By Pierre Bertrand

 

TotalEnergies said that the restart of the idled Tyra natural gas field, Denmark's largest, is expected in March.

The French oil and gas major, the field's operator, said that though some operational uncertainties remain, preparations were progressing as planned and operations could resume before the current March 31 restart date.

The natural gas field was idled for redevelopment due to the subsidence of the field's chalk reservoir after years of production, TotalEnergies said.

The field was a key production area, responsible for more than 90% of the natural gas produced in Denmark's North Sea before its redevelopment, the company said.

The redevelopment of the field included the decommissioning and recycling of old platforms, TotalEnergies said, adding that work is continuing to repower systems, unplug wells, re-establish communications and to ensure safe working conditions.

TotalEnergies said tests indicate that the ramp-up to full technical capacity from the moment the field is restarted is expected to take four months.

 

Write to Pierre Bertrand at pierre.bertrand@wsj.com

 

(END) Dow Jones Newswires

January 22, 2024 05:22 ET (10:22 GMT)

Copyright (c) 2024 Dow Jones & Company, Inc.
TotalEnergies (EU:TTE)
Graphique Historique de l'Action
De Mar 2024 à Avr 2024 Plus de graphiques de la Bourse TotalEnergies
TotalEnergies (EU:TTE)
Graphique Historique de l'Action
De Avr 2023 à Avr 2024 Plus de graphiques de la Bourse TotalEnergies