Northland Resources S.A. (TSX:NAU)(OSLO:NAUR)(FRANKFURT:NPK) ("Northland" or
"the Company") is pleased to announce a positive update to the Definitive
Feasibility Study ("DFS") on its 100%-owned Kaunisvaara Project ("the Project")
in northern Sweden. 


The update includes the results of the DFS on the logistics (the September 27,
2010 DFS press release only provided an estimate at the scoping study level for
the logistics), a revision to the estimated premium for Northland's high
quality, low impurity Fe concentrate, the impact of recent optimisation studies
on engineering costs and operating estimates and revisions to CAPEX including
sustainable capital, using current exchange rates. 


"The updated DFS of the Kaunisvaara project shows a doubling of the NPV (Net
Present Value)," said Karl-Axel Waplan, Northland's President and CEO. "This
study also confirms the positive economics, with an increase of return, measured
in IRR, and remaining strong margin in spite of an increase of operational
expenses. The updated market report reflects the new global pricing mechanism
for iron ore qualities, and could be said to present the true market value. The
high-quality pellet feed from Kaunisvaara is forecasted to command a premium of
USD 7 per Fe-unit. In addition, with a focus on what variables Northland can
control, the optimisation of the mining is positively impacting our capex
requirements.


The highlights of the revised DFS include:



--  After interest and tax, Net Present Value ("NPV") of USD 934 million
    using a discount rate of 8% and an Internal Rate of Return ("IRR") of
    24.0% (compared to the September 2010 DFS: NPV estimate of USD 463
    million using a discount rate of 8% and an IRR of 18.8%) 
--  Pre-tax and interest, NPV of USD 1,461 million using a discount rate of
    8% and an IRR of 32.0%(1) (compared to the September 2010 DFS: NPV
    estimate of USD 774 million and an IRR of 24.7%) 
--  CAPEX to reach 5 million tonnes ("MT") of USD 765 million with
    adjustments for cost optimisation and current exchange rates (compared
    to USD 694 million in September 2010 DFS) 
    --  Cost optimisation reduced initial CAPEX by USD 14 million 
    --  Currency adjustments increased CAPEX by USD 85 million. 
--  Life of Mine ("LOM") CAPEX was reduced to USD 892 million from USD 908
    million (compared to September 2010 DFS) 
    --  Cost optimisation expected to reduce LOM CAPEX by USD 111 million 
    --  Currency adjustments expected to increase CAPEX by USD 95 million. 
--  Total OPEX per tonne of concentrate delivered FOB at the port of Narvik
    for the LOM is estimated to average USD 58.80 per tonne concentrate
    (compared to the September 2010 DFS estimate of USD 53.76 per tonne) 
    --  Mining costs are estimated to be USD 3.50 per tonne lower 
    --  Logistics costs are estimated to be to USD 8 per tonne higher 
--  Independent market analyst, Raw Materials Group ("RMG"), have now
    included an estimated premium for the Northland pellet feed of USD 7 per
    Fe-unit 



(1) Northland's estimate of IRR and NPV before tax and interest are consistent
in all material respects with the equivalent pre-tax estimates derived by SRK
and presented in the NI 43-101 report.


Conference Call 

Northland will host tomorrow, Thursday, May 19, 2011, webcast presentation and
conference call to discuss the update of Kaunisvaara Definitive Feasibility
Study. The presentation is scheduled to begin at 5.00 pm Central European Time /
11.00 am Eastern Daylight Time and will be chaired by Karl-Axel Waplan, Chief
Executive Officer and Shane Williams, Vice President Projects.


A link to the live audio webcast of the conference call, together with
supporting presentation slides, will be available on the corporate website,
www.northland.eu. Please call about five minutes before the advertised starting
time to access the conference call.




Call-in details:                                                          
USA/Canada:                          +1 866 458 40 87                     
UK:                                  +44 (0)20 3043 2436                  
Sweden:                              +46 (0)8 505 598 53                  
Norway:                              +47 215 111 88                       



Improved Transparency on Product Quality and Grade

Over the past years, the new global pricing mechanism for iron ore, which is
largely based on spot pricing and indices instead of benchmark pricing, has
become a much more reliable indicator of the true market value for various
product qualities. Real-time, third party quotes from Platts (IODEX), the Steel
Index (TSI) and Metal Bulletin (MBIO) currently provide the market and investors
with greatly improved transparency on the premium for high grade/low impurity
products, like the Kaunisvaara pellet feed. 


