Marathon Gold Corporation (“Marathon” or the “Company”;
TSX: MOZ) is pleased to provide an update on progress at
its 100% owned Valentine Gold Project located in central
Newfoundland (the “Project”) for the quarter ended September 30,
2023. Highlights include:
- The Project has
marked one full year of construction since early works commenced in
October 2022. More than 800,000 hours of site work
have been completed without a lost time incident;
- The Project’s
overall budget and schedule remain in line with previous guidance,
with first gold on track for the first quarter of 2025;
- At quarter end,
overall completion stood at 50%;
- During the
quarter, important de-risking of the Project was achieved with the
completion of earthworks at the process plant and significant
advancement of earthworks at the Tailings Management Facility. Rock
placement for the tailings dam footprint is now
96% complete;
- During the
quarter, 1.56 Mtonnes of overburden and
construction waste rock were mined from the Leprechaun and Marathon
Pits, with record monthly performance of 0.58
Mtonnes during September. Project-to-date, 3.87
Mtonnes have been moved, ably supporting the Project’s
construction schedule, and at mining costs trending below
budget;
- During the
quarter, Marathon was informed by Impact Assessment Agency of
Canada that the addition of the Berry Deposit to the Project’s
permitted mine plan does not require a new impact assessment under
the Impact Assessment Act;
- Currently,
634 Marathon employees and contractors are
employed or providing services to the Project, 85%
of whom are residents of Newfoundland and Labrador; and
- The Project now
has permanent camp capacity of 424 beds and is on
track to be connected to NL Hydro grid power by the end of the
year, one full year before mill commissioning.
Matt Manson, President and CEO, commented: “The
summer construction season has seen rapid progress at the Valentine
Gold Project. We completed earthworks at our Process Plant, and
since August have been preparing concrete foundations and footings
for mill equipment and the mill building. Enclosing of the grinding
building is on schedule for completion before the end of the year.
We have been particularly encouraged by the progress achieved at
our Tailings Management Facility, the most important earthworks
element of the Project. Mining of construction materials is
comfortably supporting TMF progress, and we are consistently
achieving all requisite engineering and geotechnical standards. Our
cost and schedule-to-complete estimates remain consistent with our
previous reporting, and our procurement and detailed engineering
are approaching completion. Most importantly, we are able to report
a consistently safe and environmentally protected work site after
one full year of construction.”
A video showing 12 months of construction at the
Project is available at https://vimeo.com/870829907?share=copy.
Figure 1: Valentine Process Plant Site, Looking
West, October 2023.
Figure 2: Construction of the Tailings Management Facility,
Looking West. October 2023
Site Progress ReportProcess
Plant Site Preparation and Foundations
During the third quarter, earthworks excavations
were completed at the location of the SAG and Ball mills, the CIL
tank farm, the tailings thickener, and the crushed ore stockpile
and reclaim area. All load bearing sites successfully achieved
geotechnical specifications for foundations, and the first
foundation concrete pours commenced in July. By September 30, 2023,
all foundations had been completed, concrete work for the SAG and
Ball mill’s sloped piers was well advanced (Figure 3), and concrete
pours for the grinding building’s footings and piers was ongoing.
To date, approximately 5,500 m3 of concrete has been poured at the
Project.
During the quarter, pads were also completed at
the Mine Maintenance Facility site, the ROM stockpile, and the
conveyor alignment. Earthworks excavation of the primary crusher
location was completed, and construction of the crusher’s
Mechanically Stabilized Earth (MSE) retaining wall with gabion
baskets had commenced (Figure 3).
Ongoing civils works at the process plant site
through the fourth quarter will include the completion of the SAG
and Ball mill’s piers, completion of the grinding building wall
footings, completion of the MSE wall, and the pouring of lean
concrete and foundations for the primary crusher pad. Structural
steel for the grinding building’s exterior frame has been delivered
to site, with enclosing of the building scheduled for the end of
the year.
Figure 3: Concrete Pedestals for the SAG and
Ball Mills and Grinding Building Steel Work (left). Gabion Basket
Installation for MSE Wall at Crusher Location (right). October
2023
Mining
Mining during the Project’s construction period
is ongoing to generate rock for haul roads, pads and the TMF.
