Global Atomic Corporation (“Global Atomic” or the “Company”), (TSX:
GLO, OTCQX: GLATF, FRANKFURT: G12) announced today its operating
and financial results for the three and six months ended June 30,
2020.
HIGHLIGHTS
Dasa Uranium Project:
Preliminary Economic Assessment (“PEA”)
- A PEA of the Phase 1 Development
Plan for the Dasa Uranium Deposit was filed on SEDAR, indicating an
initial 12-year mine schedule to produce 44.1 million pounds U3O8,
with an average processed grade of 5,396 ppm;
- The PEA estimates cash costs of US
$16.72/lb U3O8, including corporate and all other off-site costs,
and an all-in sustaining cost of US $18.39/lb U3O8;
- Based on a U3O8 price of $35/lb,
the after-tax NPV discounted at 8% was estimated at $211 million
for an after-tax IRR of 26.6%;
Mining Permit
Application
- A Hydrogeological water well
drilling and testing program has been completed to support the
Mining Permit application;
- An Environmental Impact Statement
(“EIS”) was completed and filed with the Niger Government;
- A preliminary geotechnical report
was completed and identified the drilling required to finalize
geotechnical inputs to the final mine design.
Turkish Zinc Joint
Venture
- The new Turkish Zinc recovery plant
continues to ramp up with improved operating efficiencies.
- The Company’s share of the Turkish
Joint Venture (“Turkish JV”) EBITDA was $0.9 million in Q2 2020
($0.8 million in Q1);
- The non-recourse Turkish JV debt
was US $22.85 million (Global Atomic share - $11.2 million) at the
end of Q2 2020 and the cash balance was US $1.9 million;
- The Company’s share of the Turkish
JV loss was $1.2 million, attributable to a $1.5 million unrealized
foreign exchange loss on the Turkish debt, due to the decline in
both the Turkish Lira and the Canadian dollar relative to the US
dollar.
Corporate
- Global Atomic continues to receive
management fees and sales commissions from the Turkish JV, helping
to offset corporate overhead costs;
- Bob Tait was appointed
Vice-President Investor Relations effective June 1, 2020;
- Trace Arlaud, M.Eng., was appointed
to the Board as an independent director effective June 29,
2020
- The Company completed a private
placement of 5,538,335 Units on May 15th at a price of $0.60 per
Unit for gross proceeds of $3,323,000. Each Unit comprised one
common share and one-half warrant exercisable at $0.85 per common
share over a 24-month period with an accelerator clause if the
shares trade above C$1.10 for 20 days.
Stephen G. Roman, Chairman, President and CEO
commented “Global Atomic had an excellent second quarter, 2020,
achieving several milestones for the Dasa Uranium
Project. The Preliminary Economic Assessment filed in
May, which outlined a 12-year schedule to mine the low-cost,
high-grade Flank Zone, is compelling at today’s uranium
price. We have made great progress on completing various
studies required for our Mining Permit Application, which we expect
to submit to the Government of Niger prior to year end. While
our EAFD recycling business is operating below capacity due to
COVID-related interruptions in the steel industry, cash flow has
improved due to stronger zinc prices. After raising $3.3
million in the quarter, current cash on hand is sufficient to fund
our work program into the first quarter of 2021, when we expect to
receive our Mining Permit.”
OUTLOOK
Dasa Uranium Project,
Niger
- Public consultation meetings are
scheduled to be held in the town of Agadez and Tchirozerine, Niger,
prior to receipt of an Environmental Certificate of Conformity from
the Niger Government;
- With the certificate of
Environmental Conformity, the technical and other documentation
will be filed as part of the Mining Permit application; the Company
expects this to be completed in Q3 2020;
- Global Atomic anticipates the
Mining Permit to be issued in Q1, 2021;
- A structural and geotechnical
drilling program will be undertaken in Q3/Q4 2020 to finalize the
Dasa mine design;
- A Pilot Plant project to confirm
Dasa Process Plant flow sheet design is underway;
- Further studies are ongoing to
optimize the mine plan, process flow sheets, begin detailed
engineering and finalize capital and operating cost
estimates.
