TIDMTLEI TIDMTLEP
RNS Number : 7046P
ThomasLloyd Energy Impact Trust PLC
11 October 2023
THE INFORMATION CONTAINED WITHIN THIS ANNOUNCEMENT MAY
CONSTITUTE INSIDE INFORMATION AS STIPULATED UNDER THE UK'S MARKET
ABUSE REGULATION. UPON THE PUBLICATION OF THIS ANNOUNCEMENT, SUCH
INSIDE INFORMATION IS NOW CONSIDERED TO BE IN THE PUBLIC
DOMAIN.
LEI: 254900VC23329JCBR9G82
11 October 2023
ThomasLloyd Energy Impact Trust plc
(the " Company " )
Decision to proceed with the construction of the RUMS Project
and recommended proposals to amend the Company's investment
policy
DECISION TO PROCEED WITH THE CONSTRUCTION OF THE RUMS
PROJECT
On 6 June 2023, the Company announced that its current
investment manager, ThomasLloyd Global Asset Management (Americas)
LLC (the " Investment Manager " ), had indicated that, on the basis
of the significant reduction in equity returns and the increased
risk profile and having regard to the potential non-completion
liabilities and penalties of up to US$33.5 million (the "
Abandonment Penalties " ), it would be inappropriate to proceed to
construct the 200 MW DC solar PV project in Rewa Ultra Mega Solar
Park (the "RUMS Project"), owned via the Company's wholly-owned
Indian subsidiary, SolarArise India Projects Private Limited
("SolarArise"). That announcement also confirmed that, based on
then available information, the Board had concluded that it would
not be in the interests of shareholders for the Company to commit
to funding SolarArise to enable the construction of the RUMS
Project.
Following the announcement on 6 June 2023, the Investment
Manager continued to evaluate the economic options for the future
of the RUMS Project. In light of a further fall in the prices of
solar modules, being the major cost component in constructing a
solar PV project, and having regard to the Investment Manager's
revised recommendation to proceed with the RUMS Project and
independent advice received by the Board based on the information
available at that time, the Board approved, on 7 August 2023, the
funding of pre-construction preparatory work for the RUMS Project
which was required in order to preserve the RUMS Project timeline
outlined by the Investment Manager.
In September 2023, the Investment Manager advised the Board
that, in order for the RUMS Project to be sufficiently constructed
and commissioned by the expected scheduled commercial operation
date of 5 February 2024 ( " SCOD " ) to meet the minimum 125 MW
requirement under the power purchase agreements, and fully
constructed by 31 March 2024, a final decision on whether to
proceed with the RUMS Project was required by 10 October 2023. On
10 October 2023, the Investment Manager advised that proceeding
with the construction of the RUMS Project at an estimated total
cost of approximately US$84 million was estimated, in the base case
scenario, to result in a negative net present value ( " NPV " ) of
approximately US$13 million for the RUMS Project assuming that
construction proceeded to plan, before the benefit of a refinancing
once the RUMS Project is operational which could improve the NPV by
approximately US$1 million . Under other scenarios, especially if
(i) construction is not completed by 31 March 2024 (currently the
last legal date for commissioning Chinese-manufactured solar
modules within India) and/or (ii) the yield once the RUMS Project
is operational falls materially below expectations, the negative
NPV resulting from constructing the RUMS Project could be
materially higher than estimated in the base case scenario. Due to
the extremely tight timeline for completing the RUMS Project on
time, the Board believes that there is a reasonable likelihood of
construction not being fully completed on time. It should also be
noted that the RUMS Project finance is subject to a guarantee from
SolarArise.
In conjunction with considering the direct financial impact of
proceeding to construct the RUMS Project and the associated risks,
including the likelihood that the resulting negative NPV could be
materially higher than estimated in the base case scenario, the
Board has also taken into account the economic loss and other
consequences that would be triggered by failing to construct the
RUMS Project as well as the potential benefits of proceeding with
construction. Based on advice received from the Investment
Manager:
-- aborting the RUMS Project would: (i) crystallise an immediate
write off of US$8.9 million of costs incurred in respect of the
project as at 30 September 2023; (ii) result in the encashment of
US$1.2 million of performance bank guarantees; (iii) potentially
indirectly expose SolarArise to Abandonment Penalties (net of the
performance bank guarantees) of up to US$32.3 million and likely
protracted associated litigation; and (iv) lead to reputational
damage that could adversely impact the value of the SolarArise
platform; and
-- whilst the RUMS Project is clearly not value accretive,
proceeding to construct it would: (i) allow SolarArise to better
manage its liabilities in respect of the RUMS Project, providing
greater certainty compared to a very uncertain process of aborting
it, both in terms of the value of any potential Abandonment
Penalties and the expected timeline for settlement; and (ii) add a
further 200 MW of capacity to the SolarArise platform and, once
operational as part of a wider portfolio, may facilitate a more
attractive exit of SolarArise in any future liquidity event.
