaunched and expanded farm-out process to attract new potential
partners to the project. With the addition of the Canning prospect,
88 Energy believes Project Leonis is a compelling farm-in
opportunity.
Namibia PEL 93 (20% WI)
Namibia is recognised as one of the
world's most prospective, under-explored onshore frontier basins,
offering significant potential for large-scale hydrocarbon
discoveries. Petroleum Exploration Licence 93 (PEL 93) situated in the Owambo Basin,
spans an area more than 10 times the size of 88 Energy's Alaskan
portfolio and over 70 times larger than Project Phoenix.
Historical Exploration Activities:
· Joint Venture (JV)
operator Monitor Exploration Limited (Monitor), which holds a 55% working
interest, utilised geological and geophysical methods to identify
the Owambo Basin.
· Awarded in 2018, PEL 93 contains ten (10) independent
structural closures, identified through airborne geophysical
techniques and partially verified by existing 2D seismic
data.
Recent Developments:
In July 2024, Polaris Natural
Resources Development Ltd (Polaris) acquired 203-line km of 2D
seismic data. Data processing completed in Q4 CY24 identified
significant structural closures with promising hydrocarbon
potential:
· High-quality seismic
data: Strong signal-to-noise ratios
observed across all nine seismic lines.
· Interpretation by
Monitor: Confirmed multiple
significant leads in the southern PEL 93 area, with individual
closures up to ~100 km² in size, showing good vertical relief, and
clear hydrocarbon charge potential.
Forward Activities:
· Independent validation of Monitor's findings, integrating
available datasets, including well logs, airborne geophysics and
soil geochemistry.
· Delivery of a maiden, independently certified Prospective
Resource estimate in H1 2025.
· Identification of drilling locations targeting the Damara
Play.
Regional Context:
· Recon Africa (TSXV: RECO) spudded the Naingopo-1 well in PEL
73 in July 2024, reaching TD of 4,184 metres in November 2024.
Results from extensive evaluations, including wireline logging and
coring, are eagerly anticipated.
· In August 2024, BW Energy Limited farmed into PEL 73 (20%
working interest for US$16 million invested), further demonstrating
industry confidence in the Owambo Basin's potential.
Project Longhorn (~65% WI)
Q4 CY24 production averaged 358
BOE/day gross (~74% oil), down from 391 BOE/day gross in Q3 CY24
due to an incident an independently operated gas plant in late
November, necessitating gas venting. In December 2024, a cash flow
distribution of approximately A$0.4 million was
received.
Peregrine & Umiat (100% WI)
88 Energy was successful in securing
suspensions from the Bureau of Land management Alaska
(BLM) for Project
Peregrine and the Umiat Unit:
· Project Peregrine: Suspension extended
until 30 November 2025.
· Umiat
Unit: Suspension granted until 30 June
2025.
The suspensions relieve 88 Energy of
approximately A$0.6 million in lease rental obligations for
CY25.
Finance
At 31 December 2024, the Company's
cash balance was A$7.2 million. The ASX
Appendix 5B attached to this quarterly report contains the
Company's cash flow statement for the quarter.
The material cash flows for the
period include:
· Burgundy Cash Call: US$1 million (A$1.8 million) received in
Q4 2024, with US$3 million outstanding extended to 15 February 2025
(plus interest and a US$0.1 million extension fee).
· Exploration and Evaluation Expenditure: A$0.6 million,
primarily related to Hickory-1 post-well activities, offset by the
return of an A$0.6 million well bond.
· Staff
and Administration Costs: A$0.85 million, reflecting a significant
reduction in annual corporate costs to A$3.5 million in 2024, down
from A$5.4 million in 2023 (-38%).
Information required by ASX Listing Rule
5.4.3
1. Refer announcement released to ASX on 21
December 2023 regarding Project Peregrine initial suspension, which
was extended by the BLM until 30 November 2025
2. Refer announcement released to ASX on 12
December 2024, regarding highest bidder of 4 additional leases
covering ~10,203 net acres. Award expected in H1
2025.
3. Refer 2024 Half Yearly
announcement released to ASX on 2 September 2024, regarding Umiat
12-month suspension until 30 June 2025
|
Pursuant to the requirements of the ASX Listing
Rules Chapter 5 and the AIM Rules for Companies, the technical
information and resource reporting contained in this announcement
was prepared by, or under the supervision of, Dr Stephen Staley,
who is a Non-Executive Director of the Company. Dr Staley has more
than 40 years' experience in the petroleum industry, is a Fellow of
the Geological Society of London, and a qualified Geologist /
Geophysicist who has sufficient experience that is relevant to the
style and nature of the oil prospects under consideration and to
the activities discussed in this document. Dr Staley has reviewed
the information and supporting documentation referred to in this
announcement and considers the prospective resource estimates to be
fairly represented and consents to its release in the form and
context in which it appears. His academic qualifications and
industry memberships appear on the Company's website, and both
comply with the criteria for "Competence" under clause 3.1 of the
Valmin Code 2015. Terminology and standards adopted by the Society
of Petroleum Engineers "Petroleum Resources Management System" have
been applied in producing this document.