Turkish Zinc JV, Iskenderun,
Turkey
- The modernized Turkish JV plant in
Iskenderun is anticipated to operate at approximately 60% capacity
during 2020; operations in 2021 will be driven by COVID-19 impact
on the Turkish steel industry and the availability of Electric Arc
Furnace Dust (“EAFD”);
- Zinc prices have recently increased
to above $1.00/lb;
- Repayments will continue on the
Befesa loan through 2020 and 2021, to eliminate Turkish JV Project
debt.
- Dividend flow from the Turkish JV
will resume following repayment of the non-recourse, modernization
debt.
Summarized income statement and financial position information
is shown as follows:
|
Three months ended June 30, |
|
Six months ended June 30, |
(all amounts in C$) |
2020 |
2019 |
|
2020 |
2019 |
Revenue |
$ |
225,456 |
|
$ |
- |
|
|
$ |
449,653 |
|
$ |
53,678 |
|
General and administration |
948,462 |
|
1,327,038 |
|
|
1,501,288 |
|
1,782,908 |
|
Share of equity loss (earnings) |
363,072 |
|
(3,608,756 |
) |
|
1,604,274 |
|
(5,619,023 |
) |
Other income |
(30,000 |
) |
(30,000 |
) |
|
(60,000 |
) |
(60,000 |
) |
Finance expense |
4,412 |
|
- |
|
|
8,856 |
|
- |
|
Foreign exchange loss (gain) |
7,063 |
|
141 |
|
|
(18,129 |
) |
60,572 |
|
Net income (loss) |
$ |
(1,067,553 |
) |
$ |
2,311,577 |
|
|
$ |
(2,586,636 |
) |
$ |
3,889,221 |
|
Other comprehensive income (loss) |
-$ |
1,672,774 |
|
-$ |
771,880 |
|
|
$ |
(99,289 |
) |
$ |
(3,074,428 |
) |
Comprehensive income (loss) |
$ |
(2,740,327 |
) |
$ |
1,539,697 |
|
|
$ |
(2,685,925 |
) |
$ |
814,793 |
|
Basic
net income per share |
($0.007) |
|
$ |
0.016 |
|
|
$ |
(0.017 |
) |
$ |
0.027 |
|
Diluted
net income per share |
($0.007) |
|
$ |
0.015 |
|
|
$ |
(0.016 |
) |
$ |
0.026 |
|
Basic
weighted-average number of shares outstanding |
150,610,282 |
|
142,721,198 |
|
|
149,338,229 |
|
141,827,544 |
|
Diluted
weighted-average number of shares outstanding |
159,229,299 |
|
152,821,304 |
|
|
158,801,398 |
|
149,566,812 |
|
Cash
dividends declared |
$0.000 |
|
$0.000 |
|
|
$0.000 |
|
$0.000 |
|
|
As at June 30, |
|
|
|
|
2020 |
2019 |
|
|
|
Cash |
$ |
4,884,278 |
|
$ |
3,890,665 |
|
|
|
|
Exploration & evaluation assets |
35,532,041 |
|
32,515,297 |
|
|
|
|
Investment in joint venture |
12,856,825 |
|
15,870,717 |
|
|
|
|
Other assets |
1,147,828 |
|
1,328,399 |
|
|
|
|
Total assets |
$ |
54,420,972 |
|
$ |
53,605,078 |
|
|
|
|
|
|
|
|
|
|
|
|
Total liabilities |
$ |
605,717 |
|
$ |
647,755 |
|
|
|
|
|
|
|
|
|
|
|
|
Shareholders' equity |
$ |
53,815,255 |
|
$ |
52,957,323 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The consolidated financial statements reflect
the equity method of accounting for Global Atomic’s interest in
BST. The Company’s share of net earnings and net assets are
disclosed in the notes to the financial statements.
