Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF)
(“Orezone” or “Company”) reported its operational and financial
results for the first quarter of 2024. The Company will host a
conference call and webcast on May 14, 2024 commencing at 8:00am PT
to discuss its Q1-2024 results. Additional details are provided at
the end of this press release.
All dollar amounts are in USD unless otherwise
stated and abbreviation “M” means million.
Patrick Downey, President and CEO, commented
“Our Bomboré mine had another quarter of consistent performance,
delivering 30,139 ounces of gold production, mine earnings of $27
million, and positive free cashflow. In addition, we successfully
commissioned the powerline connection to the national grid and
substantially completed the construction of the MV3 resettlement
site which will open mining access to the Siga East deposit in the
third quarter of 2024.
Importantly, we continue to reinvest in the
Bomboré mine and, after a careful review of available financing
alternatives, the Company has decided to pursue its Phase II Hard
Rock Expansion in two stages to better align capital requirements
with funding sources. We have now received a debt proposal for the
first stage of the expansion from our senior lender, Coris Bank,
which we expect to finalize in the very near future.”
2024 FIRST QUARTER
HIGHLIGHTS
(All mine site figures on a 100% basis) |
|
Q1-2024 |
Q1-2023 |
Operating Performance |
|
|
|
Gold production |
oz |
30,139 |
41,301 |
Gold sales |
oz |
31,229 |
43,139 |
Average realized gold price |
$/oz |
2,066 |
1,892 |
Cash costs per gold ounce sold1 |
$/oz |
1,127 |
799 |
All-in sustaining costs1 (“AISC”) per gold ounce sold |
$/oz |
1,324 |
926 |
Financial Performance |
|
|
|
Revenue |
$000s |
64,685 |
81,712 |
Earnings from mine operations |
$000s |
26,882 |
39,670 |
Net income attributable to shareholders of Orezone1 |
$000s |
11,697 |
22,560 |
Net income per common share attributable to shareholders of
Orezone1 |
|
|
|
BasicDiluted |
$$ |
0.030.03 |
0.070.06 |
Adjusted EBITDA1 |
$000s |
25,928 |
42,645 |
Adjusted earnings attributable to shareholders of Orezone1 |
$000s |
7,736 |
24,574 |
Adjusted earnings per share attributable to shareholders of
Orezone1 |
$ |
0.02 |
0.07 |
Cash and Cash Flow Data |
|
|
|
Operating cash flow before changes in working capital |
$000s |
20,357 |
41,137 |
Operating cash flow |
$000s |
13,637 |
38,926 |
Free cash flow1 |
$000s |
2,013 |
31,498 |
Cash, end of period |
$000s |
15,597 |
45,172 |
1 Cash costs, AISC, Adjusted EBITDA, Adjusted
earnings, Adjusted earnings per share, and Free cash flow are
non-IFRS measures. See “Non-IFRS Measures” section below for
additional information.
-
Safety: Continued strong safety performance in
Q1-2024 with 1.41 million hours worked without a lost-time
injury.
- Debt
Reduction: Principal repayment of XOF 3.0 billion ($5.0
million) in Q1-2024 on the Company’s senior loans with Coris Bank
International (“Coris Bank”).
-
Liquidity: On May 10, 2024, the Company closed and
drew down on a XOF 12.0 billion (~$20 million) bridge loan with
Coris Bank in order to improve the Company’s cash position. The
Company intends to refinance the bridge loan with the project loan
for its Phase II hard rock expansion with Coris Bank expected in
Q3-2024.
The Phase II Hard Rock
Expansion
A hard rock plant, to complement the existing
Phase I oxide plant, is required to process the fresh rock and
lower transition mineral reserves of the Bomboré orebody.
The Company originally contemplated constructing
a 4.4 million tonnes per annum (“Mtpa”) hard rock plant in a single
stage as outlined in its 2023 feasibility study. Following a recent
review of available financing sources, the Company has decided to
complete this brownfield expansion in two stages to better manage
its capital requirements. Stage 1 will consist of an initial
2.5Mtpa hard rock plant, with a future Stage 2 expansion increasing
hard rock plant throughput to 5.0Mtpa – 7.0Mtpa.
A preliminary capital cost for this initial
2.5Mtpa hard rock plant is estimated at $80 million, significantly
less than the $167.5 million estimated for the 4.4Mtpa hard rock
plant. The Company expects to finance the construction costs of
this Stage 1 hard rock plant (rescoped “Phase II Hard Rock
Expansion”) primarily through senior debt and cash flow generated
from its Phase I oxide operations during the construction
period.