Northland has long been convinced that the market will highly value the high
Fe-content (69%) and low levels of impurities (e.g. 1.1% SiO2 and 0.2% Al2O3) in
its concentrate. This has been supported by Raw Materials Group ("RMG") whose
May 2, 2011 report, estimated the premium to be USD 7 per Fe-unit. The revised
estimate results in a higher FOB prices than in the September 2010 DFS (USD 137
per tonne, compared to USD 101 per tonne) using the same base assumptions about
the overall market and shipping costs.


"In the case of Northland Resources, given the information at hand it is most
reasonable that the Northland material will command a premium in the market and
that this will be in the same size as other high grade iron ore products", said
Magnus Ericsson, Senior Partner of RMG.


Optimisation Work Reduces Expected Mining Cost

Since completing the DFS study in September 2010, Northland has optimised
operating and engineering costs which has resulted in a 27% decrease in the
expected total mining cost over the LOM and a 22% reduction in expected cost per
tonne of ore.


Optimisation studies identified some low-margin/high-stripping ore which could
be excluded from the production schedule and improve economics. By removing
approximately 11.2Mt of ore from the mine plan, Northland could reduce waste
rock production by nearly 154Mt and overburden removal by 2.6Mm3. Decreasing
waste production has several positive effects including lower CAPEX (less
equipment to purchase) and lower direct costs (for items such as explosives,
fuel, etc.) The optimisation has reduced the CAPEX over the LOM with USD 88
million and the OPEX over the LOM has been reduced by USD 352 million.


Furthermore, during the ongoing negotiations with Caterpillar for the truck
fleet, an additional cost savings of USD 25 million was identified due to the
use of certified rebuilds.


DFS on Logistics

In the September 2010 DFS, the logistic costs were only presented at a scoping
study level. Since that time, Northland and the Swedish Transport Administration
have signed a Letter Of Intent on co-financing and an Agreement on cooperation
covering the comprehensive transport solution, in other words, how the iron ore
concentrate will be transported from the Kaunisvaara process plant to the port
of Narvik, Norway (see also press release March 26, 2011).


A map of the Transportation Route is available at the following address:
http://media3.marketwire.com/docs/Transportation_Route.jpg. 


The updated study has confirmed the viability of the plan presented in the
September 2010 DFS. The logistics includes




--  Trucking from Kaunisvaara to Svappavaara (150 km). The anticipated truck
    size is 105 tonnes gross (compared to 170 tonnes trucks in September
    2010 DFS). The anticipated size is based on an evaluation of existing
    dispensation as well as a thorough consideration of the expected outcome
    of the joint studies and work with the Swedish Transport Association
    will produce. 
--  Trans-loading from truck to rail in Svappavaara with a new terminal 
--  Rail using 100 tonne rail cars on the already existing rail line between
    Svappavaara and Narvik (226 km) 
--  A new terminal and berth in Narvik port with the capacity to load Cape
    Size vessels. 



The plan is to create a joint venture company ("JV") with the responsibility for
the whole logistical chain, i.e. from the process plant at Kaunisvaara to the
loading on vessels in Narvik port. Northland will be one of the partners in the
JV. 


JV Logistics

Northland is in negotiations with 3-4 prospective partners for the planned JV
with the objective of having a Letter of Intention signed during the summer and
the JV being operational during the second half of 2011. The JV would take full
responsibility for the whole logistical chain and all necessary agreements.


The total CAPEX for the logistic investment to handle 5 Mtpa of concentrate is
estimated at SEK 1,177 million/USD 145 million and will be funded through debt
to equity. Discussions have begun with a number of banks experienced in
financing such infrastructure investments. Northland is in negotiations with
Narvik port regarding the lease and rent of necessary facilities in the port
area. And these discussions are expected to be finalised before mid-summer. The
production of a proto type rail car has started as well as all necessary
planning and design work to ensure that the time line for the logistics is met
(shipments to start early in 2013).