Dasa Uranium Project, Niger
On April 15, 2020, Global Atomic announced the
results of a Preliminary Economic Assessment (“PEA”), followed by
the filing of an NI43-101 compliant technical report on May 20,
2020. The objective of the PEA was to assess the economic and
technical viability of a Phase 1 Mine Plan at the Dasa Project with
a Stand-Alone Processing Plant to produce yellowcake on the
property. The Phase 1 Mine Plan is limited to the Flank Zone,
comprising mostly Indicated Resources (88.5%) and resulting in an
initial 12-year mine schedule.
Summary project metrics for Phase 1 are as follows:
|
|
|
Summary Project Metrics @ US$35/lb U3O8 |
|
|
Project Economics |
|
|
Average Royalty rate (based on Mining Code sliding scale) |
% |
9.1% |
Average annual mine EBITDA(1) |
$M |
$93.8 |
After-tax NPV (8% discount rate) |
$M |
$ 211 |
After-tax IRR |
% |
26.6% |
Undiscounted after-tax cash flow (net of capex) |
$M |
$437 |
After-tax payback period |
Years |
4.00 |
Unit Operating Costs |
|
|
LOM average cash cost(2) |
$/lb U3O8 |
$16.72 |
AISC(2) |
$/lb U3O8 |
$18.39 |
Production Profile |
|
|
Phase 1 Schedule |
Years |
12 |
Total tonnes of mineralized material processed |
M Tonnes |
4.0 |
Peak tonnes per day mineralized material |
Tonnes/day |
1,124 |
Mill Head Grade |
Ppm |
5,396 |
Overall Mill Recovery |
% |
92% |
Total Lbs U3O8 processed |
Mlbs |
47.9 |
Total Lbs U3O8 recovered |
Mlbs |
44.1 |
Average annual Lbs U3O8 production |
Mlbs |
4.4 |
Peak annual Lbs U3O8 production |
Mlbs |
5.2 |
(1) |
Mine EBITDA is a non-IFRS measure, does not have a standardized
meaning prescribed by IFRS and may not be comparable to similar
terms and measures presented by other issuers. Mine EBITDA
comprises earnings before income taxes, interest expense (income)
and financing expense (income), amortization expense, and other
expenses including corporate costs. |
(2) |
Cash costs include all mining, processing, site G&A, and
royalty costs, as well as all head office and other off-site costs.
All-in sustain costs (“AISC”) include cash costs plus capital
expenditures forecast after the start of commercial
production. |
|
|
The economic analysis for the PEA was done via a
discounted cash flow (“DCF”) model based on the mining inventory
from the PEA Phase 1 Mine Plan and a price of US$35 per pound of
U3O8. Sensitivity analysis was carried out at $5 per pound price
intervals from $25 per pound to $50 per pound, as shown in the
table below. The DCF includes an assessment of the current tax
regime and royalty requirements in Niger. Net present value (“NPV”)
figures are calculated using a range of discount rates as shown.
The discount rate used for the base-case analysis is 8% (“NPV8”).
Cash flows are discounted to the start of first construction.
|
Economic sensitivity with varying uranium
prices(1) |
Uranium price (per pound) |
$25/lb |
$30/lb |
$35/lb |
$40/lb |
$45/lb |
$50/lb |
Before-tax NPV @ 8% |
$41 M |
$139 M |
$260 M |
$365 M |
$485 M |
$601 M |
After-tax NPV @ 8% |
$34 M |
$113 M |
$211 M |
$294 M |
$391 M |
$485 M |
After-tax IRR |
11.5% |
18.5% |
26.6% |
32.6% |
39.7% |
46.3% |
(1) |
Mine Stope Optimization (“MSO”) and schedule for all uranium price
sensitivities used the MSO base case model at $35 per pound
uranium |
Economic sensitivity with varying discount rates using
base-case uranium price $35/lb |
Discount rate (%) |
5% |
8% |
10% |
12% |
Before-tax NPV |
$341 M |
$260 M |
$215 M |
$177 M |
After-tax NPV |
$279 M |
$211 M |
$173 M |
$141 M |
|
|
|
|
|
Turkish Zinc JV, Iskenderun, Turkey
The following table summarizes comparative
operational metrics of the Iskenderun facility.