During the third quarter, overburden removal and mining was
transferred to the Marathon Pit due to its close proximity to the
TMF. Overburden stripped was consistent with forecast, and pioneer
mining proceeded quickly to the establishment of the first mining
benches. During the third quarter, a total of 1.56 Mtonnes of
material was moved, representing an average daily mining volume of
17,000 tonnes/day. Project-to-date, 3.4 Mtonnes of waste rock
construction material and 481 ktonnes of overburden material had
been mined, slightly exceeding forecast targets. Project to date,
cumulative mining costs are C$5.44/tonne compared to a budget
C$5.32/tonne. Mining costs are trending lower as high
productivities are achieved consistently, and averaged C$4.93/tonne
during the third quarter.
Tailings Management Facility (TMF)
The Project’s TMF will be a thickened tailings
facility with a capacity of 31.6 Mtonnes. It is formed by
constructing a perimeter zoned rockfill embankment dam, which will
be raised in 6 phases during the first 10 years of the Project. The
upstream face of the dam will be lined with a geomembrane which is
anchored into low-permeability foundation till, and which will
extend approximately 100m upstream of the dam toe and overlay
granular crushed rock filter layers.
Construction of the Phase 1 main dam commenced
in July with preparation of the till and bedrock foundation, and
subsequent placement of mine waste rock (“Zone 6” material with 600
mm minus sizing). As of September 30, 2023, 98% of the main dam
footprint had been excavated, and 96% of the Zone 6 rockfill had
been placed, having achieved geotechnical subgrade approval.
Production and placement of the upstream filter
layers which consists of two zones of crushed rock (“Zone 1”
material at 25 mm minus, and “Zone 2” material at 75 mm minus)
commenced in late August. As of September 30, 2023, 90% of the
subgrade material underlying the upstream filter layer had been
excavated, and 27% of the Zone 1 and Zone 2 crushed granular fill
had been placed (Figure 4).
Geomembrane liner deliveries commenced during
the quarter, with installation scheduled to commence in the second
quarter of 2024.
Figure 4: Construction of the TMF. Spreading
Filter Layers for Geomembrane Liner Placement. September 2023
Permanent Camp, Powerline and Infrastructure
During the quarter, the final dormitory of the
permanent camp was completed and approved for occupancy, bringing
total bed capacity to 424. Average camp occupancy during September
was between 280 and 340 persons. Excess camp capacity is available
if required in support of the construction schedule.
The Project’s 66 kV powerline has been completed
over its full 40 km length and ready to be connected to the on-site
transformer station (Figure 5). Subsequent to the quarter end,
modifications to the NL Hydro Star Lake Generating Station hook-up
commenced, as well as installation of the Project site’s power
distribution network. The Project site is expected to be energised,
on budget and schedule, prior to the end of the year. This means
that mill construction and camp operations in 2024 will be on grid
power, minimising the need for diesel generators and limiting
on-site fuel requirements to the mobile mining fleet and the TMF
construction contractor. 91% of NL Hydro’s power is generated from
renewable, hydroelectric sources, giving the Valentine Gold Project
a comparatively low carbon footprint compared to similarly sized
mining projects.
During the third quarter, upgrades to the
Project’s 80 km access road from Millertown commenced, so as to
provide greater reliability during the spring 2024 construction
season and into mine operations. This work has included culvert
installation, ditching, raising of the road-bed and applying new
road top coats of crushed rock. This work is being carried out by a
local contractor based in the community of Millertown and is
proceeding well (Figure 5).
The 80km road from Millertown to the Valentine
Gold Project is public infrastructure, and with its connection to
the historic Burgeo Highway it provides an alternate
cross-Newfoundland vehicle route. Marathon’s investment in this
road, including the 2022 replacement of the Victoria River Bridge,
creates a significant societal and economic benefit for the
Province of Newfoundland and Labrador.
Figure 5: The Project’s 66kv Powerline, Now
Complete from the Star Lake Generating Station to the Project Site
(left). Ongoing Road Improvement Works (right).
Engineering and Procurement
Detailed engineering is substantially complete
on all aspects of the Project, with the exception of additional
design hours to accommodate certain changes to mill building design
in the areas of concrete, structural & layout design described
in Marathon’s Second Quarter report (see Marathon news release
dated 2nd August, 2023).