The investment costs for the logistics have been included as OPEX in the updated
model, with the exception of USD 15 million which is Northland's equity
participation in the JV.




--------------------------------------------------------------------------
                              September 2010 DFS,   Updated logistics DFS,
                              scoping study level   presented May 18, 2011
--------------------------------------------------------------------------
Cost category               USD/tonne concentrate    USD/tonne concentrate
--------------------------------------------------------------------------
Cost of CAPEX charged by                                                  
 the JV to Northland                          0.0                      3.1
--------------------------------------------------------------------------
Trucking                                     10.4                     15.6
--------------------------------------------------------------------------
Rail                                          2.7                      4.9
--------------------------------------------------------------------------
Port                                          4.4                      1.5
--------------------------------------------------------------------------
Contingency, 5%                               0.9                      1.3
--------------------------------------------------------------------------
Total                                       18.36                 26.37(i)
--------------------------------------------------------------------------
                                                                          
(i)  Including 3% margin on all numbers pre-contingency                   



FX

The OPEX and the CAPEX in the September 2010 DFS used an exchange rate of 8.125
SEK/USD. Since then the SEK has strengthened considerably against the USD. To
reflect this, 2/3 of the CAPEX in SEK has been adjusted using a new rate of 6.40
SEK/USD and 1/3 at 6.95 SEK/USD which was the exchange rate at the time of the
equity offering in December 2010. The impact of these FX changes is USD 85
million.


OPEX

The revised total OPEX for the LOM operation is estimated to be USD 58.80
(including 5% contingency) per tonne of concentrate (dry) delivered Free on
Board ("FOB") to the Port of Narvik, Norway. This compares to USD 53.76 per
tonne in the September 2010 DFS. A comparison of the current and previous DFS
estimates is shown in table below:




--------------------------------------------------------------------------
                                                    Updated logistics DFS,
                               September 2010 DFS   presented May 18, 2011
--------------------------------------------------------------------------
Cost category               USD/tonne concentrate    USD/tonne concentrate
--------------------------------------------------------------------------
Mining                                      21.12                    17.64
--------------------------------------------------------------------------
Process                                     12.31                    12.60
--------------------------------------------------------------------------
General & Administration                     1.36                     1.45
--------------------------------------------------------------------------
Transportation                              18.36                    26.37
--------------------------------------------------------------------------
Royalties                                    0.26                     0.36
--------------------------------------------------------------------------
Other                                        0.35                     0.38
--------------------------------------------------------------------------
Total                                       53.76                    58.80
--------------------------------------------------------------------------



As shown above, the increase in the OPEX is largely a result of an increase in
transportation costs to Narvik, partially offset by lower mining costs.


CAPEX

The revised CAPEX in order to reach 5 Mtpa capacity (end 2014) has been
estimated at USD 765 million, adjusted for revised exchange rates and a 10%
contingency. This compares to an initial CAPEX estimate in the DFS of USD 694
million. The increase is to be referred to the change in FX.


CAPEX for the LOM is estimated at USD 892 million, including sustainable capital
adjusted for the revised exchange rate and a 10% contingency. This number
compares with the original DFS estimate of USD 908 million (including a 10%
contingency). A comparison to the current and previous CAPEX estimate is shown
in the table below.




--------------------------------------------------------------------------
                                     Updated CAPEX                        
                                              with   Updated CAPEX with FX
USD million, incl    CAPEX September  optimization       adjustment(1) and
 10% contingency            2010 DFS      benefits   optimization benefits
--------------------------------------------------------------------------
Area Breakdown              End 2014      End 2014                End 2014
--------------------------------------------------------------------------
Mines - dikes,                                                            
 mobile mining                                                            
 equipment                       139           136                     148
--------------------------------------------------------------------------
Mines - crushing                                                          
 stations and                                                             
 conveyors                        58            55                      58
--------------------------------------------------------------------------
Plant -                                                                   
stream Sahavaara                 122           115                     125
--------------------------------------------------------------------------
Plant - stream                                                            
 Tapuli                          174           147                     163
--------------------------------------------------------------------------
Tailings and                                                              
water ponds /                                                             
 lines                            34            34                      43
--------------------------------------------------------------------------
Power supply                      15            13                      16
--------------------------------------------------------------------------
Filtration plant /                                                        
common equipment                                                          
and infrastructure                91           108                     127
--------------------------------------------------------------------------
Owners cost                       57            57                      70
--------------------------------------------------------------------------
Closure cost                       4             0                       0
--------------------------------------------------------------------------
Logistics                          0            15                      15
--------------------------------------------------------------------------
Total                            694           680                     765
--------------------------------------------------------------------------