|
|
|
|
|
|
|
|
|
|
|
Three months ended June 30, |
|
|
Six months ended June 30, |
|
|
2020 |
|
2019 |
|
|
2020 |
|
2019 |
|
|
100% |
|
100% |
|
|
100% |
|
100% |
|
Exchange rate (TL/C$,
average) |
4.96 |
|
4.39 |
|
|
4.74 |
|
4.21 |
|
Exchange rate (C$/US$,
average) |
1.39 |
|
1.34 |
|
|
1.37 |
|
1.33 |
|
Exchange rate (TL/C$,
period-end) |
5.03 |
|
4.42 |
|
|
5.03 |
|
4.42 |
|
Exchange rate (C$/US$,
period-end) |
1.36 |
|
1.31 |
|
|
1.36 |
|
1.31 |
|
Average zinc price
(US$/LB.) |
0.89 |
|
1.25 |
|
|
0.93 |
|
1.24 |
|
EAFD processed (DMT) |
20,606 |
|
- |
|
|
39,026 |
|
4,644 |
|
Production (DMT) |
7,715 |
|
- |
|
|
14,161 |
|
1,291 |
|
Shipments (DMT) |
7,738 |
|
- |
|
|
15,752 |
|
1,553 |
|
Shipments (zinc content, 000 lb.) |
11,842 |
|
- |
|
|
24,345 |
|
2,271 |
|
|
|
|
|
|
|
|
|
|
|
The Turkish Zinc JV owns and operates an EAFD
processing plant in Iskenderun, Turkey. The plant processes EAFD
containing 25% to 30% zinc that is obtained from electric arc steel
mills and produces a zinc concentrate grading 68% to 70% zinc that
is then sold to zinc smelters.
Global Atomic holds a 49% interest in the
Turkish Zinc JV and, as such, the investment is accounted for using
the equity basis of accounting. Under this basis of accounting, the
Company’s share of the JV’s earnings is shown as a single line in
its income statement.
In 2018, the Turkish Zinc JV approved a capital
project to modernize and expand the Iskenderun plant. The project
began in 2018 and was completed in 2019. Prior to February 2019,
all work involved manufacturing of components for the new plant. In
January 2019, the Iskenderun plant shut down so that the site
reconstruction could begin. Commissioning of the new plant was
completed in August and production ramp up began in September. The
Iskenderun plant now has the capacity to process 110,000 tonnes
EAFD per annum, an increase from the 65,000 tonne per annum
previous capacity.
The following table summarizes comparative
results for 2020 and 2019 of the JV at 100%.
|
|
|
|
|
|
|
|
|
|
|
Three months ended June 30, |
|
|
Six months ended June 30, |
|
|
2020 |
|
2019 |
|
|
2020 |
|
2019 |
|
|
100% |
|
100% |
|
|
100% |
|
100% |
|
Net sales revenues |
$ |
8,810,299 |
|
$ |
171,612 |
|
|
$ |
17,094,569 |
|
$ |
5,356,688 |
|
Cost of sales |
7,281,400 |
|
1,376,112 |
|
|
14,430,707 |
|
5,324,139 |
|
Foreign
exchange loss (gain) |
(259,670 |
) |
(435,357 |
) |
|
(755,091 |
) |
(774,737 |
) |
EBITDA(1) |
$ |
1,788,569 |
|
$ |
(769,143 |
) |
|
$ |
3,418,953 |
|
$ |
807,286 |
|
Management fees & sales
commissions |
457,545 |
|
8,236 |
|
|
907,972 |
|
123,961 |
|
Depreciation |
712,625 |
|
20,964 |
|
|
1,610,037 |
|
48,884 |
|
Interest expense |
428,088 |
|
80,704 |
|
|
913,123 |
|
111,788 |
|
Foreign exchange loss on
debt |
1,242,187 |
|
- |
|
|
4,254,847 |
|
- |
|
Other expense (income) |
- |
|
(773 |
) |
|
- |
|
(7,103 |
) |
Tax
expense |
(310,914 |
) |
(8,243,080 |
) |
|
(992,997 |
) |
(10,937,637 |
) |
Net
income |
$ |
(740,963 |
) |
$ |
7,364,806 |
|
|
$ |
(3,274,030 |
) |
$ |
11,467,393 |
|
Global
Atomic's equity share |
$ |
(363,072 |
) |
$ |
3,608,755 |
|
|
$ |
(1,604,275 |
) |
$ |
5,619,023 |
|
|
|
|
|
|
|
|
|
|
|
Global
Atomic's share of EBITDA |
876,399 |
|
-376,880 |
|
|
1,675,287 |
|
395,570 |
|
(1) |
EBITDA is a non-IFRS measure, does not have a standardized meaning