The Company has significantly advanced
discussions with Coris Bank for additional project debt and
anticipates concluding a binding debt commitment in June 2024.
Based on forecasted construction and key equipment timelines, the
Company expects first gold from the Phase II Hard Rock Expansion to
be achieved in late 2025.
The Company intends to provide more detailed
guidance for its Phase II Hard Rock Expansion later this year after
the Company has secured a binding debt commitment and Board
approval to proceed with the expansion.
BOMBORÉ GOLD MINE (100% BASIS) –
OPERATING HIGHLIGHTS
|
|
Q1-2024 |
Q1-2023 |
Safety |
|
|
|
Lost-time injuries frequency rate (LTIFR) |
per 1M hours |
0.00 |
0.00 |
Personnel-hours worked |
000s hours |
1,410 |
928 |
Mining Physicals |
|
|
|
Ore tonnes mined |
tonnes |
2,402,533 |
2,205,056 |
Waste tonnes mined |
tonnes |
3,123,099 |
2,382,135 |
Total tonnes mined |
tonnes |
5,525,631 |
4,587,191 |
Strip ratio |
waste:ore |
1.3 |
1.1 |
Processing Physicals |
|
|
|
Ore tonnes milled |
tonnes |
1,355,619 |
1,445,693 |
Head grade milled |
Au g/t |
0.78 |
0.96 |
Recovery rate |
% |
89.0 |
92.2 |
Gold produced |
Au oz |
30,139 |
41,301 |
Unit Cash Cost |
|
|
|
Mining cost per tonne |
$/tonne |
3.48 |
2.91 |
Mining cost per ore tonne processed |
$/tonne |
8.02 |
6.51 |
Processing cost |
$/tonne |
9.24 |
9.21 |
Site general and admin (“G&A”) cost |
$/tonne |
3.79 |
3.23 |
Cash cost per ore tonne processed |
$/tonne |
21.05 |
18.96 |
Cash Costs and AISC Details |
|
|
|
Mining cost (net of stockpile movements) |
$000s |
10,867 |
9,417 |
Processing cost |
$000s |
12,520 |
13,322 |
Site G&A cost |
$000s |
5,134 |
4,667 |
Refining and transport cost |
$000s |
117 |
148 |
Government royalty cost |
$000s |
5,132 |
4,912 |
Gold inventory movements |
$000s |
1,416 |
2,019 |
Cash costs1 on a sales
basis |
$000s |
35,186 |
34,485 |
Sustaining capital |
$000s |
4,018 |
3,530 |
Sustaining leases |
$000s |
73 |
187 |
Corporate G&A cost |
$000s |
2,069 |
1,731 |
All-In Sustaining Costs1
on a sales basis |
$000s |
41,346 |
39,933 |
Gold sold |
Au oz |
31,229 |
43,139 |
Cash costs per gold ounce
sold1 |
$/oz |
1,127 |
799 |
All-In Sustaining Costs per gold ounce
sold1 |
$/oz |
1,324 |
926 |
1 Non-IFRS measure. See “Non-IFRS Measures” section
for additional details.
Bomboré Production Results
Gold production in Q1-2024 was 30,139 ounces, a
decline of 27% from the 41,301 ounces produced in Q1-2023. The
lower gold production is attributable to an 18% decrease in head
grades, a 6% decline in plant throughput, and a 3% decrease in
plant recoveries. The better head grade achieved in Q1-2023 was
primarily the result of processing of high-grade stockpiles
accumulated during the Phase I construction which have now been
fully depleted. Mill availability in Q1-2024 was impacted by the
commissioning of grid power to site and from the shortage of power
from the national grid towards the end of the quarter. In addition,
as mining deepens in the certain pits, the quantity of transition
ore has started to increase. The presence of transition ore results
in slightly lower metallurgical recoveries, lower plant throughput,
and additional plant maintenance due to the harder nature of the
ore.
Plant throughput, head grades, and recoveries
are expected to improve from a greater blend of oxide ore once
mining commences at Siga East in Q3-2024.
Bomboré Operating Costs
AISC per gold ounce sold in Q1-2024 was $1,324,
a 43% increase from the $926 per ounce sold in Q1-2023. The higher
AISC is primarily the result of: (a) lower Q1-2024 gold production
and sales as explained above; (b) greater per ounce royalty costs
from new royalty rates that took effect in October 2023 and from a
higher realized selling price; and (c) increased mining costs.