This announcement has been authorised by the
Board.
Media and Investor Relations:
88
Energy Ltd
Ashley Gilbert, Managing
Director
Tel: +61 (0)8 9485 0990
Email:investor-relations@88energy.com
|
|
|
|
Fivemark Partners, Investor and
Media Relations
|
Michael Vaughan
|
Tel: +61 (0)422 602 720
|
|
|
EurozHartleys Ltd
|
|
Dale Bryan
|
Tel: +61 (0)8 9268 2829
|
|
|
Cavendish Capital Markets Limited
|
|
Derrick Lee / Pearl
Kellie
|
Tel: +44 (0)131 220 6939
|
Information required by ASX Listing Rule 5.4.3 - Lease
Schedules as at 31 December 2024
Appendix 5B
Mining exploration entity or
oil and gas exploration entity
quarterly cash flow report
Name of entity
|
88 Energy Limited
|
ABN
|
|
Quarter ended ("current
quarter")
|
80 072 964 179
|
|
31 December 2024
|
Consolidated statement of cash flows
|
Current quarter
$A'000
|
Year to date (12 months)
$A'000
|
|
1.
|
Cash flows
from operating activities
|
-
|
-
|
|
1.1
|
Receipts from customers
|
|
1.2
|
Payments for
|
-
|
-
|
|
|
(a) exploration &
evaluation
|
|
|
(b)
development
|
-
|
-
|
|
|
(c)
production
|
-
|
-
|
|
|
(d) staff
costs
|
(306)
|
(1,527)
|
|
|
(e) administration and
corporate costs
|
(554)
|
(2,019)
|
|
1.3
|
Dividends received (see
note 3)
|
-
|
-
|
|
1.4
|
Interest received
|
26
|
130
|
|
1.5
|
Interest and other costs of finance
paid
|
-
|
-
|
|
1.6
|
Income taxes paid
|
-
|
-
|
|
1.7
|
Government grants and tax
incentives
|
-
|
-
|
|
1.8
|
Other
|
-
|
-
|
|
1.9
|
Net
cash from / (used in) operating activities
|
(834)
|
(3,416)
|
|
|
|
2.
|
Cash flows
from investing activities
|
-
|
-
|
|
2.1
|
Payments to acquire or
for:
|
|
|
(a) entities
|
|
|
(b) tenements
|
(86)
|
(1,484)
|
|
|
(c) property, plant and
equipment
|
-
|
-
|
|
|
(d) exploration &
evaluation
|
(632)
|
(23,829)
|
|
|
(e)
investments
|
-
|
-
|
|
|
(f) other
non-current assets
|
-
|
-
|
|
2.2
|
Proceeds from the disposal
of:
|
-
|
-
|
|
|
(a) entities
|
|
|
(b) tenements
|
-
|
-
|
|
|
(c) property, plant and
equipment
|
-
|
-
|
|
|
(d)
investments
|
-
|
-
|
|
|
(e) other non-current
assets
|
-
|
-
|
|
2.3
|
Cash flows from loans to other
entities
|
-
|
-
|
|
2.4
|
Dividends received (see
note 3)
|
-
|
-
|
|
2.5
|
Other - Joint Venture
Contributions
Other - Distribution from Project
Longhorn
Other - Return of Bond
|
1,837
388
609
|
5,042
2,285
609
|
|
2.6
|
Net
cash from / (used in) investing activities
|
(2,116)
|
(17,377)
|
|
|
|
3.
|
Cash flows
from financing activities
|
-
|
9,696
|
|
3.1
|
Proceeds from issues of equity
securities (excluding convertible debt securities)
|
|
3.2
|
Proceeds from issue of convertible
debt securities
|
-
|
-
|
|
3.3
|
Proceeds from exercise of
options
|
-
|
-
|
|
3.4
|
Transaction costs related to issues
of equity securities or convertible debt securities
|
-
|
(670)
|
|
3.5
|
Proceeds from borrowings
|
-
|
-
|
|
3.6
|
Repayment of borrowings
|
-
|
-
|
|
3.7
|
Transaction costs related to loans
and borrowings
|
-
|
-
|
|
3.8
|
Dividends paid
|
-
|
-
|
|
3.9
|
Other (provide details if
material)
|
-
|
-
|
|
3.10
|
Net
cash from / (used in) financing activities
|
-
|
9,026
|
|
|
|
4.
|
Net increase /
(decrease) in cash and cash equivalents for the
period
|
|
|
|
4.1
|
Cash and cash equivalents at
beginning of period
|
5,509
|
18,183
|
|
4.2
|
Net cash from / (used in) operating
activities (item 1.9 above)
|
(834)
|
(3,416)
|
|
4.3
|
Net cash from / (used in) investing
activities (item 2.6 above)
|
2,116
|
(17,377)
|
|
4.4
|
Net cash from / (used in) financing
activities (item 3.10 above)
|
-
|
9,026
|
|
4.5
|
Effect of movement in exchange rates
on cash held
|
407
|
782
|
|
4.6
|
Cash and cash equivalents at end of period
|
7,198
|
7,198
|
|
5.