Procurement stands at approximately 72%
complete. Marathon reports procurement on the basis of all Project
goods and services on an earned progress basis. All long-lead
items, including major mill components and the Project’s mobile
mining fleet, have been procured. The SAG and Ball mills, including
motors, are expected to be delivered to the site in the first
quarter of 2024. Major construction packages remaining outstanding
at the quarter end were the Structural, Mechanical and Piping, and
Electrical and Instrumentation packages for the mill.
Schedule and Budget
The Project remains on schedule to achieve mill
commissioning in the fourth quarter of 2024 and first gold in the
first quarter of 2025. The Project’s critical path is the
development of the process plant, including its foundations,
building enclosure, equipping, and commissioning as well as the
TMF. Earthworks associated with the development of the TMF are
scheduled over two summer construction seasons and one winter
season so as to allow operating tailings commissioning in the
second half of 2024.
Capital costs incurred from the start of early
works in October 2022 to the end of September 2023 were C$190
million with C$318 million committed (excluding sunk costs of C$71
million incurred prior to October 2022). The Project’s cost to
complete, including contingency, was estimated at C$463 million as
at October 31, 2022 and $318 million at September 30, 2023. As at
September 30, 2023, Marathon had approved contingency draws of
C$13.2 million from a total contingency reserve of C$38.9 million.
Unused contingency stood at C$25.7 million, or 66%. Contingency
draws are approved on a package-by-package basis as construction
proceeds. During the quarter, C$3.9 million of unused contingency
on finalised construction packages was transferred to the
Management Reserve, which now stands at C$4.1 million.
Human Resources
At the end of September 30, 2023, 634 persons
were employed directly or contracted to the Project. Marathon
collects diversity employment data on the basis of voluntary
declaration. On this basis, 15% of the persons employed by the
Project are female and 8% are Indigenous persons. 23% are residents
of the six communities within the Project’s socio-economic area of
influence (Millertown, Buchans, Buchans Junction, Grand Falls
Windsor, Badger and Bishop’s Falls) and 85% are residents of the
province of Newfoundland and Labrador.
Construction Permitting and Berry
Environmental Assessment
The Valentine Gold Project was released from its
Newfoundland and Labrador Environmental Assessment (“EA”) on March
17, 2022, and its federal EA process on August 24, 2022. Permitting
for specific site activities has continued throughout the mine
development process in accordance with the construction schedule.
At the end of September 30, 2023, overall permitting progress stood
at 97% complete, with site permitting proceeding smoothly in
support of the construction schedule.
The Berry Complex (pit, waste rock facility and
associated infrastructure) is subject to further EA requirements to
identify, assess and mitigate potential environmental effects
during all project phases, including construction, operation,
decommissioning, rehabilitation and closure, and post-closure.
Marathon filed EA registration materials for Berry with the
Newfoundland and Labrador Department of Environment and Climate
Change, EA Division, (“NLDECC”) and the Impact Assessment Agency of
Canada (“IAAC”) on August 11, 2023, following the completion of an
effects assessment and consultation with both the provincial and
federal regulators, Indigenous groups, communities, and stakeholder
organizations.
In late August 2023, Marathon was informed by
IAAC that changes to the Project to accommodate Berry do not
require a new impact assessment under the Impact Assessment Act
(“IAA”). This means that, federally, the addition of the Berry
Complex is considered a change to the Designated Project referenced
in the August 2022 Decision Statement of the Minister of
Environment and Climate Change Canada, and potential amendments to
the Decision Statement are now being considered. Provincially, the
assessment of Berry is considered a “new undertaking” and requires
the submission of a new EA registration with the NLDECC. Marathon
expects to be notified shortly by the NL Minister of Environment
and Climate Change if additional information is required to
complete the provincial assessment process, which is expected take
the form of an Environmental Preview Report.
Marathon anticipates the Berry review processes
will be completed during 2023 and 2024, well in advance of the
scheduled commencement of mining at Berry in the second quarter of
2025.
Qualified Persons
Disclosure of a scientific or technical nature
in this news release has been approved by Mr. Paolo Toscano, P.Eng.
(Ont.), Senior Vice President, Projects, Engineering and
Construction for Marathon, Mr. James Powell, P.Eng. (NL), Vice
President, Regulatory and Government Affairs for Marathon and Mr.
David Ross, P.Geo. (NL), Vice President of Geology and Exploration
for Marathon. Mr. Toscano, Mr. Powell and Mr. Ross are qualified
persons under National Instrument (“NI”) 43-101.