Cash cost per ore tonne processed in Q1-2024 was
$21.05 per tonne, an increase of 11% from the $18.96 per tonne in
Q1-2023. The higher cash cost in Q1-2024 was predominantly due to
increased mining and site G&A costs, and from fewer ore tonnes
processed. Mining costs have increased as lower benches are mined
resulting in longer hauls and more transition material that
requires drill-and-blast prior to excavation. In addition, unit
mining costs have increased from a higher strip ratio and more
management fees from the mobilization of a second mining contractor
in July 2023 to supplement material movement of the main mining
contractor. Site G&A costs reflect greater spending for
security as the Company expands its operations into the southern
portion of the mining permit.
Processing costs per ore tonne has remained
relatively stable from $9.21 per tonne in Q1-2023 to $9.24 per
tonne in Q1-2024. Unit processing costs were expected to decline in
Q1-2024 from 2023 levels upon the introduction of grid power to the
Bomboré mine at the end of January 2024; however, the power costs
savings from using grid power has been offset by greater blend of
transition ore requiring higher per tonne consumption of power,
grinding media, and main reagents; more plant maintenance to
address higher equipment wear; and from lower plant throughput
resulting in fixed processing costs being absorbed over fewer
tonnes in Q1-2024. Furthermore, the mine relied on more self
generated power beginning in March 2024 from lower-than-expected
availability of grid power as the dry season impacted the
contributions of hydropower to the national grid.
Bomboré Growth Capital
Projects
Grid Power Connection
The commissioning of the powerline to connect
Bomboré to Burkina Faso’s national energy grid commenced in January
2024 and was successfully energized by the end of the same month.
As of March 31, 2024, the Company has incurred costs of $19.3M for
the grid power connection, of which $1.1M was incurred in
Q1-2024.
Resettlement Action Plan (“RAP”) Phases II and
III
RAP Phases II and III involve the construction
of three new resettlement communities (MV3, MV2, and BV2) in order
to relocate households currently residing within the southern half
of the Bomboré mining permit. The Company has sequenced MV3 first
in order to gain access to mining areas that are currently
contemplated in the 2024 mine plan.
Construction of MV3 was substantially completed
in April 2024 with the Company now organizing with local leaders
and residents to relocate families into their new resettlement
homes later in Q2-2024. In parallel, the Company has commenced
earthworks for the next resettlement site (MV2) and awarded
contracts to local companies to begin construction shortly.
As of March 31, 2024, the Company has incurred
project-to-date costs of $13.5M for RAP Phases II and III, of which
$3.1M was incurred in Q1-2024.
NON-IFRS MEASURES
The Company has included certain terms or
performance measures commonly used in the mining industry that is
not defined under IFRS, including “cash costs”, “AISC”, “EBITDA”,
“adjusted EBITDA”, “adjusted earnings”, “adjusted earnings per
share”, and “free cash flow”. Non-IFRS measures do not have any
standardized meaning prescribed under IFRS, and therefore, they may
not be comparable to similar measures presented by other companies.
The Company uses such measures to provide additional information
and they should not be considered in isolation or as a substitute
for measures of performance prepared in accordance with IFRS. For a
complete description of how the Company calculates such measures
and reconciliation of certain measures to IFRS terms, refer to
“Non-IFRS Measures” in the Management’s Discussion and Analysis for
the three months ended March 31, 2024 which is incorporated by
reference herein.
CONFERENCE CALL AND WEBCAST
The condensed consolidated interim financial
statements and Management’s Discussion and Analysis are available
at www.orezone.com and on the Company’s profile on SEDAR+ at
www.sedarplus.ca. Orezone will host a conference call and audio
webcast to discuss 2024 first quarter results on May 14, 2024 at
8:00am PT (11:00am ET).
Webcast |
Date: |
Tuesday, May 14, 2024 |
Time: |
8:00 am Pacific time (11:00 am
Eastern time) |
Please register for
the webcast here: Orezone Q1-2024 Conference Call and
Webcast |
|
Conference CallToll-free in U.S.
and Canada: 1-800-715-9871International callers: +646-307-1963Event
ID: 2084420
QUALIFIED PERSONS
The scientific and technical information in this
news release was reviewed and approved by Dr. Pascal Marquis, Geo.,
Senior Vice President of Exploration and Mr. Rob Henderson, P. Eng,
Vice President of Technical Services, both of whom are Qualified
Persons as defined under NI 43-101 Standards of Disclosure for
Mineral Projects.
