By completing the line early, the Windsor-Essex
region will benefit from increased reliability and resiliency,
supporting the region's clean energy future
CHATHAM-KENT, ON, Nov. 3, 2023
/PRNewswire/ - Today, Hydro One Networks Inc. (Hydro One) announced
that the Chatham to Lakeshore
Transmission Line is on track to be completed by the end of 2024, a
full year ahead of schedule. By completing the project early, the
company expects to reduce the cost of the project by approximately
$15 million. This estimated
$253 million investment will increase
the reliability and resiliency of the entire electricity network in
the Windsor-Essex region. The line will add approximately 400
megawatts of clean electricity to the region, which is enough power
to supply a city the size of Windsor, supporting economic growth in
agri-foods, clean energy supply chain and manufacturing.
The advancements on this project were made possible by:
Indigenous communities –As part of the company's ongoing
Reconciliation efforts, Hydro One has committed to building
new partnerships with Indigenous communities. Through this
approach, Hydro One and local Indigenous communities have and will
continue to collaborate on project planning and advancement. As
part of Hydro One's industry leading First Nations Equity Model,
five local First Nations will have the opportunity to invest in a
50 per cent equity ownership stake in the transmission line
component of the project.
Residents and affected property owners – Early and
meaningful engagement with the community allowed the company to
integrate local needs into the project planning. Measures such as
route refinements addressed community concerns, and the company was
able to achieve voluntary land right agreements with all affected
property owners along the corridor in a timely manner.
Provincial and municipal prioritization – As part of its
planning process, the Independent Electricity System Operator
(IESO) identified that energy demand in southwest Ontario is expected to quadruple by 2035. In
2019 and 2022, the Minister of Energy amended Hydro One's
transmission license to develop five new transmission lines to
support growth in southwest Ontario. This consolidated approach to
developing the new transmission lines has expedited development in
the region and allowed Hydro One the certainty to advance its
relationships with regulators, local communities, industry and
businesses. The company also advanced procurement activities to
mitigate against potential supply chain constraints.
"We're grateful for the collaboration with so many in the
planning, development and construction of this line. Working
together with Indigenous communities, municipalities, local
community members and organizations, landowners and farmers, and
our construction teams has supported very efficient delivery," said
Andrew Spencer, Executive Vice
President, Capital Portfolio Delivery, Hydro One. "The long-lasting
partnerships we've developed have enabled us to work in a
transparent and meaningful way and have been instrumental in
accelerating the pace of this transmission line project. We remain
focused on bringing tangible benefits through this line to the
community, including more jobs, economic growth and reliable
power."
"To power economic development, industries in our region need
access to reliable and resilient power" said Stephen
MacKenzie, President and Chief Executive Officer, Invest
WindsorEssex. "We're pleased to see the progress Hydro One has made
on this priority transmission project that will create new
opportunities and attract investments in
southwestern Ontario."
Construction began in spring 2023 on the 49-kilometre,
230-kilovolt line between Chatham Switching Station in the
Municipality of Chatham-Kent and
the new Lakeshore Transformer Station in the Municipality of
Lakeshore. This new transmission line is part of a network of
infrastructure projects across southwest Ontario and the next step of a multi-phase
approach that will unlock the electrification potential of
Ontario's economy. The line is now
anticipated to be in service by December
2024. For more information about the project, please visit
hydroone.com/chatham-to-lakeshore.
Hydro One Limited (TSX:
H)
Hydro One Limited, through its wholly-owned subsidiaries, is
Ontario's largest electricity
transmission and distribution provider with approximately 1.5
million valued customers, approximately $31.5 billion in assets as at December 31, 2022, and annual revenues in 2022 of
approximately $7.8 billion.
Our team of approximately 9,300 skilled and dedicated employees
proudly build and maintain a safe and reliable electricity system
which is essential to supporting strong and successful communities.
In 2022, Hydro One invested approximately $2.1 billion in its transmission and distribution
networks, and supported the economy through buying approximately
$1.9 billion of goods and
services.
We are committed to the communities where we live and work
through community investment, sustainability and diversity
initiatives. We are designated as a Sustainable Electricity Leader™
by Electricity Canada.
Hydro One Limited's common shares are listed on the TSX and
certain of Hydro One Inc.'s medium term notes are listed on the
NYSE. Additional information can be accessed at www.hydroone.com,
www.sedarplus.com or www.sec.gov.
Forward-Looking Statements and
Information:
This press release and the application and investment plan to
which it refers may contain "forward-looking information" within
the meaning of applicable securities laws. Words such as "expect",
"anticipate", "intend", "attempt", "may", "plan", "will", "can",
"believe", "seek", "estimate", and variations of such words and
similar expressions are intended to identify such forward-looking
information. These statements are not guarantees of future
performance or actions and involve assumptions and risks and
uncertainties that are difficult to predict. Therefore, actual
outcomes and results may differ materially from what is expressed,
implied or forecasted in such forward-looking information. Some of
the factors that could cause actual results or outcomes to differ
materially from the results expressed, implied or forecasted by
such forward-looking information, including some of the assumptions
used in making such statements, are discussed more fully in Hydro
One's filings with the securities regulatory authorities
in Canada, which are available on SEDAR+
at www.sedarplus.com. Hydro One does not intend, and it
disclaims any obligation, to update any forward-looking
information, except as required by law.