About Marathon
Marathon (TSX:MOZ) is a Toronto based gold
company advancing its 100%-owned Valentine Gold Project located in
the central region of Newfoundland and Labrador, one of the top
mining jurisdictions in the world. The Project comprises a
series of five mineralized deposits along a 32-kilometre system. A
December 2022 Updated Feasibility Study outlined an open pit mining
and conventional milling operation producing 195,000 ounces of gold
a year for 12 years within a 14.3-year mine life. The Project was
released from federal and provincial environmental assessment in
2022 and construction commenced in October 2022. The Project has
estimated Proven Mineral Reserves of 1.43 Moz (23.36 Mt at 1.89
g/t) and Probable Mineral Reserves of 1.27 Moz (28.22 Mt at 1.40
g/t). Total Measured Mineral Resources (inclusive of the Mineral
Reserves) comprise 2.06 Moz (29.23 Mt at 2.19 g/t) with Indicated
Mineral Resources (inclusive of the Mineral Reserves) of 1.90 Moz
(35.40 Mt at 1.67 g/t). Additional Inferred Mineral Resources are
1.10 Moz (20.75 Mt at 1.65 g/t Au). Please see the NI 43-101
Technical Report “Valentine Gold Project, NI 43-101 Technical
Report and Feasibility Study” effective November 30, 2022,
Marathon’s Annual Information Form for the year ended December 31,
2022 and other filings made with Canadian securities regulatory
authorities available at www.sedar.com for further details and
assumptions relating to the Valentine Gold Project.
For more information, please
contact:
Amanda MalloughManager, Investor RelationsTel: 416
855-8202amallough@marathon-gold.com |
Matt MansonPresident & CEOmmanson@marathon-gold.com |
Julie RobertsonCFOjrobertson@marathon-gold.com |
To find out more information on Marathon Gold
Corporation and the Valentine Gold Project, please visit
www.marathon-gold.com.
Cautionary Statement Regarding
Forward-Looking Information
Certain information contained in this news
release, constitutes forward-looking information within the meaning
of Canadian securities laws (“forward-looking statements”). All
statements in this news release, other than statements of
historical fact, which address events, results, outcomes or
developments that Marathon expects to occur are forward-looking
statements. Forward-looking statements include statements that are
predictive in nature, depend upon or refer to future events or
conditions, or include words such as “expects”, “anticipates”,
“plans”, “believes”, “estimates”, “considers”, “intends”,
“targets”, or negative versions thereof and other similar
expressions, or future or conditional verbs such as “may”, “will”,
“should”, “would” and “could”. We provide forward-looking
statements for the purpose of conveying information about our
current expectations and plans relating to the future, and readers
are cautioned that such statements may not be appropriate for other
purposes. More particularly and without restriction, this news
release contains forward-looking statements and information about
the FS and the results therefrom (including IRR, NPV5%, Capex, FCF,
AISC and other financial metrics and economic analysis), the
realization of mineral reserve and mineral resource estimates, the
future financial or operating performance of the Company and the
Project, capital and operating costs, the ability of the Company to
obtain all government approvals, permits and third-party consents
in connection with the Company’s exploration, development and
operating activities, the potential impact of COVID-19 on the
Company, the Company’s ability to successfully advance the Project
and anticipated benefits thereof, economic analyses for the
Valentine Gold Project, processing and recovery estimates and
strategies, future exploration and mine plans, objectives and
expectations and corporate planning of Marathon, future
environmental impact statements and the timetable for completion
and content thereof and statements as to management's expectations
with respect to, among other things, the matters and activities
contemplated in this news release.
Forward-looking statements involve known and
unknown risks, uncertainties and assumptions and accordingly,
actual results and future events could differ materially from those
expressed or implied in such statements. You are hence cautioned
not to place undue reliance on forward-looking statements. In
respect of the forward-looking statements concerning the
interpretation of exploration results and the impact on the
Project’s mineral resource estimate, the Company has provided such
statements in reliance on certain assumptions it believes are
reasonable at this time, including assumptions as to the continuity
of mineralization between drill holes. A mineral resource that is
classified as “inferred” or “indicated” has a great amount of
uncertainty as to its existence and economic and legal feasibility.