About Orezone Gold
Corporation
Orezone Gold Corporation (TSX: ORE OTCQX: ORZCF)
is a West African gold producer engaged in mining, developing, and
exploring its 90%-owned flagship Bomboré Gold Mine in Burkina Faso.
The Bomboré mine achieved commercial production on its oxide
operations on December 1, 2022, and is now focussed on its staged
hard rock expansion that is expected to materially increase annual
and life-of-mine gold production from the processing of hard rock
mineral reserves. Orezone is led by an experienced team focused on
social responsibility and sustainability with a proven track record
in project construction and operations, financings, capital
markets, and M&A.
The technical report entitled Bomboré Phase II
Expansion, Definitive Feasibility Study is available on SEDAR+ and
the Company’s website.
Patrick DowneyPresident and Chief Executive
Officer
Vanessa PickeringManager, Investor Relations
Tel: 1 778 945 8977 / Toll Free: 1 888 673
0663info@orezone.com / www.orezone.com
For further information please contact
Orezone at +1 (778) 945-8977 or visit the Company’s
website at
www.orezone.com.
The Toronto Stock Exchange neither approves nor
disapproves the information contained in this news release.
Cautionary Note Regarding
Forward-Looking Statements
This press release contains certain information
that constitutes “forward-looking information” within the meaning
of applicable Canadian Securities laws and “forward-looking
statements” within the meaning of applicable U.S. securities laws
(together, “forward-looking statements”). Forward-looking
statements are frequently characterized by words such as “plan”,
“expect”, “project”, “intend”, “believe”, “anticipate”, “estimate”,
“potential”, “possible” and other similar words, or statements that
certain events or conditions “may”, “will”, “could”, or “should”
occur.
All forward-looking statements are subject to a
variety of risks and uncertainties and other factors that could
cause actual events or results to differ materially from those
projected in the forward-looking statements including, but not
limited to, terrorist or other violent attacks, the failure of
parties to contracts to honour contractual commitments, unexpected
changes in laws, rules or regulations, or their enforcement by
applicable authorities; social or labour unrest; changes in
commodity prices; unexpected failure or inadequacy of
infrastructure, the possibility of project cost overruns or
unanticipated costs and expenses, accidents and equipment
breakdowns, political risk, unanticipated changes in key management
personnel, the spread of diseases, epidemics and pandemics
diseases, market or business conditions, the failure of exploration
programs, including drilling programs, to deliver anticipated
results and the failure of ongoing and uncertainties relating to
the availability and costs of financing needed in the future, and
other factors described in the Company's most recent annual
information form and management’s discussion and analysis filed on
SEDAR+ on www.sedarplus.ca. Readers are cautioned not to place
undue reliance on forward-looking statements.
Forward-looking statements are based on the
applicable assumptions and factors management considers reasonable
as of the date hereof, based on the information available to
management at such time. These assumptions and factors include, but
are not limited to, assumptions and factors related to the
Company’s ability to carry on current and future operations,
including: development and exploration activities; the timing,
extent, duration and economic viability of such operations,
including any mineral resources or reserves identified thereby; the
accuracy and reliability of estimates, projections, forecasts,
studies and assessments; the Company’s ability to meet or achieve
estimates, projections and forecasts; the availability and cost of
inputs; the price and market for outputs, including gold; foreign
exchange rates; taxation levels; the timely receipt of necessary
approvals or permits; the ability to meet current and future
obligations; the ability to obtain timely financing on reasonable
terms when required; the current and future social, economic and
political conditions; and other assumptions and factors generally
associated with the mining industry.
Although the forward-looking statements
contained in this press release are based upon what management of
the Company believes are reasonable assumptions, the Company cannot
assure investors that actual results will be consistent with these
forward-looking statements. These forward-looking statements are
made as of the date of this press release and are expressly
qualified in their entirety by this cautionary statement. Subject
to applicable securities laws, the Company does not assume any
obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after
the date of this press release.
Orezone Gold (TSX:ORE)
Graphique Historique de l'Action
De Fév 2025 à Mar 2025
Orezone Gold (TSX:ORE)
Graphique Historique de l'Action
De Mar 2024 à Mar 2025