prescribed by IFRS and may not be comparable to similar terms and
measures presented by other issuers. EBITDA comprises earnings
before income taxes, interest expense (income), foreign exchange
loss (gain) on debt, depreciation, management fees, sales
commissions, losses (gains) on sale of property, plant and
equipment and impairment charges. |
|
|
BST processed 39,026 tonnes EAFD in H1 2020,
which represents approximately 71% of plant capacity. 2019
production is not comparable, as the plant was shut down for
reconstruction after January 2019. Operations in the year earlier
period was subject to the ramp-up and adjustment of certain
equipment to optimize performance. COVID-19 had a negative impact
on the Turkish steel industry in Q2 2020 which is affecting the
availability of EAFD in Q3 and possibly Q4 as well. The current
outlook is that the plant will process about 65,000 tonnes EAFD in
2020.
The zinc content in concentrate shipments during
H1 2020 was 24.3 million pounds. Based on the current outlook for
2020, zinc content of concentrate shipments for the year is
expected to be 36.2 million pounds.
The total cost for the plant modernization and
expansion was approximately US $26.6 million, which was funded by
cash on hand, available credit lines from the BST JV’s Turkish bank
and loans from Befesa. At June 30, 2020, the Befesa loans totaled
US $16.85 million, bearing interest at Libor + 4.0% and mature
between May and December 2022. The bank loans totaled US $6.0
million at June 30, 2020 and bear interest at an average rate of
3.6% and mature in August/September 2020. The bank loans are
expected to roll over into new one-year bank loans. The Befesa
loans are expected to be partially repaid in 2020, with the
majority repaid by the end of 2021.
The loans are denominated in US dollars but
converted to Turkish Lira for functional accounting purposes. For
presentation purposes, the equity interests are then converted to
Canadian dollars. The foreign exchange loss for the 6 months to
June 30, 2020 related to the joint venture debt was C$4.3 million
($1.2 million for the three months ended June 30, 2020). This
foreign exchange loss is an unrealized loss, and largely relates to
the depreciation of the Turkish Lira relative to the US dollar from
5.95 at December 31, 2019 to 6.84 at June 30, 2020, as well as the
Canadian dollar relative to the US dollar, from $0.750 at December
31, 2019 to $.735 at June 30, 2020. In economic terms, all revenues
are received in US dollars and these will be used to pay down the
US denominated debt, so no real exchange gains/losses will be
realized in US dollar terms. The accounting exchange losses relate
to the debt are shown below EBITDA as a financing related cost.
The cash balance of the Turkish entities was
$2.6 million at June 30, 2020.
The Turkish entities qualified for an investment
tax credit incentive on the new plant, of which TL 77.2 million
(C$16.6 million) remains as a carry-forward balance at the end of
Q2 2020. Tax expense (income) shown in the income statement is a
non-cash deferred tax amount.
Overall, the Company’s share of EBITDA was $0.9
million in Q2 2020 ($1.8 million for H1 2020) and its share of net
loss was $0.4 million ($1.6 million for H1 2020), driven largely by
the unrealized foreign exchange loss recognized on the debt
balances.