Based on the advice received from the Investment Manager and the
Company's other appointed advisers (not including Octopus Energy
Generation, which, as previously announced, the Company is
proposing to appoint as its transitional investment manager), the
Board has concluded that proceeding with the construction of the
RUMS Project may now be the less value destructive option for
shareholders. Accordingly, the Board has agreed to provide funding
of up to US$20 million by way of an INR denominated external
commercial borrowings loan from the Company to SolarArise to enable
construction of the RUMS Project to proceed.
Recommended proposals to amend the Company's investment
policy
The Company's only development project (the "TT8 Project") is a
150 MW DC solar PV project, held by a special purpose vehicle of
SolarArise. The Board was advised by the Investment Manager in
August 2023 to proceed with development of the project and sign the
power purchase agreement with Maharashtra State Electricity
Distribution Company Limited.
The provision of funding for the construction of the RUMS
Project, at the same time as continuing with the TT8 Project, may
result in the fair value of the Company's Indian portfolio
exceeding 50 per cent. of its gross asset value, which is the
single country limit in the Company's investment policy.
Accordingly, to ensure that there is no breach of the Company's
investment policy, a material change to the policy is required. The
proposed changes to the investment policy will permit the Company
to exclude the amount of any funds invested in the RUMS Project up
to completion of commissioning from the assessment of the single
country limit. The revised investment policy will also contain a
commitment that no further sustainable energy infrastructure assets
shall be acquired, or projects committed to, with exposure to India
until the Company is in compliance with the single county limit.
The Company is also proposing clarificatory changes to its gearing
policy.
A circular detailing the proposed changes to the Company's
investment policy, and convening a general meeting at which a
resolution to approve the changes will be proposed (the
"Resolution"), is today being posted to shareholders; copies will
shortly be available for inspection on the Company's website,
www.tlenergyimpact.com , and at the National Storage Mechanism,
which is located at
https://data.fca.org.uk/#/nsm/nationalstoragemechanism .
SHAREHOLDER SUPPORT FOR THE proposed changes to the investment
policy
The Company has received signed agreements from shareholders
representing approximately 69 per cent. of the voting rights of the
Company indicating their support for the proposed changes to the
investment policy and confirming their intention to vote in favour
of the Resolution.
The person responsible for arranging the release of this
announcement on behalf of the Company is Rachel Orebote of JTC (UK)
Limited, the Company Secretary.
Enquiries:
ThomasLloyd Energy Impact Trust plc Tel: +4 4 (0)20 3757 1892
Sue Inglis, Chair
Shore Capital (Joint Corporate Broker) Tel: +44 (0)20 7408 4050
Robert Finlay / Rose Ramsden (Corporate)
Adam Gill / Matthew Kinkead / William Sanderson (Sales)
Fiona Conroy (Corporate Broking)
Peel Hunt LLP (Joint Corporate Broker) Tel: +44 (0)20 7418 8900
Luke Simpson / Huw Jeremy (Investment Banking Division)
Alex Howe / Richard Harris / Michael Bateman / Ed Welsby (Sales)
Smith Square Partners LLP Tel: +44 (0)20 3696 7260
(Financial Adviser to the Company)
John Craven / Douglas Gilmour
Camarco (PR Adviser) Tel: +44 (0)20 3757 4982
Louise Dolan / Eddie Livingstone-Learmonth / Phoebe Pugh thomaslloyd@camarco.co.uk
, the news service of the London Stock Exchange. RNS is approved by
the Financial Conduct Authority to act as a Primary Information
Provider in the United Kingdom. Terms and conditions relating to
the use and distribution of this information may apply. For further
information, please contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms
and conditions, to analyse how you engage with the information
contained in this communication, and to share such analysis on an
anonymised basis with others as part of our commercial services.
For further information about how RNS and the London Stock Exchange
use the personal data you provide us, please see our Privacy
Policy.
END
PFUGPGCPUUPWPUU
(END) Dow Jones Newswires
October 11, 2023 02:00 ET (06:00 GMT)
Thomaslloyd Energy Impact (LSE:TLEP)
Graphique Historique de l'Action
De Nov 2024 à Déc 2024
Thomaslloyd Energy Impact (LSE:TLEP)
Graphique Historique de l'Action
De Déc 2023 à Déc 2024