(1) CAPEX adjusted - 2/3 using a new rate of 6.40 SEK/USD and 1/3 at 6.95 SEK/USD 

Audit of the New Model

As part of the NI 43-101 process, SRK Consulting (UK) Limited ("SRK") has
audited the updated capital and operating cost estimates for the Kaunisvaara
Project. SRK's estimates for IRR and NPV before tax and interest presented in
the NI 43-101 are consistent in all material respects with the pre-tax estimates
derived by Northland and presented in the DFS. 


A complete NI 43-101 compliant DFS report will be filed on SEDAR on
www.sedar.com and on Northland's website www.northland.eu within 45 days.


Previous information on the Kaunisvaara DFS was published in the September 27,
2010 press release and in the October 6, 2010 technical report. 


Northland is a development-stage mining company with a portfolio of iron ore
projects in northern Sweden and Finland. The Company's Kaunisvaara Project will
exploit magnetite iron ore deposits, feeding a single, multi-line processing
facility in Sweden. The process yields a very high-grade, high-quality magnetite
iron concentrate. The Company is also preparing a Definitive Feasibility Study
for the Hannukainen Iron Ore Copper Gold Project in northern Finland.


ON BEHALF OF THE BOARD 

Karl-Axel Waplan, President and Chief Executive Officer

Northland Resources S.A.

Raw Materials Group, Magnus Ericsson

SRK Consulting, Howard Baker 

CAUTION REGARDING FORWARD-LOOKING INFORMATION

This press release contains forward-looking information within the meaning of
securities laws. Except for statements of historical fact relating to the
Company, certain information contained herein constitutes "forward-looking
information" under Canadian securities legislation. Forward-looking information
includes, but is not limited to, statements with respect to mineral reserve and
resource estimates; the ability to realise estimated mineral reserves and to
convert mineral resources into mineral reserves; terms and costs of future
exploration; mineralisation projections; receipt of all necessary approvals; the
parameters and assumptions underlying the mineral resource estimates and iron
ore prices. Generally, forward-looking information can be identified by the use
of forward-looking terminology such as "plans", "expects" or "does not expect",
"is expected", "budget", "scheduled", "estimates", "forecasts", "intends",
"anticipates" or "does not anticipate", or "believes", or variations of such
words and phrases or statements that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be achieved".
Forward-looking statements are based on the opinions and estimates of management
as of the date such statements are made. Estimates regarding the mineral
resources, as outlined above and in the technical report, have been based on
knowledge of company management and the knowledge and experience of third party
experts. Forward-looking information is subject to known and unknown risks,
uncertainties and other factors that may cause the actual results, level of
activity, performance or achievements of Northland Resources S.A. to be
materially different from those expressed or implied by such forward-looking
information. Although management of Northland Resources S.A. has attempted to
identify important factors that could cause actual results to differ materially
from those contained in forward-looking information, there may be other factors
that cause results not to be as anticipated, estimated or intended. There can be
no assurance that such statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in such
statements. Accordingly, readers should not place undue reliance on
forward-looking information. Northland Resources S.A. does not undertake to
update any forward-looking information, except in accordance with applicable
securities laws.


Rainmaker Resources Ltd. (TSXV:RMG)
Graphique Historique de l'Action
De Jan 2025 à Fév 2025 Plus de graphiques de la Bourse Rainmaker Resources Ltd.
Rainmaker Resources Ltd. (TSXV:RMG)
Graphique Historique de l'Action
De Fév 2024 à Fév 2025 Plus de graphiques de la Bourse Rainmaker Resources Ltd.