It cannot be assumed that any or part of an “inferred mineral
resource” or an “indicated mineral resource” will ever be upgraded
to a higher category of mineral resource. Investors are cautioned
not to assume that all or any part of mineral deposits in these
categories will ever be converted into proven and probable mineral
reserves.
By its nature, this information is subject to
inherent risks and uncertainties that may be general or specific
and which give rise to the possibility that expectations,
forecasts, predictions, projections or conclusions will not prove
to be accurate, that assumptions may not be correct and that
objectives, strategic goals and priorities will not be achieved.
Factors that could cause future results or events to differ
materially from current expectations expressed or implied by the
forward-looking statements include risks and uncertainties relating
to the interpretation of drill results, the geology, grade and
continuity of mineral deposits and conclusions of economic
evaluations; uncertainty as to estimation of mineral resources;
inaccurate geological and metallurgical assumptions (including with
respect to the size, grade and recoverability of mineral
resources); the potential for delays or changes in plans in
exploration or development projects or capital expenditures, or the
completion of feasibility studies due to changes in logistical,
technical or other factors; the possibility that future
exploration, development, construction or mining results will not
be consistent with the Company’s expectations; risks related to the
ability of the current exploration program to identify and expand
mineral resources; risks relating to possible variations in grade,
planned mining dilution and ore loss, or recovery rates and changes
in project parameters as plans continue to be refined; operational
mining and development risks, including risks related to accidents,
equipment breakdowns, labour disputes (including work stoppages and
strikes) or other unanticipated difficulties with or interruptions
in exploration and development; risks related to the inherent
uncertainty of production and cost estimates and the potential for
unexpected costs and expenses; risks related to commodity and power
prices, foreign exchange rate fluctuations and changes in interest
rates; the uncertainty of profitability based upon the cyclical
nature of the mining industry; risks related to failure to obtain
adequate financing on a timely basis and on acceptable terms or
delays in obtaining governmental or other stakeholder approvals or
in the completion of development or construction activities; risks
related to environmental regulation and liability, government
regulation and permitting; risks relating to the Company’s ability
to attract and retain skilled staff; risks relating to the timing
of the receipt of regulatory and governmental approvals for
continued operations and future development projects; political and
regulatory risks associated with mining and exploration; risks
relating to the potential impacts of the COVID-19 pandemic on the
Company and the mining industry; changes in general economic
conditions or conditions in the financial markets; and other risks
described in Marathon’s documents filed with Canadian securities
regulatory authorities, including the Annual Information Form for
the year ended December 31, 2022.
You can find further information with respect to
these and other risks in Marathon’s Annual Information Form for the
year ended December 31, 2022 and other filings made with Canadian
securities regulatory authorities available at www.sedar.com. Other
than as specifically required by law, Marathon undertakes no
obligation to update any forward-looking statement to reflect
events or circumstances after the date on which such statement is
made, or to reflect the occurrence of unanticipated events, whether
as a result of new information, future events or results
otherwise.
Photos accompanying this announcement are
available:
https://www.globenewswire.com/NewsRoom/AttachmentNg/f1331ff8-5d96-43c7-9381-822c3dc3af7c
https://www.globenewswire.com/NewsRoom/AttachmentNg/131d1b31-4bf4-4a70-b36d-3504ad72ebfd
https://www.globenewswire.com/NewsRoom/AttachmentNg/5e3a34dc-27b0-4872-8ded-9a44afa4b260
https://www.globenewswire.com/NewsRoom/AttachmentNg/b9c7f760-3e32-4c09-a7df-f1de2e8dc9fa
https://www.globenewswire.com/NewsRoom/AttachmentNg/792d05a5-7d0b-4712-923e-7fcedc0a6fe8
https://www.globenewswire.com/NewsRoom/AttachmentNg/5a644e04-2b5f-45e3-a928-2d2aca6ffa7e
https://www.globenewswire.com/NewsRoom/AttachmentNg/62b85a4a-2604-4ba0-a55a-bac08df67008
https://www.globenewswire.com/NewsRoom/AttachmentNg/3b6b0757-f477-45eb-9ee8-8d6eb343a724
Marathon Gold (TSX:MOZ)
Graphique Historique de l'Action
De Oct 2024 à Nov 2024
Marathon Gold (TSX:MOZ)
Graphique Historique de l'Action
De Nov 2023 à Nov 2024