QP Statement The scientific and technical
disclosures in this news release have been reviewed and approved by
Ronald S. Halas, P.Eng. and George A. Flach, P.Geo. who are
“qualified persons” under National Instrument 43-101 – Standards of
Disclosure for Mineral Properties.
About Global Atomic
Global Atomic Corporation
(www.globalatomiccorp.com) is a TSX listed company that provides a
unique combination of high-grade uranium mine development and
cash-flowing zinc concentrate production.
The Company’s Uranium Division includes four
deposits with the flagship project being the large, high-grade Dasa
Project, discovered in 2010 by Global Atomic geologists through
grassroots field exploration. The Company plans to submit its
Development Plan for the Phase 1 high grade underground mine to the
Ministry of Mines in the Republic of Niger together with a Mining
Permit application in Q3 2020.
Global Atomics’ Base Metals Division holds a 49%
interest in the Befesa Silvermet Turkey, S.L. (“BST”) Joint
Venture, which operates a new, state of the art processing
facility, located in Iskenderun, Turkey. The plant recovers zinc
from Electric Arc Furnace Dust (“EAFD”) to produce a high-grade
zinc oxide concentrate which is sold to zinc smelters around the
world. The Company’s joint venture partner, Befesa Zinc S.A.U.
(“Befesa”) listed on the Frankfurt exchange under ‘BFSA’, holds a
51% interest in and is the operator of the BST Joint Venture.
Befesa is a market leader in EAFD recycling, with approximately 50%
of the European EAFD market and facilities located throughout
Europe and Asia.
Key contacts:
Stephen G. RomanChairman, President and CEOTel: +1 (416)
368-3949Email: sgr@globalatomiccorp.com |
Bob TaitVP Investor RelationsTel: +1 (416) 558-3858Email:
bt@globalatomiccorp.com |
|
|
The information in this release may contain
forward-looking information under applicable securities laws.
Forward-looking information includes, but is not limited to,
statements with respect to completion of any financings; Global
Atomics’ development potential and timetable of its operations,
development and exploration assets; Global Atomics’ ability to
raise additional funds necessary; the future price of uranium; the
estimation of mineral reserves and resources; conclusions of
economic evaluation; the realization of mineral reserve estimates;
the timing and amount of estimated future production, development
and exploration; cost of future activities; capital and operating
expenditures; success of exploration activities; mining or
processing issues; currency exchange rates; government regulation
of mining operations; and environmental and permitting
risks. Generally, forward-looking statements can be
identified by the use of forward-looking terminology such as
“plans”, “is expected”, “estimates”, variations of such words
and phrases or statements that certain actions, events or
results “could”, “would”, “might”, “will be taken”, “will begin”,
“will include”, “are expected”, “occur” or “be achieved”. All
information contained in this news release, other than statements
of current or historical fact, is forward-looking
information. Statements of forward-looking information
are subject to known and unknown risks, uncertainties and other
factors that may cause the actual results, level of activity,
performance or achievements of Global Atomic to be materially
different from those expressed or implied by such forward-looking
statements, including but not limited to those risks described in
the annual information form of Global Atomic and in its public
documents filed on SEDAR from time to time.
Forward-looking statements are based on the
opinions and estimates of management at the date such statements
are made. Although management of Global Atomic has attempted
to identify important factors that could cause actual results to be
materially different from those forward-looking statements, there
may be other factors that cause results not to be as anticipated,
estimated or intended. There can be no assurance that such
statements will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such
statements. Accordingly, readers should not place undue
reliance upon forward-looking statements. Global Atomic does
not undertake to update any forward-looking statements, except in
accordance with applicable securities law. Readers should
also review the risks and uncertainties sections of Global Atomics’
annual and interim MD&As.
The Toronto Stock Exchange has not reviewed and
does not accept responsibility for the adequacy and accuracy of
this news release.
Global Atomic (TSX:GLO)
Graphique Historique de l'Action
De Oct 2024 à Nov 2024
Global Atomic (TSX:GLO)
Graphique Historique de l'Action
De Nov 2023 à Nov 2024