Raft River Project Update; First Power Production Expected in Fourth Quarter 2007
25 Juillet 2007 - 3:00PM
PR Newswire (US)
BOISE, Idaho, July 25 /PRNewswire-FirstCall/ -- U.S. Geothermal
Inc. (OTC Bulletin Board: UGTH; TSX.V: GTH), a renewable energy
development company focused on the production of electricity from
geothermal energy, announced today construction progress on its
Raft River geothermal power plant in southeastern Idaho. The
construction of the Unit One, 13-megawatt power plant is under the
direction of Ormat Nevada Inc., a subsidiary of Ormat Technologies
Inc. (NYSE: ORA). Plant construction is proceeding on schedule and
budget. This element of the Raft River project is expected to be
fully functional and online in the fourth quarter of 2007. * All
major power plant equipment has been delivered to site and set on
foundations. * The prime electrical construction contract was
awarded to Merit Electric Incorporated in May. * Piping and
electrical connections are proceeding on schedule. * The control
room and motor control center building has been erected and
switchgear installed. * The cooling tower is 95% complete. * The
geothermal injection pumps and motors have been set in place. *
High voltage interconnection to BPA substation with Idaho Power and
Raft River Electrical Co-operative metering is nearing completion.
U.S. Geothermal is construction manager for the remainder of the
project construction work outside the scope of the Ormat contract.
This work includes pipelines, production pumps and certain
electrical transmission activities. The first two geothermal
production pumps manufactured by Goulds/ITT have been delivered to
the site. A drill rig is currently on site and has installed a
29-stage, 900 horsepower production pump in production well RRG-2.
The drill rig will move next to production well RRG-1 to install a
33-stage, 1000 horsepower production pump. Two more production well
pumps are scheduled for delivery to the site within the next 60
days. Pipeline completion activities and wellhead installations are
in progress. DISCO Associates has delivered to production well
RRG-2 the first of four containerized well control modules. Each
module contains an electronic control package, cooling system, and
lubrication system required to operate and monitor the pump at the
production well. Hot geothermal brine from production well RRG-2 is
scheduled to flow through the new geothermal pipelines to the power
plant for the first time in mid-August. The cooling water supply
piping system is approximately 75% complete for initial operations,
including the refurbishment of an existing 300,000 gallon storage
tank, and the development of a land application system that will be
used to dispose of the cooling tower blow down water. Electrical
transmission work needed to connect the new geothermal power plant
to the existing substation is 100% complete. New photos of the
construction site and equipment are posted in the Gallery section
on our website at http://www.usgeothermal.com/ and are updated
regularly. The Company has assembled a team of seven qualified
technicians for the ongoing operation and maintenance of the Unit
One power plant and planned future power plant units at Raft River.
The team is currently on site and undergoing training and other
activities associated with the finalization of the power plant
construction and its planned operating procedures. Contract
negotiations with Idaho Power Company, the regulated utility owned
by IDACORP (NYSE:IDA), are progressing toward the mutual goal of
converting the existing power sales contract for Unit One from a
limit of 10 average megawatts per month to a full output contract
with an estimated annual average output of between 12 and 14
megawatts. Detailed contract negotiations are focusing on the terms
and conditions specific to Idaho's first geothermal power project.
Idaho Power and the Company expect to be able to use this first
contract as a template for advancing negotiations for the output
from the planned Unit Three at Raft River and 26 megawatts of
planned production from the Company's Neal Hot Springs project
located in southeast Oregon. As reported earlier, Idaho Power named
U.S. Geothermal successful bidder for 45 megawatts of geothermal
power from future development of Raft River and the initial phase
of Neal Hot Springs. The Company is also in the final stages of
contract negotiations with Eugene Water and Electric Board
("EWEB"), Eugene Oregon, for a power purchase agreement associated
with the power output from the planned 13-megawatt Unit Two at Raft
River. The negotiations with Idaho Power and EWEB recognize that
the power purchase agreements are subject to the parties' board
approval and are contingent upon extension of the federal
Production Tax Credit and successful drilling and resource
discovery at Raft River and Neal Hot Springs. About U.S. Geothermal
Inc U.S. Geothermal is a renewable energy development company that
is currently developing a geothermal power project at Raft River,
Idaho and conducting exploration activities at Neal Hot Springs,
Oregon. The company believes Raft River is ideally located to make
an important contribution to the power needs of the Pacific
Northwest. U.S. Geothermal owns and leases geothermal rights of
private lands, which comprise the Raft River project in
Southeastern Idaho. On the basis of a report prepared by the
company's independent consultant, GeothermEx Inc., of Richmond
California, the site has a 50% probability of a power production
capacity of 15.6 megawatts per square mile which may translate to
100 megawatts or more. Please visit our Website at:
http://www.usgeothermal.com/ The information provided in this news
release contains forward-looking statements within the definition
of the Safe Harbor provisions of the US Private Securities
Litigation Reform Act of 1995, including statements regarding the
nature, size and viability of the geothermal resource, the
construction of power plants and the projected production date.
These statements are based on U.S. Geothermal Inc.'s current
expectations and beliefs and are subject to a number of risks and
uncertainties that can cause actual results to differ materially
from those described in forward looking statements, including the
risks that financing will not be available for construction of the
power plants, construction will not be completed on budget or on
schedule, and the revenues generated under the power sales
agreements will not prove sufficient to fund operations and/or
service debt, among others. Forward-looking statements are based on
management's expectations, beliefs and opinions on the date the
statements are made. U.S. Geothermal Inc. assumes no obligation to
update forward-looking statements if management's expectations,
beliefs, or opinions, or other factors, should change. The TSX
Venture and OTC Bulletin Board Exchanges do not accept
responsibility for the adequacy of this release. DATASOURCE: U.S.
Geothermal Inc. CONTACT: Saf Dhillon - Investor Relations of U.S.
Geothermal Inc., +1- 866-687-7059 (Toll Free) or +1-604-484-3031,
or Fax, +1-604-688-9895, ; or Dave Parker of Scott Peyron &
Associates, Inc., +1- 208-388-3800, or Fax, +1-208-388-8898, , for
U.S. Geothermal Inc. Web site: http://www.usgeothermal.com/
Copyright