|
Reconciliation
of cash and cash equivalents at
the end of the quarter (as shown in the consolidated statement of
cash flows) to the related items in the accounts
|
Current quarter
$A'000
|
Previous quarter
$A'000
|
5.1
|
Bank balances
|
7,198
|
5,509
|
5.2
|
Call deposits
|
-
|
-
|
5.3
|
Bank overdrafts
|
-
|
-
|
5.4
|
Other (provide details)
|
-
|
-
|
5.5
|
Cash and cash equivalents at end of quarter (should equal
item 4.6 above)
|
7,198
|
5,509
|
6.
|
Payments to
related parties of the entity and their
associates
|
Current quarter
$A'000
|
6.1
|
Aggregate amount of payments to
related parties and their associates included in
item 1
|
227
|
6.2
|
Aggregate amount of payments to
related parties and their associates included in
item 2
|
-
|
Note: if any amounts are shown in items 6.1 or 6.2, your
quarterly activity report must include a description of, and an
explanation for, such payments.
|
6.1 Payments relate to
Director and consulting fees paid to Directors. All transactions
involving directors and associates were on normal commercial
terms.
7.
|
Financing
facilities
Note: the term
"facility' includes all forms of financing arrangements available
to the entity.
Add notes as necessary for an understanding of the sources of
finance available to the entity.
|
Total facility amount at quarter end
$US'000
|
Amount drawn at quarter end
$US'000
|
7.1
|
Loan facilities
|
-
|
-
|
7.2
|
Credit standby
arrangements
|
-
|
-
|
7.3
|
Other (please specify)
|
-
|
-
|
7.4
|
Total financing facilities
|
-
|
-
|
|
|
|
7.5
|
Unused financing facilities available at quarter
end
|
-
|
7.6
|
Include in the box below a
description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any
additional financing facilities have been entered into or are
proposed to be entered into after quarter end, include a note
providing details of those facilities as well.
|
|
8.
|
Estimated cash
available for future operating activities
|
$A'000
|
8.1
|
Net cash from / (used in) operating
activities (item 1.9)
|
(834)
|
8.2
|
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
|
(632)
|
8.3
|
Total relevant outgoings
(item 8.1 + item 8.2)
|
(1,466)
|
8.4
|
Cash and cash equivalents at quarter
end (item 4.6)
|
7,198
|
8.5
|
Unused finance facilities available
at quarter end (item 7.5)
|
-
|
8.6
|
Total available funding
(item 8.4 + item 8.5)
|
7,198
|
|
|
|
8.7
|
Estimated quarters of funding available (item 8.6 divided
by item 8.3)
|
4.91
|
Note: if the entity has reported positive relevant outgoings
(ie a net cash inflow) in item 8.3, answer item 8.7 as
"N/A". Otherwise, a figure for the estimated quarters of funding
available must be included in item 8.7.
|
8.8
|
If item 8.7 is less than
2 quarters, please provide answers to the following
questions:
|
|
8.8.1 Does
the entity expect that it will continue to have the current level
of net operating cash flows for the time being and, if not, why
not?
|
|
Answer:
n/a
|
|
8.8.2 Has
the entity taken any steps, or does it propose to take any steps,
to raise further cash to fund its operations and, if so, what are
those steps and how likely does it believe that they will be
successful?
|
|
Answer:
n/a
|
|
8.8.3 Does
the entity expect to be able to continue its operations and to meet
its business objectives and, if so, on what basis?
|
|
Answer:
n/a
|
|
Note: where item 8.7 is less than 2 quarters, all of
questions 8.8.1, 8.8.2 and 8.8.3 above must be
answered.
|
Compliance statement
1 This statement has
been prepared in accordance with accounting standards and policies
which comply with Listing Rule 19.11A.
2 This statement
gives a true and fair view of the matters disclosed.
Date:
21 January 2025
Authorised by: By the
Board
(Name of body or officer authorising
release - see note 4)
Notes
1. This
quarterly cash flow report and the accompanying activity report
provide a basis for informing the market about the entity's
activities for the past quarter, how they have been financed and
the effect this has had on its cash position. An entity that wishes
to disclose additional information over and above the minimum
required under the Listing Rules is encouraged to do so.
2. If
this quarterly cash flow report has been prepared in accordance
with Australian Accounting Standards, the definitions in, and
provisions of, AASB 6:
Exploration for and Evaluation of Mineral Resources and
AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow
report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the
corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from
operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If
this report has been authorised for release to the market by your
board of directors, you can insert here: "By the board". If it has
been authorised for release to the market by a committee of your
board of directors, you can insert here: "By the [name of board committee - eg Audit and Risk Committee]". If it
has been authorised for release to the market by a disclosure
committee, you can insert here: "By the Disclosure
Committee".
5. If
this report has been authorised for release to the market by your
board of directors and you wish to hold yourself out as complying
with recommendation 4.2 of the ASX Corporate Governance
Council's Corporate Governance
Principles and Recommendations, the board should have
received a declaration from its CEO and CFO that, in their opinion,
the financial records of the entity have been properly maintained,
that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and
that their opinion has been formed on the basis of a sound system
of risk management and internal control which is operating
effectively.